SSEN Transmission has announced that it will take forward community and landowner proposals for the next stage of Kintore-Tealing overhead line project.
The energy firm has published a report on the public consultation it undertook in March and April 2024 on the proposed Kintore to Tealing 400kV project. This 'Report on Consultation' confirms the overhead line routes that are now being taken forward to the next stage of development and includes community and landowner proposals around Careston, Drumoak and Echt.
These stakeholder-led proposals are now being progressed in parallel with other overhead line route options that were consulted on in March and April 2024. Potential overhead line alignments along the full Kintore-Tealing route are being finalised ahead of the next round of public consultation next month.
Building on previous community and stakeholder-led changes
In December 2023, SSEN Transmission confirmed it was no longer progressing plans to develop a new substation at Fiddes in the Mearns, relocating this substation to a new site, Hurlie, in Fetteresso Forest, in close proximity to SSEN Transmission's existing Fetteresso substation.
At the same time, several changes to overhead line route proposals were set out, including in the sections between Kintore and the River Dee and between Brechin and Forfar.
These changes were as a direct result of ongoing and constructive engagement with local communities, landowners and wider stakeholders, demonstrating the effectiveness of SSEN Transmission's consultation.
Feedback on potential overhead line alignments will be sought from community members and other stakeholders at the next series of public consultation events for the project, which are scheduled to take place in September and October.
Calum Grant, Senior Development Project Manager for the Kintore-Tealing project, said: "As we work to deliver the critical national infrastructure that is required to deliver energy security and net zero, we've been undertaking one of the biggest public consultations that Scotland has ever seen.
"The feedback and local insight that we've received so far has been invaluable and has already led to major changes being made to our plans.
"As we publish our latest Report on Consultation, summarising feedback and decisions taken following the March and April engagement events, we can confirm we are taking community and landowner led alternative proposals around Careston, Drumoak and Echt to the next round of consultation, which will take place next month.
"We would encourage anyone who has an interest in the Kintore to Tealing project to come along to these events to provide their feedback, which will be carefully considered as we continue to refine our plans."
Public consultation on overhead line alignments will take place in the following venues between 2pm and 7pm unless stated otherwise. All consultation material, including maps of overhead line alignments, will be published and issued ahead of these events.
• 23 September – Tealing Village Hall, Tealing
• 24 September – Royal Hotel, Wallace Suite, Forfar
• 25 September – Memus Hall, Memus
• 26 September – Brechin City Hall, Brechin
• 30 September – Menmuir Hall, Menmuir
• 1 October – Kintore Public Hall, Kintore (1.30-6.30pm)
• 2 October – Echt Hall, Echt
• 3 October – Drumoak, Durris & Crathes Bowling Club, Drumoak
• 7 October – Drumlithie Village Hall, Drumlithie
• 8 October – Stonehaven Town Hall, Stonehaven
• 9 October – Dickson Hall, Laurencekirk
• 10 October - Durris Kirkton Hall, Durris
For more information on the Kintore-Tealing project, including the latest Report on Consultation, please visit www.ssen-transmission.co.uk/projects/project-map/kintore-tealing-400kv-ohl-connection/
Construction News
20/08/2024
Community And Landowner Proposals Accepted For Kintore-Tealing Project


16/04/2025
Construction work on the £5 million repair and refurbishment project at the Loch Centre in Tranent is scheduled to commence in June 2026.
East Lothian Council has announced the anticipated start date for the significant upgrade to the well-used community facility.
Under the current timetable, the

16/04/2025
A £636,000 project to install solar panels at the Gorbals water pumping station in South Ayrshire has been successfully completed.
The scheme aims to provide a renewable energy source for pumping water to thousands of customers in the region.
The project involved the installation of 793 solar pan

16/04/2025
A planning application has been lodged with Glasgow City Council by The JR Group, acting on behalf of Wheatley Group, for the construction of 29 much-needed affordable homes in the Baillieston area of the city.
The proposed development on Caledonia Road will offer a mix of one- and two-bedroom apa

16/04/2025
Residents in 20 blocks of flats across Coatbridge are already experiencing the positive impacts of a recently completed, ambitious energy efficiency refurbishment project.
The extensive construction work has delivered significant improvements to the properties, including the installation of cavity

16/04/2025
Ground investigation works are commencing this month at the proposed site for Orkney Islands Council’s Scapa Deep Water Quay at Deepdale in Holm.
These initial investigations will be followed by marine-based site investigation works scheduled to begin in June.
These works form part of the Pre-Con

16/04/2025
Construction work has been finalised on a significant new housing development in Motherwell town centre, delivering 42 newly built, highly energy-efficient flats alongside the respectful conversion of the B-Listed YMCA building into a further six homes. The project, part of North Lanarkshire Council

16/04/2025
The Construction Industry Training Board (CITB) has today released its year-end performance data for its New Entrant Support Team (NEST), revealing a significant increase in apprenticeship starts. During the financial year 2024-25, NEST supported 4,128 individuals in commencing apprenticeships, a su

16/04/2025
A water-powered mill in Angus is set to grind grain once again after receiving a record-breaking donation to fund its restoration.
The National Trust for Scotland has announced that a long-time member of the conservation charity has gifted an incredible £2.4 million, one of the largest single dona

15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip