Shetland Islands Connected To GB Electricity Grid For First Time

Construction News Image
Scotland's Shetland Islands have been connected to the GB electricity grid for the first time, in what SSE Renewables described as 'monumental step forward' in the UK's journey toward a sustainable energy future.

This milestone comes with the completion of two major projects:

• the Viking Wind Farm, which is set to become the UK’s most productive onshore wind farm

• a 260-kilometer subsea transmission link that will transport the generated electricity from Shetland to the mainland

Featuring 103 Vestas turbines, the Viking Wind Farm has an installed capacity of 443MW and is expected to produce around 1.8 terawatt-hours (TWh) of renewable electricity annually. This output is sufficient to power nearly 500,000* homes each year. It will be the most productive onshore wind farm in the UK, marking a significant increase in the UK's clean energy capacity^.

The completion of the Viking Wind Farm and the subsea transmission link represents a £1 billion investment by SSE as part of our £20.5 billion commitment to UK clean energy infrastructure by 2027. This investment is one of the largest private commitments to clean energy the country has ever seen.

The subsea cable, a 260km high-voltage direct current (HVDC) link, will transport electricity between Shetland and the GB mainland for the first time. The cable was installed by SSEN Transmission in three campaigns, using specialist cable-laying vessel NKT Victoria. The cable connects a new converter station at Kergord in Shetland to a switching station at Noss Head on the Scottish mainland.

First Minister of Scotland, John Swinney, commented on the significance of the project, stating:

"The completion of these projects is a significant step in unlocking the green energy potential of the Shetland islands.

"These developments will not only aid us in our efforts to decarbonise our energy system, but help to stimulate sustainable economic growth in the local area.

"It is welcome that Scotland's onshore wind capacity continues to expand. This is a vital component of our mission to bring about a just transition to net zero."

This connection will enable clean energy generated in the Shetland Islands to flow to the rest of the UK, providing a new source of renewable energy and enhancing energy security. The link will also allow for energy to be supplied back to Shetland, ensuring a reliable supply of electricity for the islands.

-- Advertisement --
NorthernAsbestosServicesLtd

UK Energy Secretary, Ed Miliband, commented on the crucial role Viking will play in the UK's clean energy mission: "By Switching on Viking, hundreds of thousands of homes in the Shetlands and right across the country will benefit from cheap, homegrown energy, and this project has created jobs and growth for local communities.

"This shows why we need more developments like this to make Britain a clean energy superpower – and that is why we lifted the onshore wind farm ban in our first 72 hours in Government.

"This will be a crucial part of delivering our mission for clean power by 2030 – reducing our reliance on volatile fossil fuel markets, boosting our energy independence and protecting consumers."

The Viking Wind Farm and the HVDC link have already had a positive impact on the local economy and employment. During peak construction, the projects supported around 650 jobs and contributed £125 million to the Shetland economy. The ongoing operations of the Viking Wind Farm will support 35 permanent roles and are expected to contribute over £70 million to the local economy over the lifetime of the wind farm.

In addition to economic benefits, the Viking Community Fund, managed by community representatives, is the largest for a single renewable project in Great Britain, totalling over £72 million. This fund focuses on priority areas identified by Shetland residents, such as youth programs, housing and transportation, and has already supported nearly 200 local projects.

The Viking Wind Farm is a significant addition to the UK's renewable energy portfolio, increasing the combined onshore and offshore wind capacity to over 30GW, enough to meet the annual power needs of 26 million homes. This milestone underlines the UK's commitment to transitioning to a clean energy future, reducing carbon emissions by over 35 million tonnes annually.

Alistair Phillips-Davies, SSE Chief Executive, commented on this important achievement: "Delivery of both the Viking Wind Farm and Shetland HVDC Transmission link are big engineering achievements and together represent a major milestone on the UK's path to a clean energy system.

"Shetland and the wider North Sea have long supported the country's energy security and now they are playing a significant role in decarbonising our power system.

"But it has taken nearly two decades for these projects to move from concept to completion and if we are serious about delivering clean power by 2030 – less than 2,000 days away – we need to make it much easier and faster to build this kind of mission-critical infrastructure."

