Skye Members of The Highland Council visited the Island of Raasay earlier this week to inspect progress on the Council's biggest current construction contract – a new £12 million ferry terminal to link the island with Sconser, Skye.
The terminal is being built at Churchton Bay and will provide a sheltered roll on roll off facility for the Caledonian MacBrayne car ferry, Loch Striven, and overnight berthage.
Work began in March, last year, and has been continuing on a 24-hour daily basis through the summer months by contractor Balfour Beatty Civil Engineering Ltd. Their workforce of 60 has increased the island population by 40%.
The new terminal is two kilometres from the existing terminal at Suisnish, which was constructed at the beginning of the 20th century for the transportation of iron ore from Raasay.
In the early 1970s Suisnish was enhanced to provide a slipway and berthing structure for the introduction of a new Island Class ferry direct to Sconser rather than Portree. Suisnish pier has now reached the end of it’s life, and is in a very poor state of repair suffering from both corrosion of the precast concrete sections and accelerated low water corrosion of the sheet piles and does not provide the shelter that a modern day roll on/roll off ferry service requires.
The pier is in such a poor state that contingency measures have been put in place to maintain the ferry service in case of collapse.
The new terminal is 150 meters long and will have a 40 metre dog leg to provide shelter. Councillors were told that good progress has been achieved on the casting of the underwater concrete foundations for the new pier structure, which is presently 70% complete. Placement of the pre-cast concrete "Lego Blocks" is also advancing with 40% in place and progressing seaward.
Drilling, blasting and dredging rock from the new inner harbour seabed is close to completion. Protective armouring work to the new terminal is progressing well, with regular deliveries of armour stone by sea from Kishorn Quarry.
Construction of a new 0.5km single track road serving the marine facility is progressing steadily.
Balfour Beatty is targeting the end of the year to complete the underwater elements of the project. However, this is subject to the vagaries of the upcoming autumn/winter weather.
Councillor John Laing, Chairman of the Transport Environmental and Community Services Committee, is delighted that the lifeline link between Skye and Raasay is being secured with such a major investment.
He said that the new ferry terminal will provide opportunities for Raasay to encourage visitors and improve the economy and sustainability of this remote island community.
(GK/KMcA)
Time and date
CONSTRUCTION DIRECTORY
Construction News
08/09/2009
Councillors Given Progress Report On Raasay Ferry Terminal
Latest Construction News
22/11/2024
SP Energy Networks has announced a major investment in Britain's electricity grid, selecting 19 preferred partners to deliver a £5.4bn supply chain programme. This significant initiative aims to meet increasing energy demand and facilitate future growth. The selected companies, many of which are ...
22/11/2024
Edinburgh City Council has launched a 12-week public consultation on a new strategy to revitalise Princes Street and the wider Waverley Valley. The vision aims to create a more vibrant and welcoming city centre, attracting investment, supporting businesses, and enhancing the visitor ...
22/11/2024
Ener-G Services Limited, a leading UK electrical engineering company specialising in renewables, marine, and offshore sectors, has expanded its operations in Westhill, Aberdeenshire. The company has leased Unit 6E at Kingshill Commercial Park, a 2,500 sq ft space, on a 5-year lease. This new ...
22/11/2024
A consortium of leading scientists, industry experts, and academic institutions has joined forces to accelerate Scotland's offshore wind sector. The £2.5 million project, led by the University of Edinburgh in collaboration with the University of Dundee and the Forth and Tay Offshore cluster (FTO), ...
22/11/2024
The Port of Aberdeen and Turner & Townsend were highly commended in the 'Engineering, Construction & Infrastructure Project of the Year' category at the APM Project Management Awards 2024. The award recognises excellence in project management and the positive impact on end-users. The £420 million ...
22/11/2024
South Lanarkshire Council's £10 million fire safety improvement programme has reached a significant milestone, with CCG (Scotland) completing installations in over 1,700 high-rise residences across East Kilbride and Cambuslang. The Glasgow-based construction firm has been working closely with the ...
22/11/2024
SSEN Transmission, a key player in the UK's energy transition, is set to further expand its workforce and move into a new, sustainable office space in Glasgow. The company's commitment to net zero and the increasing demand for green energy workers has led to significant growth, with the number of ...
22/11/2024
Scottish Water is investing in the upgrade of its Loch Eck clean water plant in Dunoon. The project involves replacing outdated dry well pumps with new, more reliable pumps capable of operating in both wet and dry conditions. WGM Engineering, an RSK Group company, has been tasked with carrying out ...
22/11/2024
Scottish Land & Estates has expressed serious concerns over the Scottish Government's Land Reform Bill, particularly the provisions that would allow ministers to force landowners to sell large estates in lots. Sarah-Jane Laing, the organisation's chief executive, stated that while the land-based ...
22/11/2024
Clark Contracts employees have once again shown their commitment to community engagement by volunteering at Silverburn Park in Leven. On Thursday, 21st November, 16 members of the team spent their day planting over 400 trees and carrying out other landscaping tasks. This latest volunteering effort ...