16/01/2025

A9 Dualling Programme To Proceed As Planned

Construction News Image
A new report commissioned by Transport Secretary Fiona Hyslop has recommended against rescheduling or accelerating the A9 Dualling Programme.

The report, which was requested following recommendations from the A9 Inquiry Petitions Committee, considered whether to prioritise sections of the programme based on safety records or potential disruption caused by road closures.

It concluded that maintaining the current schedule would achieve the overall completion of the dualling programme more quickly than any proposed rescheduling.

The report also recommends that the delivery plan is not accelerated, because of the likelihood that this would negatively impact procurement, construction, supply chains and increase disruption for road users.

The report highlights a potential opportunity to bring forward construction of the improved Dalnaspidal Junction through an advance works contract, subject to further assessment and the availability of funding. This would involve extending the existing Glen Garry dual carriageway north by approximately 1km.

The A9 Dualling Programme aims to upgrade 83 miles of the A9 between Perth and Inverness from single to dual carriageway.

-- Advertisement --
NorthernAsbestosServicesLtd

Cabinet Secretary for Transport Fiona Hyslop said: "This report considers proposals that the delivery plan for the A9 Dualling programme be rescheduled and/or accelerated. That plan was developed to balance market capacity, impacts on road users and challenging financial constraints and it provides much-needed certainty for road users, local communities and the construction industry on when works all along the A9 are expected.

"I appreciate that there are a range of views on how completion of the dualling programme should be achieved. I believe that the report demonstrates that the delivery plan is a robust and practical approach to undertaking this large programme of work in the years ahead, and the Scottish Government remains fully focused and committed to taking these projects forward as set out in that plan. This is supported by a Cabinet decision to prioritise completion of the A9 dualling programme within our available budgets.

"We are already making real progress in delivering on the plan. In the next few months, I expect to see main construction work start on the Tomatin to Moy project, publication of draft Orders for the Pass of Birnam to Tay Crossing project, contract award for the Tay Crossing to Ballinluig project and commencement of procurement for the Pitlochry to Killiecrankie project.

"In parallel with this, we expect to complete works on the £5m package of short term measures by the end of March this year, and the A9 Safety Group will continue to work together to explore any measures to positively influence driver behaviour to help reduce the numbers of people being injured or killed on the road.

"However, I have asked Transport Scotland to assess the potential to undertake an advance works contract for the Dalnaspidal Junction, as recommended in the report. I am wholly committed to progressing the A9 dualling programme, to listening to and keeping Parliament and local residents, businesses and communities informed of and engaged with our delivery plan. Where improvements can be made, within budget, which enhance delivery and/or the timetable, then we will make them."

Latest Construction News

16/01/2025

Robertson Property Ltd (RPL) has officially commenced ground clearance works on a major mixed-use regeneration project in Elgin, marking a significant step forward in revitalising the town centre. The project, a partnership between RPL, Moray Council, Moray Growth Deal, and UHI Moray, will see the ...
16/01/2025

A new report commissioned by Transport Secretary Fiona Hyslop has recommended against rescheduling or accelerating the A9 Dualling Programme. The report, which was requested following recommendations from the A9 Inquiry Petitions Committee, considered whether to prioritise sections of the ...
16/01/2025

Twenty-seven suppliers have been appointed to a new £814million Facilities Management Framework managed by procurement provider Pagabo, offering significant opportunities for Scottish construction firms. The framework, which will run until January 2029, will be used by public sector organisations ...
16/01/2025

Morris & Spottiswood, a leading construction services firm, is set to relocate its Glasgow office to EastWorks in Dalmarnock, joining a growing number of businesses moving to the Clyde Gateway regeneration area. The company, which reported its highest-ever turnover of £128 million in 2023, will ...
16/01/2025

NFRC Scotland is set to host a series of high-profile events and skills demonstrations throughout 2025, building on the success of numerous events held in 2024. These events, which attracted large numbers of individuals interested in traditional roofing skills, will provide hands-on experiences ...
16/01/2025

A new report commissioned by ScottishPower and WWF has highlighted the significant economic and health benefits of decarbonising UK homes. The report, titled 'Warmer Homes, Better Living: The Double Win for Health and Economics', was presented at a Parliamentary roundtable event hosted by the two ...
16/01/2025

Amey has received the Silver Award in its first submission to the Sustainable Facilities Management Index (SFMI). SFMI is a newly developed tool designed to assess and benchmark the ESG performance of Facilities Management providers. During an extensive audit process, Amey demonstrated ...
16/01/2025

Scottish Water will begin the second phase of essential sewer repair works in Rosebery Crescent, Edinburgh, on Monday 20th January 2024. This phase of the project involves repairing a damaged 450mm sewer pipe following the successful completion of upgrades to the waste water infrastructure at the ...
16/01/2025

Over £5 million is being invested in improving Dundee's school estate, with £3.5 million already spent in 2024/25 and a further £2.1 million proposed for 2025/26. The Children, Families and Communities Committee will review the latest report on the condition and suitability of nursery, primary, ...
16/01/2025

A collaborative effort between Balfour Beatty and The City of Edinburgh Council is underway to restore the historic North Bridge. The 125-year-old bridge, a Category A listed structure, is a vital transportation link in the city centre. The refurbishment project aims to preserve the bridge's ...
Morris & Spottiswood LtdRBT Underfloor LimitedHugh Simpson (Contractors) LtdTennants (Elgin) LtdCF Concrete PumpingPAUL Heat RecoveryAtlas Winch & Hoist Services LtdClaymore Training LimitedMulberry Kitchen DesignScaftec Ltd
Terms and Conditions
2025/01/16 19:13:23