A new report commissioned by Transport Secretary Fiona Hyslop has recommended against rescheduling or accelerating the A9 Dualling Programme.
The report, which was requested following recommendations from the A9 Inquiry Petitions Committee, considered whether to prioritise sections of the programme based on safety records or potential disruption caused by road closures.
It concluded that maintaining the current schedule would achieve the overall completion of the dualling programme more quickly than any proposed rescheduling.
The report also recommends that the delivery plan is not accelerated, because of the likelihood that this would negatively impact procurement, construction, supply chains and increase disruption for road users.
The report highlights a potential opportunity to bring forward construction of the improved Dalnaspidal Junction through an advance works contract, subject to further assessment and the availability of funding. This would involve extending the existing Glen Garry dual carriageway north by approximately 1km.
The A9 Dualling Programme aims to upgrade 83 miles of the A9 between Perth and Inverness from single to dual carriageway.
Cabinet Secretary for Transport Fiona Hyslop said: "This report considers proposals that the delivery plan for the A9 Dualling programme be rescheduled and/or accelerated. That plan was developed to balance market capacity, impacts on road users and challenging financial constraints and it provides much-needed certainty for road users, local communities and the construction industry on when works all along the A9 are expected.
"I appreciate that there are a range of views on how completion of the dualling programme should be achieved. I believe that the report demonstrates that the delivery plan is a robust and practical approach to undertaking this large programme of work in the years ahead, and the Scottish Government remains fully focused and committed to taking these projects forward as set out in that plan. This is supported by a Cabinet decision to prioritise completion of the A9 dualling programme within our available budgets.
"We are already making real progress in delivering on the plan. In the next few months, I expect to see main construction work start on the Tomatin to Moy project, publication of draft Orders for the Pass of Birnam to Tay Crossing project, contract award for the Tay Crossing to Ballinluig project and commencement of procurement for the Pitlochry to Killiecrankie project.
"In parallel with this, we expect to complete works on the £5m package of short term measures by the end of March this year, and the A9 Safety Group will continue to work together to explore any measures to positively influence driver behaviour to help reduce the numbers of people being injured or killed on the road.
"However, I have asked Transport Scotland to assess the potential to undertake an advance works contract for the Dalnaspidal Junction, as recommended in the report. I am wholly committed to progressing the A9 dualling programme, to listening to and keeping Parliament and local residents, businesses and communities informed of and engaged with our delivery plan. Where improvements can be made, within budget, which enhance delivery and/or the timetable, then we will make them."
Construction News
16/01/2025
A9 Dualling Programme To Proceed As Planned


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont