Scottish Gas Network (SGN) is making significant progress with the installation of a new hydrogen pipeline along the A904 Bo'ness Road in Grangemouth. This pipeline will play a crucial role in the company's Local Transmission System (LTS) Futures trial, which aims to demonstrate the feasibility of transporting hydrogen at scale across the UK.
So far, SGN's contractors, Advance Group, have successfully laid 600 meters of the 1.2km supply line. The project has involved navigating around complex existing infrastructure, including INEOS Gate 7, a busy access point for SGN's partner INEOS.
The next phase of the project involves crossing the Avon Bridge. To minimise disruption to the community, SGN will thread the new 3-inch pipeline through an old, unused 16-inch gas main. This approach will avoid the need for multiple excavations and road closures.
Once the pipeline is completed along Bo'ness Road, SGN will use horizontal directional drilling (HDD) to connect it to the transmission line for the hydrogen trial. The HDD process will allow the company to carefully avoid existing underground assets, and much of the pipeline needed for this phase is already prepared.
Construction News
15/10/2024
SGN Progresses Hydrogen Pipeline Installation in Grangemouth


16/04/2025
Construction work on the £5 million repair and refurbishment project at the Loch Centre in Tranent is scheduled to commence in June 2026.
East Lothian Council has announced the anticipated start date for the significant upgrade to the well-used community facility.
Under the current timetable, the

16/04/2025
A £636,000 project to install solar panels at the Gorbals water pumping station in South Ayrshire has been successfully completed.
The scheme aims to provide a renewable energy source for pumping water to thousands of customers in the region.
The project involved the installation of 793 solar pan

16/04/2025
A planning application has been lodged with Glasgow City Council by The JR Group, acting on behalf of Wheatley Group, for the construction of 29 much-needed affordable homes in the Baillieston area of the city.
The proposed development on Caledonia Road will offer a mix of one- and two-bedroom apa

16/04/2025
Residents in 20 blocks of flats across Coatbridge are already experiencing the positive impacts of a recently completed, ambitious energy efficiency refurbishment project.
The extensive construction work has delivered significant improvements to the properties, including the installation of cavity

16/04/2025
Ground investigation works are commencing this month at the proposed site for Orkney Islands Council’s Scapa Deep Water Quay at Deepdale in Holm.
These initial investigations will be followed by marine-based site investigation works scheduled to begin in June.
These works form part of the Pre-Con

16/04/2025
Construction work has been finalised on a significant new housing development in Motherwell town centre, delivering 42 newly built, highly energy-efficient flats alongside the respectful conversion of the B-Listed YMCA building into a further six homes. The project, part of North Lanarkshire Council

16/04/2025
The Construction Industry Training Board (CITB) has today released its year-end performance data for its New Entrant Support Team (NEST), revealing a significant increase in apprenticeship starts. During the financial year 2024-25, NEST supported 4,128 individuals in commencing apprenticeships, a su

16/04/2025
A water-powered mill in Angus is set to grind grain once again after receiving a record-breaking donation to fund its restoration.
The National Trust for Scotland has announced that a long-time member of the conservation charity has gifted an incredible £2.4 million, one of the largest single dona

15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip