Network Rail is preparing for the installation of a new active travel bridge to connect Methilhill and Cameron Bridge.
Over the next two weeks, Network Rail will crane the 129-metre structure into position, connecting the various active travel paths under construction as part of the Levenmouth Rail Link project.
That work is taking place from 2 to 16 September, with nine pre-fabricated sections, including bridge piers, staircase sections and four spans of bridge-deck being installed.
The installation had originally been planned ahead of the opening of the rail link but was delayed due to the company building the bridge going into administration this year.
Complex discussions with the administrator to release the part-built structure, as well as the need to source a new supplier, compounded that delay.
Now, with plans in place to complete the work, no parking and no waiting zones have been introduced on Poplar Road and Kirkland Walk until 16 September so that work vehicles can access the site.
Tommy McPake, senior programme manager, Network Rail said: "The team has worked hard to build the alternative walking route and then to deliver on the revised timeline to get the structure complete and site prepared for the bridge installation.
"While it was disappointing not to have the bridge in place ahead of the opening, it was due to circumstances beyond our control that could not have been foreseen.
"We hope the new bridge allows the community in Methilhill the opportunity to fully join in the excitement the return of the passenger service to Levenmouth has created. We're now very close to completing the connection to their local station which will enable them to easily access all of the opportunities the railway delivers.
"It is always exciting to see the crane lift the bridge into position to create what will be a very impressive looking structure that will support active travel in the area.
"We are grateful to the surrounding communities for their cooperation as we bring the bridge sections to site and look forward to completing the work in the coming weeks."
The bridge will be craned into position using a 750-tonne crane.
At its highest the bridge will sit approximately 8m above the river and will drop in height as it crosses the railway to connect into Cameron Bridge station.
Construction News
04/09/2024
Network Rail Unveils Levenmouth Rail Link Bridge Installation


24/04/2025
Offshore Solutions Group (OSG), a UK developer specialising in the floating offshore wind (FLOW) sector, has signed a two-year Exclusivity Agreement with Crown Estate Scotland for seabed areas in the Moray Firth.
This marks a significant step forward for OSG's groundbreaking FLOW-Park project.
Th

24/04/2025
Perth-based civil engineering firm I & H Brown has commenced construction on the first phase of a pioneering tyre recycling plant at the Port of Sunderland for new client, Wastefront.
This landmark project, known as Project Arrow, marks the UK's first facility of its kind, with the potential to re

24/04/2025
Hitachi Energy and SP Energy Networks (SPEN) have formalised their commitment to Scotland's energy transition by signing a Memorandum of Understanding (MoU) focused on deploying sustainable critical energy infrastructure.
The agreement will see Hitachi Energy supply switchgear from its innovative E

24/04/2025
Land surrounding the popular Inchgarth Reservoir in Aberdeen has undergone biodiversity improvements aimed at creating a better habitat for wading and farmland birds, while also protecting and enhancing the local ecosystem.
Scottish Water, the owner and operator of Inchgarth Reservoir, collaborated

24/04/2025
Prime Minister Rishi Sunak has today unveiled an initial £300 million funding package, allocated through Great British Energy ahead of the Spending Review, to bolster supply chains for the burgeoning offshore wind sector.
The funding will be made available through a grant application process, open

24/04/2025
Mountain bikers are once again able to enjoy the trails at Forestry and Land Scotland's (FLS) Carron Valley following the completion of significant upgrade works.
The site, renowned for offering some of the best official mountain biking trails in close proximity to Glasgow, has undergone resurfacin

24/04/2025
Aberdeen-headquartered Wood Group, a global leader in consulting and engineering, has been awarded two new engineering and procurement framework agreements worth $11 million (approx £8.3m) by TotalEnergies EP Ratawi Hub in Iraq.
The contracts form part of the Gas Growth Integrated Project (GGIP),

24/04/2025
Ayrshire Housing has appointed Scott Cunningham as its new Director of Assets and Compliance, a key role created to oversee a substantial £11.4 million investment in its housing stock over the next five years.
The housing association's recently launched Business Plan 2030 outlines this significant

24/04/2025
Hillcrest has announced the appointment of John Alexander as its new Chief Executive, with his tenure set to begin in early Summer 2025.
John Alexander currently serves as the Head of Local Authorities within SSEN Transmission and brings a wealth of experience from a diverse range of sectors at bot

24/04/2025
South Ayrshire Council's Thriving Communities team is continuing its vital work in supporting local community councils to develop Community-Led Action Plans across the region.
These action plans serve as a blueprint for each community, outlining a shared vision, identifying key local priorities, an