Work has begun to install the foundations of a new footbridge at the relocated Hairmyres station.
Network Rail and contractor AmcoGiffen will be carrying out piling works over the next two weeks, 11 to 25 July, as part of the East Kilbride Enhancements project.
Engineers will use a 58-tonne piling rig to drive 24 steel pile foundations to depths of between 2m to 5m to support the new footbridge and lifts.
When complete, the footbridge and lifts will provide step free access to the two platforms for passengers.
A double tracked section of the route will run between the platforms to help keep trains running on time.
Paul Reilly, Network Rail's senior programme manager for the station works, said: "The piling marks an important and exciting stage in the delivery of the project, as it’s a critical step in then allowing the installation of an accessible footbridge at the new Hairmyres station.
"Once the foundations are in place, we can start to focus on the construction of the lift towers and bridge deck, as well as the framework for the new station building which people will see emerging from the site over the coming months.
"When the construction of Hairmyres station is complete by summer 2025, it will provide a modern and accessible environment for passengers; whilst the electrification of the East Kilbride to Glasgow line will help encourage more people to switch from cars to rail and generate an even greener railway"
The station works are part of a wider £140 million Scottish Government investment to decarbonise passengers services across Scotland’s Railway.
The new Hairmyres station is located about 600m west of its current location.
As well as activity at Hairmyres, work at East Kilbride station to extend the existing platform by 51m finished in May. This allowed the buffer stop there to be relocated so that construction of the new building can take place.
The rebuild of two bridges on the route completed in the spring, with work underway on two more at Thornliebank Road and Westerton Lane near Busby station.
Over 160 steel foundations have been installed along the track to provide the base for new overhead masts which will support the overhead power cables.
The East Kilbride Enhancement project is scheduled to complete in December 2025.
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
22/11/2024
SP Energy Networks has announced a major investment in Britain's electricity grid, selecting 19 preferred partners to deliver a £5.4bn supply chain programme. This significant initiative aims to meet increasing energy demand and facilitate future growth. The selected companies, many of which are ...
22/11/2024
Edinburgh City Council has launched a 12-week public consultation on a new strategy to revitalise Princes Street and the wider Waverley Valley. The vision aims to create a more vibrant and welcoming city centre, attracting investment, supporting businesses, and enhancing the visitor ...
22/11/2024
Ener-G Services Limited, a leading UK electrical engineering company specialising in renewables, marine, and offshore sectors, has expanded its operations in Westhill, Aberdeenshire. The company has leased Unit 6E at Kingshill Commercial Park, a 2,500 sq ft space, on a 5-year lease. This new ...
22/11/2024
A consortium of leading scientists, industry experts, and academic institutions has joined forces to accelerate Scotland's offshore wind sector. The £2.5 million project, led by the University of Edinburgh in collaboration with the University of Dundee and the Forth and Tay Offshore cluster (FTO), ...
22/11/2024
The Port of Aberdeen and Turner & Townsend were highly commended in the 'Engineering, Construction & Infrastructure Project of the Year' category at the APM Project Management Awards 2024. The award recognises excellence in project management and the positive impact on end-users. The £420 million ...
22/11/2024
South Lanarkshire Council's £10 million fire safety improvement programme has reached a significant milestone, with CCG (Scotland) completing installations in over 1,700 high-rise residences across East Kilbride and Cambuslang. The Glasgow-based construction firm has been working closely with the ...
22/11/2024
SSEN Transmission, a key player in the UK's energy transition, is set to further expand its workforce and move into a new, sustainable office space in Glasgow. The company's commitment to net zero and the increasing demand for green energy workers has led to significant growth, with the number of ...
22/11/2024
Scottish Water is investing in the upgrade of its Loch Eck clean water plant in Dunoon. The project involves replacing outdated dry well pumps with new, more reliable pumps capable of operating in both wet and dry conditions. WGM Engineering, an RSK Group company, has been tasked with carrying out ...
22/11/2024
Scottish Land & Estates has expressed serious concerns over the Scottish Government's Land Reform Bill, particularly the provisions that would allow ministers to force landowners to sell large estates in lots. Sarah-Jane Laing, the organisation's chief executive, stated that while the land-based ...
22/11/2024
Clark Contracts employees have once again shown their commitment to community engagement by volunteering at Silverburn Park in Leven. On Thursday, 21st November, 16 members of the team spent their day planting over 400 trees and carrying out other landscaping tasks. This latest volunteering effort ...