Scotland's largest wastewater pumping station, located in Gailes near Irvine, is now partially powered by renewable energy, thanks to a newly completed £478,000 solar power scheme.
The Scottish Water site, in Gailes near Irvine, has seen 576 solarpanels installed on the ground and roof of the pumping station, generating around 0.27GWh of green energy each year.
It means that 7% of the power used by the pumping station – which returns treated waste water back to the sea – is now provided by solar energy, saving around 54 tonnes of carbon dioxide equivalent annually.
It is the first Scottish Water solar project to see the use of in-line mounted solar panels which were built into the structure of the pumping station roof while it was being replaced.
A range of biodiversity work is also in the process of being delivered at the site, including the planting of wildflowers and hedges, and installation of bat and hedgehog boxes.
The project has been led by Scottish Water Horizons, the public utility's commercial subsidiary, and delivered by R&A Group.
Scottish Water Horizons Project Manager Pauline Donelly said: "It is great to see this project completed and to have more solar energy now powering the processes all our customers rely on across Scotland. "In the last three years we've installed more solar energy than in the previous 12 combined, with capacity for 14.4 GWh installed compared to 9.6 GWh, and we continue to ramp up the pace and scale of our renewables programme as we respond to the climate crisis and focus on meeting our net zero targets by 2040."
Scottish Water Operations Team Leader Ian MacKinnon added: "Thepumping station at Gailes is the largest in Scotland and as such, is a big user of energy, helping to return treated waste water back to the natural environment.
"It is great that some of the carbon associated with this essential process is now being offset by renewable energy, helping us to meet our net zero ambitions."
Construction News
26/02/2025
Gailes Pumping Station Gets Solar Power Boost


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont