Major engineering works will stretch over a 16-week period, beginning from January, as part of upgrades to electrify the railway between East Kilbride and Glasgow.
To help deliver these vital improvements, from Saturday, January 25 until Sunday, May 18, no trains will run on the line between East Kilbride and Thornliebank stations while work is carried out to the track, bridges and overhead line equipment along the route.
This critical period in the electrification project will also see 22km of new overhead power cables installed and the lengthening of the double-track between East Kilbride and Hairmyres.
The existing track will also be lowered at locations near Busby, Clarkston and Giffnock stations so that overhead line equipment can be accommodated under some bridges on the route.
The £140m project will help to decarbonise rail services as well as improve reliability for passengers and has an overall completion date of December 2025.
By that stage, the investment in the line will see: Electrification of the railway from Glasgow to East Kilbride; A new station at East Kilbride; A new station with two platforms and accessible footbridge at Hairmyres; A new footbridge at Busby station; Improved access at Giffnock, with a new accessible footbridge; and a new station entrance at Clarkston.
The project is being delivered by Network Rail and is part of a Scottish Government investment in the line.
Gerry McQuade, Network Rail capital delivery director, said: "This programme of extended engineering works is a critical point in the delivery of the electrification of the East Kilbride line.
"Closing the railway is never an easy decision, but the engineering work taking place over these 16 weeks can only be done when no trains are running. This approach allows the completion of these major works in the most efficient, fastest way.
"We do appreciate the impact this will have both on those living closest to the line and to our passengers. We hope that by advising people three-months ahead of the work starting, this raises awareness and allows people the time to consider alternative travel arrangements."
Meanwhile, Mark Ilderton, ScotRail service delivery director, said: "The works being carried out by Network Rail are absolutely critical in the latest phase of the project to electrify the railway on the East Kilbride line.
"Unfortunately, during the 16-week closure, we will be unable to operate trains to and from East Kilbride and an alternate transport plan will help to make sure customers are still able to travel.
"In the coming weeks, we will communicate the plan through all our customer information channels, including where replacement buses will operate, and the other routes available for customers."
Damian Briody, Transport Scotland’s head of rail projects and technical services, added: "This announcement marks the build-up to the latest phase of progress on the East Kilbride electrification project.
"Whilst any disruption to passengers is unwelcome, we acknowledge the careful consideration which has gone into delivering the significant improvement works taking place during the closure.
"It is welcome that Network Rail and ScotRail have listened to passengers in planning these works and that they will continue to work closely together to ensure these passengers can make informed journey planning choices."
Throughout the works, no train services will run to East Kilbride. To help minimise disruption for passengers, a replacement bus service will be in place during this period.
At the same time as the 16-weeks of work finishes, in May 2025, the new Hairmyres station is scheduled to open to the public.
Information on the bus replacement service will be available in the coming weeks and customers are advised to check at www.scotrail.co.uk or via www.nationalrail.co.uk when planning their journeys over this period.
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
22/11/2024
SP Energy Networks has announced a major investment in Britain's electricity grid, selecting 19 preferred partners to deliver a £5.4bn supply chain programme. This significant initiative aims to meet increasing energy demand and facilitate future growth. The selected companies, many of which are ...
22/11/2024
Edinburgh City Council has launched a 12-week public consultation on a new strategy to revitalise Princes Street and the wider Waverley Valley. The vision aims to create a more vibrant and welcoming city centre, attracting investment, supporting businesses, and enhancing the visitor ...
22/11/2024
Ener-G Services Limited, a leading UK electrical engineering company specialising in renewables, marine, and offshore sectors, has expanded its operations in Westhill, Aberdeenshire. The company has leased Unit 6E at Kingshill Commercial Park, a 2,500 sq ft space, on a 5-year lease. This new ...
22/11/2024
A consortium of leading scientists, industry experts, and academic institutions has joined forces to accelerate Scotland's offshore wind sector. The £2.5 million project, led by the University of Edinburgh in collaboration with the University of Dundee and the Forth and Tay Offshore cluster (FTO), ...
22/11/2024
The Port of Aberdeen and Turner & Townsend were highly commended in the 'Engineering, Construction & Infrastructure Project of the Year' category at the APM Project Management Awards 2024. The award recognises excellence in project management and the positive impact on end-users. The £420 million ...
22/11/2024
South Lanarkshire Council's £10 million fire safety improvement programme has reached a significant milestone, with CCG (Scotland) completing installations in over 1,700 high-rise residences across East Kilbride and Cambuslang. The Glasgow-based construction firm has been working closely with the ...
22/11/2024
SSEN Transmission, a key player in the UK's energy transition, is set to further expand its workforce and move into a new, sustainable office space in Glasgow. The company's commitment to net zero and the increasing demand for green energy workers has led to significant growth, with the number of ...
22/11/2024
Scottish Water is investing in the upgrade of its Loch Eck clean water plant in Dunoon. The project involves replacing outdated dry well pumps with new, more reliable pumps capable of operating in both wet and dry conditions. WGM Engineering, an RSK Group company, has been tasked with carrying out ...
22/11/2024
Scottish Land & Estates has expressed serious concerns over the Scottish Government's Land Reform Bill, particularly the provisions that would allow ministers to force landowners to sell large estates in lots. Sarah-Jane Laing, the organisation's chief executive, stated that while the land-based ...
22/11/2024
Clark Contracts employees have once again shown their commitment to community engagement by volunteering at Silverburn Park in Leven. On Thursday, 21st November, 16 members of the team spent their day planting over 400 trees and carrying out other landscaping tasks. This latest volunteering effort ...