Subscribe to our Construction Newsfeed
Scotland Construction Directory
Search our 14,696 companies....

Construction News

23/02/2009

Talks To Resolve Tram Dispute To Continue

Talks are to resume later in an effort to resolve the Edinburgh tram dispute.

The row between a consortium including the German firm Bilfinger Berger and tram project managers Transport Initiatives Edinburgh (Tie) has resulted in work to lay tram tracks being put on hold.

The closure of the main shopping thoroughfare went ahead on Saturday as plans to re-route traffic to accommodate the closure of Princes Street were too far advanced to be halted.

Contractor consortium BSC claim they can't start work until an agreement has been reached on additional costs.

Tie said: "The project was given 48 hours notice before the commencement of works that the consortium, BSC, comprising Bilfinger Berger, Siemens and CAF, wished to impose unacceptable conditions as a requirement."

According to Tie these conditions could add £50m to £80m to the cost of the project.
-- Advertisement --
NorthernAsbestosServicesLtd



Bilfinger Berger said utility works, including the routing of electricity, gas and water supplies, were fallen a year behind schedule, leading to an impact on costs.

Edinburgh Conservative MSP David McLetchie told BBC Radio's Good Morning Scotland programme: "This needs to be resolved this week, it needs to be resolved quickly.

"That should be possible in terms of the contract but I think that the council has to stand very firm on this and some of the figures that are being bandied about like wanting an extra £80m are frankly ridiculous.

"There can be no question of the council or the Scottish taxpayer, for that matter, being held to ransom on this."

Steve Cardownie, deputy leader of Edinburgh City Council, said: "The best scenario for everyone concerned would be for Bilfinger to drop their demands and commence with their work. There is an issue regarding our future working relationship with them because of what has happened.

"Unless it can be justified, no further money should be given to the company. We cannot stand by and let people plunder the public purse."

The closure of Princes Street was planned until the end of November although if no agreement can be reached it will reopen next week.

As the dispute continues of a tram the city of Edinburgh council have placed a mock-up of a tram for members of the public to view.

The mock-up was produced as part of the contract by the Spanish manufacturer, CAF, for necessary testing and approval by authorities.

Once up and running, there will be 27 trams in total. Each tram is 42.8m long and 2.65m wide with 7 articulated sections. There is a capacity for approximately 250 passengers on each, which is the equivalent to 2.5 double deck buses.

(GK/JM)

Latest Construction News

16/04/2025
Construction work on the £5 million repair and refurbishment project at the Loch Centre in Tranent is scheduled to commence in June 2026. East Lothian Council has announced the anticipated start date for the significant upgrade to the well-used community facility. Under the current timetable, the
16/04/2025
A £636,000 project to install solar panels at the Gorbals water pumping station in South Ayrshire has been successfully completed. The scheme aims to provide a renewable energy source for pumping water to thousands of customers in the region. The project involved the installation of 793 solar pan
16/04/2025
A planning application has been lodged with Glasgow City Council by The JR Group, acting on behalf of Wheatley Group, for the construction of 29 much-needed affordable homes in the Baillieston area of the city. The proposed development on Caledonia Road will offer a mix of one- and two-bedroom apa
16/04/2025
Residents in 20 blocks of flats across Coatbridge are already experiencing the positive impacts of a recently completed, ambitious energy efficiency refurbishment project. The extensive construction work has delivered significant improvements to the properties, including the installation of cavity
16/04/2025
Ground investigation works are commencing this month at the proposed site for Orkney Islands Council’s Scapa Deep Water Quay at Deepdale in Holm. These initial investigations will be followed by marine-based site investigation works scheduled to begin in June. These works form part of the Pre-Con
16/04/2025
Construction work has been finalised on a significant new housing development in Motherwell town centre, delivering 42 newly built, highly energy-efficient flats alongside the respectful conversion of the B-Listed YMCA building into a further six homes. The project, part of North Lanarkshire Council
16/04/2025
The Construction Industry Training Board (CITB) has today released its year-end performance data for its New Entrant Support Team (NEST), revealing a significant increase in apprenticeship starts. During the financial year 2024-25, NEST supported 4,128 individuals in commencing apprenticeships, a su
16/04/2025
A water-powered mill in Angus is set to grind grain once again after receiving a record-breaking donation to fund its restoration. The National Trust for Scotland has announced that a long-time member of the conservation charity has gifted an incredible £2.4 million, one of the largest single dona
15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground. Drone footage has captured the progress of the project, which is a partnership between developer Artisa
15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond. The new connections system, anticip
RBT Underfloor LimitedMorris & Spottiswood LtdPlant Glazing LtdThe Water PointCRGP LimitedM&C McLean LtdStoneCleanScotland.co.ukDunedin Stone LtdSEEIT3DLogical Insulation Solutions Limited