Scottish Water has announced the successful completion of a £516,000 project to install over 886 solar panels at a waste water treatment works in East Ayrshire, supporting their pledge to reach net zero emissions by 2040.
The site, located in Cumnock, has been fitted out with a combination of ground and roof-mounted solar photovoltaic (PV) panels, helping to lower the carbon footprint of waste water services in the surrounding areas.
This carbon reducing technology will offset around one third of the electricity required to operate the facility, with the new PV system generating 0.4GWh of energy annually – the equivalent to the amount of energy needed to boil around 267,000 kettles. The scheme will also save around 97 tonnes of CO2 equivalent tonnes per year.
Ben Anderson, Specialist Graduate for Scottish Water Horizons, said: "Last week saw the earth's hottest day on record. Solar PV power is crucial in our fight against climate change and reducing our carbon footprint.
"The renewable energy generated from our projects will significantly contribute to Scottish Water's efforts to become a greener organisation and achieve our net zero carbon emissions target by 2040 and beyond."
The project was delivered by Scotland-based FES Group. Mandeep Singh, an apprentice electrician working for the company and who picked up Scotland's Net Zero Apprentice of the Year title at the recent Scottish Apprenticeship Awards.
He said: "I am very proud of how this solar project turned out. There were a few challenges along the way which we managed to resolve and has been a great development experience for me.
"I think the work we are doing partnership with Scottish Water Horizons is fantastic. It's helping create clean energy which is being used on site locally and reducing operational emissions."
Mechelle Barbour, Scottish Water Operations Team Leader for East and South Ayrshire, said: "Implementing sustainable solutions like this solar PV scheme benefits both the environment and our customers.
"Planned biodiversity measures for the site will also help to protect local species and habitats. By reducing emissions at this treatment facility, we are contributing to a greener, more sustainable community."
The energy needed to provide essential water and waste water services makes Scottish Water the largest single user of electricity in the country. This latest investment by Scottish Water Horizons, sees the site join a growing list of water and waste water treatment works which are now either self-sufficient or partly sufficient in their power requirements.
Construction News
05/08/2024
Scottish Water Completes Major Solar Installation Project


16/04/2025
Construction work on the £5 million repair and refurbishment project at the Loch Centre in Tranent is scheduled to commence in June 2026.
East Lothian Council has announced the anticipated start date for the significant upgrade to the well-used community facility.
Under the current timetable, the

16/04/2025
A £636,000 project to install solar panels at the Gorbals water pumping station in South Ayrshire has been successfully completed.
The scheme aims to provide a renewable energy source for pumping water to thousands of customers in the region.
The project involved the installation of 793 solar pan

16/04/2025
A planning application has been lodged with Glasgow City Council by The JR Group, acting on behalf of Wheatley Group, for the construction of 29 much-needed affordable homes in the Baillieston area of the city.
The proposed development on Caledonia Road will offer a mix of one- and two-bedroom apa

16/04/2025
Residents in 20 blocks of flats across Coatbridge are already experiencing the positive impacts of a recently completed, ambitious energy efficiency refurbishment project.
The extensive construction work has delivered significant improvements to the properties, including the installation of cavity

16/04/2025
Ground investigation works are commencing this month at the proposed site for Orkney Islands Council’s Scapa Deep Water Quay at Deepdale in Holm.
These initial investigations will be followed by marine-based site investigation works scheduled to begin in June.
These works form part of the Pre-Con

16/04/2025
Construction work has been finalised on a significant new housing development in Motherwell town centre, delivering 42 newly built, highly energy-efficient flats alongside the respectful conversion of the B-Listed YMCA building into a further six homes. The project, part of North Lanarkshire Council

16/04/2025
The Construction Industry Training Board (CITB) has today released its year-end performance data for its New Entrant Support Team (NEST), revealing a significant increase in apprenticeship starts. During the financial year 2024-25, NEST supported 4,128 individuals in commencing apprenticeships, a su

16/04/2025
A water-powered mill in Angus is set to grind grain once again after receiving a record-breaking donation to fund its restoration.
The National Trust for Scotland has announced that a long-time member of the conservation charity has gifted an incredible £2.4 million, one of the largest single dona

15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip