Construction is set to begin on the UK's largest subsea connection project following the final approval on the costs of delivery by energy regulator, Ofgem.
The Eastern Green Link 2 (EGL2) project will see the delivery of a 525kV 2GW subsea connection between Peterhead in the north-east of Scotland and Drax on the east coast of England.
Ofgem's final decision on the project assessment for the 500km+ high voltage direct current (HVDC) connection is the key final approval in the regulatory process and allows construction to get underway later this year, with the connection due to be operational in 2029.
And in a separate development that underlines the progress being made on the project, Aberdeenshire Council has recently granted final planning approval for a new HVDC converter station to be built near Peterhead, with construction to begin at the site near Boddam later this year.
Delivered as a joint venture by National Grid and SSEN Transmission, EGL2 will include the longest HVDC subsea cable in the UK and is the UK's single largest electricity transmission project ever, providing enough electricity to power two million homes.
At a total expected nominal investment of around £4.3bn, it is the single largest-ever investment in electricity transmission infrastructure in Great Britain and one of the most significant, strategic investments in energy infrastructure the country has seen in recent years.
Contracts have now been awarded to deliver the project, including with Prysmian Group to supply around 1,000km of cable and with Hitachi Energy and BAM for the supply of converter stations at either end of the subsea cable.
EGL2 is part of SSEN Transmission's Pathway to 2030 programme, a £20bn investment to upgrade the electricity network in the north of Scotland to unlock the country's renewable energy resources in support of national net zero and energy security targets. It is also part of National Grid's The Great Grid Upgrade, 17 major infrastructure projects that will update the grid network boosting energy security, affordability and helping England and Wales become more self-sufficient.
Ricky Saez, EGL2 Project Director, commented: "Ofgem's decision to issue its final project assessment decision is a major milestone, and testament to the hard work of our project teams within SSEN Transmission and NGET in getting us to the stage where construction can begin later this year.
"We're also delighted that Aberdeenshire Council has granted approval for our HVDC converter station near Peterhead, and we'd like to thank the council for their efficient handling of our applications and for their recognition of the importance of the project which will support hundreds of skilled jobs during the construction phase and thousands more across the wider economy.
"Not only will EGL2 will play a major role in bolstering energy security and contributing to net zero targets, it will also provide a lasting legacy in local communities where our teams are already supporting local environmental initiatives that enhance community wellbeing.
"This is a commitment that will continue throughout the lifetime of the project and beyond, as we aim to be a positive force in the communities we operate."
Sandy Mactaggart, Director of Offshore Delivery for SSEN Transmission, said: "With HVDC technology set to play a leading role in the energy transition, the delivery of EGL2 will build on our significant expertise demonstrated through the success of our Caithness-Moray HVDC link, and the ongoing delivery of our Shetland HVDC link.
"We now look forward to working with our partners in NGET on construction and delivery of this important project, and on future projects including the proposed Eastern Green Link 3 where work is already underway to secure the supply chain."
Zac Richardson, Offshore Delivery Director for National Grid said: "Ofgem's funding decision is a major milestone for EGL2, the single largest-ever investment in a UK electricity transmission infrastructure project. We now look forward to delivering supply chain contracts, jobs, and skills, and helping to fulfil the government's ambition for the UK to be a clean energy superpower."
Jonathan Brearley, Ofgem CEO, said: "Ofgem is fully committed to supporting the government to meet its aims of getting clean power by 2030. Today's announcement is a further step in putting the regulatory systems and processes in place to speed up network regulation to achieve its aim.
"Accelerated Strategic Transmission Investment (ASTI) accelerates approval times for projects such as Eastern Green Link 2 (EGL2) by up to two years. However, streamlining the process does not mean blank cheques for developers as we are able to step in and make financial adjustments to maximise efficiency and consumer benefit."
Construction News
13/08/2024
Final Approval Granted For Eastern Green Link 2 Project


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont