A new Construction Quality Improvement Collaborative (CQIC) survey has revealed that Contractor Design Portions remains an issue that needs improvement.
The survey, issued by CQIC which was established in early 2023 to further embed and promote a quality culture across Scotland’s construction sector, sought the views on what needs to change to improve the CDP process.
In total there were 380 respondents from a wide spread of organisation types and sizes covering a variety of professions and occupations from across the construction sector.
Over the last 25-30 years there has been an increasing tendency to use CDP for construction projects where a range of specialist sub-contractors are required to contribute towards the overall design and construction of major buildings. However, many believe the CDP system is being used inappropriately and too late in the process.
The top line results from the survey show:
• 45% thought the term CDP was not clearly defined and understood
• 91% of respondents agreed that appointment of the CDP contractor impacts positively upon design and design quality
• 95% of respondents agreed that early or very early appointment of the CDP contractor would have a positive impact on design and design quality
• 78% are of the opinion that the scope of CDP design work should be agreed before RIBA Stage 3
• 90% stated that CDP design work should be carried out by RIBA Stage 4
• The barriers to change in use of CDP are lowest price procurement, procurement routes and design consultancy fees
Colin Campbell, Associate Director at the Scottish Futures Trust, who co-chairs and provides the secretariat for the CQIC work, said: "This has been a phenomenal response to the survey, showing just how passionately industry feels about the issue. We will now begin sifting through all the submissions with a focus to engage further with industry later this year, with the aim to produce best practice guidance for the sector to follow."
Iain Kent, Commercial Director of Morgan Sindall Construction and co-chair of the CQIC, which is the Quality Working Group within the Construction Leadership Forum’s Transformation Action Plan, noted: "The use of CDP has grown over the years and it can have an impact on the quality of the design and construction. Whilst there is undoubtedly a need for CDP in specialist areas of construction, the level of response to this survey shows change is needed that will benefit the whole of the construction industry."
Time and date
CONSTRUCTION DIRECTORY
Construction News
26/06/2024
Survey Reveals Issues Remain On Contractor Design Portions
Latest Construction News
26/11/2024
Scottish Water has unveiled its largest-ever procurement initiative, aiming to modernise the nation's water and wastewater infrastructure while safeguarding the environment. The program, named Delivery Vehicle 4, is valued between £5 billion and £9 billion and is set to run from 2027 to 2033, with ...
26/11/2024
The City of Edinburgh Council has granted planning permission, subject to conditions, for the refurbishment of Calton Square, an office building currently occupied by Baillie Gifford until the end of December 2025. Promoted by Ardstone Capital on behalf of Manova Partners, the project aims to ...
26/11/2024
First Minister John Swinney, MSP for Perthshire North, praised the progress being made on the construction of the new Perth High School during a visit on Friday, 22 November. He was joined by Jim Fairlie, MSP for Perthshire South and Kinross-shire, alongside senior Perth and Kinross Councillors, ...
26/11/2024
A state-of-the-art playpark has officially opened at King George V Park in Bearsden, following the completion of a £100,000 refurbishment. Funded by a combination of East Dunbartonshire Council (EDC) Capital Funding and the Scottish Government’s Renewing Scotland’s Play Parks initiative, the ...
26/11/2024
Fife Council has launched a public consultation, inviting residents, businesses, and organizations to contribute ideas and propose sites for inclusion in the next Local Development Plan, known as Fife's Place Plan. The council is calling on community councils, landowners, and developers to share ...
26/11/2024
The Chief Executive of East Lothian Council has announced she is to retire in February 2025. Monica Patterson who has been Chief Executive for almost five years, has spent most of her professional career working in local government. Prior to joining East Lothian Council in 2010, she was Head of ...
25/11/2024
West of Scotland Housing Association (WSHA) and Connect Modular have jointly submitted a planning application to Glasgow City Council for the development of 33 affordable homes in Cowlairs. This project aligns with the wider Cowlairs Park regeneration scheme and the city's ambitious housing ...
25/11/2024
Arc-Tech (Scotland) has successfully completed a £6m Mechanical and Electrical (M&E) services package for the Lost Shore Surf Resort in Edinburgh. The state-of-the-art resort, which opened its doors earlier this month, features a range of amenities, including a wave pool, luxury lodges, and ...
25/11/2024
Scottish Water has successfully completed the construction of a groundbreaking hydro energy generation scheme at Whiteadder Reservoir in East Lothian. This innovative project, believed to be the first of its kind in Europe, will harness the power of water to offset a significant portion of the ...
25/11/2024
Work is set to commence on a £6.5 million project to upgrade the Double Dykes Gypsy/Traveller site near Perth. The initiative aims to replace outdated chalets with modern, energy-efficient accommodation and implement significant site improvements. Perth & Kinross Council secured £3.9 million from ...