South Ayrshire Council has reported that it remains on target to successfully complete its programme of safety works at the former Station Hotel in Ayr on Monday, 17 June, 2024.
The building was extensively damaged in a fire in September 2023. The Council's Building Standards team instructed urgent safety works to be carried out under Section 29 of the Building (Scotland) Act 2003.
The former Station Hotel is a Grade B listed building and there are strict criteria limiting any demolition. Section 29 of the Building (Scotland) Act 2003 enables the demolition of a listed building where that building presents an urgent risk to safety or adjoining property.
These safety works have addressed the risk of collapsing chimneys, fire damaged supporting beams and crumbling walls and have led to the removal of the southern section of the building, the tower and the first three bays of the northern section.
The remaining part of the building has been assessed and although it's in a poor condition, it's not an immediate safety risk, so it cannot be removed under Section 29 of the Building (Scotland) Act 2003. Therefore, a Dangerous Building Notice has been issued in accordance with Section 30 of the Building (Scotland) Act 2003, which means the owners of the remainder of the building must make it safe.
Network Rail is already looking to prevent unauthorised access, prop the newly formed gable, secure the canopies which run across the platform and the tracks and remove or repair any loose materials.
This means that when the Council's safety works finish on 17 June, ScotRail will be able to reintroduce electric services between Ayr and Glasgow and, due to the extended period of closure, work with Network Rail to complete all activities required to re-establish services south of Ayr, working towards the full return of services later in July.
Mike Newall, Chief Executive of South Ayrshire Council said: "For over 10 years, we have been actively working to protect the public and the critical infrastructure of the railway.
"Our responsibilities have increased significantly since the devastating fire last year, but throughout we have maintained and developed strong working ties with our key stakeholders, particularly Network Rail and ScotRail.
"We issued the Dangerous Building Notice to the owners in advance of our safety works finishing and Network Rail has begun the works to satisfy the requirements of that Notice and facilitate the re-opening of the railway station.
"We continue to pursue Mr Ung for sums due in respect of the safety works, and decrees that have been awarded in the Council's favour in both the Sheriff Court and Court of Session. Debt recovery action is being taken in both the United Kingdom and in Malaysia."
Construction News
10/06/2024
Ayr Station Hotel Safety Works Near Completion


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont