Network Rail has announced a £3 million project at Rannoch Road Bridge in Killiecrankie.
The six-month programme, from Monday 02 September 2024 until March 2025, involves replacing the existing bridge deck to keep the railway running safely and reliably.
Engineers will also make alterations to the bridge abutments to accommodate a new concrete arch deck on the 128-year-old single-span structure, which sits over the Highland Main Line.
Representatives from Network Rail and principal contractor AmcoGiffen will set up a compound in land adjacent to Faskally Caravan Park to provide site offices and welfare facilities for those delivering the project.
To maintain an all-vehicle access route throughout, except over two weekends later in the year, a temporary bridge is being installed before the existing one is removed.
Susan Menmuir, scheme project manager, Network Rail, said: "Renewal work such as this is essential in allowing Network Rail to maintain and improve our assets across Scotland’s Railway.
"This is a significant piece of engineering and not without its challenges. Not only are we replacing the bridge deck, we’re also installing a temporary structure next to it and within a tight space. However, this allows vehicle access to be maintained for the community during delivery of much of the works.
"Replacing the 128-year-old bridge will ensure that work on this scale will not be required for at least another 120-years.
"We do appreciate the impact our activity will have on Killiecrankie village, particularly those living closest to the bridge and we will do all we can to minimise this where possible.
"We are grateful to the community for their patience while we complete this vital work."
Access at Rannoch Road will be maintained throughout the works except when the existing bridge is demolished and the new bridge is installed. This will be done over two consecutive weekends of extended engineering works, with no trains running on the line, from 30 November to 2 December and 7 December to 9 December.
Over both weekends, the road will be closed at the bridge, with traffic management measures in place including an all-vehicle diversion route. Further updates will be issued to advise the community and passengers in advance of this element of the works.
The project is part of a wide-ranging bridge modernisation programme aimed at protecting and improving Scotland’s Railway, with over £1.95 billion being invested to increase reliability and improve performance.
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
26/11/2024
Scottish Water has unveiled its largest-ever procurement initiative, aiming to modernise the nation's water and wastewater infrastructure while safeguarding the environment. The program, named Delivery Vehicle 4, is valued between £5 billion and £9 billion and is set to run from 2027 to 2033, with ...
26/11/2024
The City of Edinburgh Council has granted planning permission, subject to conditions, for the refurbishment of Calton Square, an office building currently occupied by Baillie Gifford until the end of December 2025. Promoted by Ardstone Capital on behalf of Manova Partners, the project aims to ...
26/11/2024
First Minister John Swinney, MSP for Perthshire North, praised the progress being made on the construction of the new Perth High School during a visit on Friday, 22 November. He was joined by Jim Fairlie, MSP for Perthshire South and Kinross-shire, alongside senior Perth and Kinross Councillors, ...
26/11/2024
A state-of-the-art playpark has officially opened at King George V Park in Bearsden, following the completion of a £100,000 refurbishment. Funded by a combination of East Dunbartonshire Council (EDC) Capital Funding and the Scottish Government’s Renewing Scotland’s Play Parks initiative, the ...
26/11/2024
Fife Council has launched a public consultation, inviting residents, businesses, and organizations to contribute ideas and propose sites for inclusion in the next Local Development Plan, known as Fife's Place Plan. The council is calling on community councils, landowners, and developers to share ...
26/11/2024
The Chief Executive of East Lothian Council has announced she is to retire in February 2025. Monica Patterson who has been Chief Executive for almost five years, has spent most of her professional career working in local government. Prior to joining East Lothian Council in 2010, she was Head of ...
25/11/2024
West of Scotland Housing Association (WSHA) and Connect Modular have jointly submitted a planning application to Glasgow City Council for the development of 33 affordable homes in Cowlairs. This project aligns with the wider Cowlairs Park regeneration scheme and the city's ambitious housing ...
25/11/2024
Arc-Tech (Scotland) has successfully completed a £6m Mechanical and Electrical (M&E) services package for the Lost Shore Surf Resort in Edinburgh. The state-of-the-art resort, which opened its doors earlier this month, features a range of amenities, including a wave pool, luxury lodges, and ...
25/11/2024
Scottish Water has successfully completed the construction of a groundbreaking hydro energy generation scheme at Whiteadder Reservoir in East Lothian. This innovative project, believed to be the first of its kind in Europe, will harness the power of water to offset a significant portion of the ...
25/11/2024
Work is set to commence on a £6.5 million project to upgrade the Double Dykes Gypsy/Traveller site near Perth. The initiative aims to replace outdated chalets with modern, energy-efficient accommodation and implement significant site improvements. Perth & Kinross Council secured £3.9 million from ...