With the completion of these projects, the Shetland Islands are set to play a crucial role in the UK's renewable energy landscape, harnessing their unique position as the windiest region of the UK. The Viking Wind Farm is poised to be a leading contributor to the UK's wind energy production, driving the nation closer to its net-zero goals and fostering sustainable growth in local communities.

Dan McGrail, Renewable UK Chief Executive, emphasised the importance of the project: "When the Viking project was first conceived nearly twenty years ago, the UK's wind capacity stood at less than five gigawatts, and turbines were around 75% less efficient than they are now.

"Reaching the milestone of 30GW is a phenomenal achievement for the entire industry and further underlines the fact that wind is now the backbone of our future energy system, having generated a record 28% of our electricity last year."



*475,099 homes powered per annum based on annual GB average domestic household consumption base of 3.781MWh published by the Department of Business, Energy and Industrial Strategy (BEIS) as of November 2018, and projected total generation output by Viking Wind Farm of 1,796.35 GWh per annum.

^ Most productive UK onshore wind farm claim based on projected total average generation output by Viking Wind Farm of ~1.8TWh per annum and a comparison with the leading UK operational and in construction wind farms.


Latest Construction News

22/11/2024

SP Energy Networks has announced a major investment in Britain's electricity grid, selecting 19 preferred partners to deliver a £5.4bn supply chain programme. This significant initiative aims to meet increasing energy demand and facilitate future growth. The selected companies, many of which are ...
22/11/2024

Edinburgh City Council has launched a 12-week public consultation on a new strategy to revitalise Princes Street and the wider Waverley Valley. The vision aims to create a more vibrant and welcoming city centre, attracting investment, supporting businesses, and enhancing the visitor ...
22/11/2024

Ener-G Services Limited, a leading UK electrical engineering company specialising in renewables, marine, and offshore sectors, has expanded its operations in Westhill, Aberdeenshire. The company has leased Unit 6E at Kingshill Commercial Park, a 2,500 sq ft space, on a 5-year lease. This new ...
22/11/2024

A consortium of leading scientists, industry experts, and academic institutions has joined forces to accelerate Scotland's offshore wind sector. The £2.5 million project, led by the University of Edinburgh in collaboration with the University of Dundee and the Forth and Tay Offshore cluster (FTO), ...
22/11/2024

The Port of Aberdeen and Turner & Townsend were highly commended in the 'Engineering, Construction & Infrastructure Project of the Year' category at the APM Project Management Awards 2024. The award recognises excellence in project management and the positive impact on end-users. The £420 million ...
22/11/2024

South Lanarkshire Council's £10 million fire safety improvement programme has reached a significant milestone, with CCG (Scotland) completing installations in over 1,700 high-rise residences across East Kilbride and Cambuslang. The Glasgow-based construction firm has been working closely with the ...
22/11/2024

SSEN Transmission, a key player in the UK's energy transition, is set to further expand its workforce and move into a new, sustainable office space in Glasgow. The company's commitment to net zero and the increasing demand for green energy workers has led to significant growth, with the number of ...
22/11/2024

Scottish Water is investing in the upgrade of its Loch Eck clean water plant in Dunoon. The project involves replacing outdated dry well pumps with new, more reliable pumps capable of operating in both wet and dry conditions. WGM Engineering, an RSK Group company, has been tasked with carrying out ...
22/11/2024

Scottish Land & Estates has expressed serious concerns over the Scottish Government's Land Reform Bill, particularly the provisions that would allow ministers to force landowners to sell large estates in lots. Sarah-Jane Laing, the organisation's chief executive, stated that while the land-based ...
22/11/2024

Clark Contracts employees have once again shown their commitment to community engagement by volunteering at Silverburn Park in Leven. On Thursday, 21st November, 16 members of the team spent their day planting over 400 trees and carrying out other landscaping tasks. This latest volunteering effort ...
Morris & Spottiswood LtdRBT Underfloor LimitedToner Damp Proofing SuppliesNo HydroSEEIT3DCF Concrete PumpingMaccaferri LtdDiscount Kitchens and Bathrooms LtdShopfronts ScotlandJSJ Foam Insulation Ltd
Terms and Conditions
2024/11/23 08:55:21