Work has begun to install the foundations of a new footbridge at the relocated Hairmyres station.
Network Rail and contractor AmcoGiffen will be carrying out piling works over the next two weeks, 11 to 25 July, as part of the East Kilbride Enhancements project.
Engineers will use a 58-tonne piling rig to drive 24 steel pile foundations to depths of between 2m to 5m to support the new footbridge and lifts.
When complete, the footbridge and lifts will provide step free access to the two platforms for passengers.
A double tracked section of the route will run between the platforms to help keep trains running on time.
Paul Reilly, Network Rail's senior programme manager for the station works, said: "The piling marks an important and exciting stage in the delivery of the project, as it’s a critical step in then allowing the installation of an accessible footbridge at the new Hairmyres station.
"Once the foundations are in place, we can start to focus on the construction of the lift towers and bridge deck, as well as the framework for the new station building which people will see emerging from the site over the coming months.
"When the construction of Hairmyres station is complete by summer 2025, it will provide a modern and accessible environment for passengers; whilst the electrification of the East Kilbride to Glasgow line will help encourage more people to switch from cars to rail and generate an even greener railway"
The station works are part of a wider £140 million Scottish Government investment to decarbonise passengers services across Scotland’s Railway.
The new Hairmyres station is located about 600m west of its current location.
As well as activity at Hairmyres, work at East Kilbride station to extend the existing platform by 51m finished in May. This allowed the buffer stop there to be relocated so that construction of the new building can take place.
The rebuild of two bridges on the route completed in the spring, with work underway on two more at Thornliebank Road and Westerton Lane near Busby station.
Over 160 steel foundations have been installed along the track to provide the base for new overhead masts which will support the overhead power cables.
The East Kilbride Enhancement project is scheduled to complete in December 2025.
Construction News
11/07/2024
Foundation Work Begins At New Hairmyres Station


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont