Talks are to resume later in an effort to resolve the Edinburgh tram dispute.
The row between a consortium including the German firm Bilfinger Berger and tram project managers Transport Initiatives Edinburgh (Tie) has resulted in work to lay tram tracks being put on hold.
The closure of the main shopping thoroughfare went ahead on Saturday as plans to re-route traffic to accommodate the closure of Princes Street were too far advanced to be halted.
Contractor consortium BSC claim they can't start work until an agreement has been reached on additional costs.
Tie said: "The project was given 48 hours notice before the commencement of works that the consortium, BSC, comprising Bilfinger Berger, Siemens and CAF, wished to impose unacceptable conditions as a requirement."
According to Tie these conditions could add £50m to £80m to the cost of the project.
Bilfinger Berger said utility works, including the routing of electricity, gas and water supplies, were fallen a year behind schedule, leading to an impact on costs.
Edinburgh Conservative MSP David McLetchie told BBC Radio's Good Morning Scotland programme: "This needs to be resolved this week, it needs to be resolved quickly.
"That should be possible in terms of the contract but I think that the council has to stand very firm on this and some of the figures that are being bandied about like wanting an extra £80m are frankly ridiculous.
"There can be no question of the council or the Scottish taxpayer, for that matter, being held to ransom on this."
Steve Cardownie, deputy leader of Edinburgh City Council, said: "The best scenario for everyone concerned would be for Bilfinger to drop their demands and commence with their work. There is an issue regarding our future working relationship with them because of what has happened.
"Unless it can be justified, no further money should be given to the company. We cannot stand by and let people plunder the public purse."
The closure of Princes Street was planned until the end of November although if no agreement can be reached it will reopen next week.
As the dispute continues of a tram the city of Edinburgh council have placed a mock-up of a tram for members of the public to view.
The mock-up was produced as part of the contract by the Spanish manufacturer, CAF, for necessary testing and approval by authorities.
Once up and running, there will be 27 trams in total. Each tram is 42.8m long and 2.65m wide with 7 articulated sections. There is a capacity for approximately 250 passengers on each, which is the equivalent to 2.5 double deck buses.
(GK/JM)
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
22/11/2024
SP Energy Networks has announced a major investment in Britain's electricity grid, selecting 19 preferred partners to deliver a £5.4bn supply chain programme. This significant initiative aims to meet increasing energy demand and facilitate future growth. The selected companies, many of which are ...
22/11/2024
Edinburgh City Council has launched a 12-week public consultation on a new strategy to revitalise Princes Street and the wider Waverley Valley. The vision aims to create a more vibrant and welcoming city centre, attracting investment, supporting businesses, and enhancing the visitor ...
22/11/2024
Ener-G Services Limited, a leading UK electrical engineering company specialising in renewables, marine, and offshore sectors, has expanded its operations in Westhill, Aberdeenshire. The company has leased Unit 6E at Kingshill Commercial Park, a 2,500 sq ft space, on a 5-year lease. This new ...
22/11/2024
A consortium of leading scientists, industry experts, and academic institutions has joined forces to accelerate Scotland's offshore wind sector. The £2.5 million project, led by the University of Edinburgh in collaboration with the University of Dundee and the Forth and Tay Offshore cluster (FTO), ...
22/11/2024
The Port of Aberdeen and Turner & Townsend were highly commended in the 'Engineering, Construction & Infrastructure Project of the Year' category at the APM Project Management Awards 2024. The award recognises excellence in project management and the positive impact on end-users. The £420 million ...
22/11/2024
South Lanarkshire Council's £10 million fire safety improvement programme has reached a significant milestone, with CCG (Scotland) completing installations in over 1,700 high-rise residences across East Kilbride and Cambuslang. The Glasgow-based construction firm has been working closely with the ...
22/11/2024
SSEN Transmission, a key player in the UK's energy transition, is set to further expand its workforce and move into a new, sustainable office space in Glasgow. The company's commitment to net zero and the increasing demand for green energy workers has led to significant growth, with the number of ...
22/11/2024
Scottish Water is investing in the upgrade of its Loch Eck clean water plant in Dunoon. The project involves replacing outdated dry well pumps with new, more reliable pumps capable of operating in both wet and dry conditions. WGM Engineering, an RSK Group company, has been tasked with carrying out ...
22/11/2024
Scottish Land & Estates has expressed serious concerns over the Scottish Government's Land Reform Bill, particularly the provisions that would allow ministers to force landowners to sell large estates in lots. Sarah-Jane Laing, the organisation's chief executive, stated that while the land-based ...
22/11/2024
Clark Contracts employees have once again shown their commitment to community engagement by volunteering at Silverburn Park in Leven. On Thursday, 21st November, 16 members of the team spent their day planting over 400 trees and carrying out other landscaping tasks. This latest volunteering effort ...