Work on the refurbishment contract in the Thurso Pedestrian Precinct has now been been completed apart from the laying of coloured bitumen over the tarmac area running through the centre of the precinct and a few other minor works.
The project which cost just over £370,000 was financed by the Highland Council's T.E.C and Planning & Development Services was designed by the councils Wick based engineering team who consulted with the Community Council and members of the public before finalising their plans.
The three Thurso ward elected members authorised a spend of £14,000 from their Ward Discretionary Budget for improvements not covered in the contract and this included the provision and erection of a new electric clock as a centre piece in the precinct, cleaning of the Façade above the shop fronts, refurbishment of the pavement in Durness Street and insertion of directional Caithness flagstones at the Western entrance to the precinct.
The contract carried out by John Gunn & Sons of Lybster was started in November 2008 and was initially scheduled to be completed in two phases with the second phase due to start in April 2009 however following a request from the local shopkeepers this date was brought forward to allow the completion of the work in one phase.
Councillor John Rosie, one of the three Thurso ward members, said that they were "delighted" with the refurbishment of the pedestrian area and they have had a very positive response from the traders and members of the public.
"The use of Caithness Flagstone has given the area a very attractive appearance whilst also creating local employment. The clock which was funded from the discretionary budget has made an attractive centre piece to the area and the whole scheme fits in well with the Caithness Horizons project in the old town hall."
Councillor Rosie also thanked all those who were involved in planning and construction of the project.
(GK/JM)
Construction News
14/05/2009
Thurso Pedestrian Precinct Completed

15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont