Glasgow CC Welcomes Progress Of George Square Project

Construction News Image
Glasgow City Council has welcomed the progress being made on the programme for the George Square project, with confirmation that work will begin on-site in January 2025, with the main work to begin next April.

The first phase of this work will be the creation of a site compound and hoarding of George Square in January 2025, once the Christmas 2024 decorations come down. Between January - March 2025, 11 bronze statues will be removed and transported to an adequate storage facility.

The statues will be conserved and restored between July 2025 - July 2027, before being returned to their new location on the completThe public realm works on George Square and surrounding Avenues will start in April 2025, with phased completion up to April 2027 (with George Square delivered by August 2026).

The works in George Square will deliver high-quality stone throughout the Square; informal 'play' areas for children in sensory gardens in the eastern areas; a water feature; a raised lawn platform; bespoke sheltered seating; and feature lighting.

In terms of the new design for George Square, the design for the eastern part of the Square responds to its institutional character and the formality of the City Chambers and of the Cenotaph; and a further raised green area will be created in front of the Cenotaph. The western, non-institutional part of the Square will feature an area for cafes to spill out, as well as a generous paved area for events, including a water feature.

-- Advertisement --
NorthernAsbestosServicesLtd

The final design of George Square - now ready to progress to public procurement - was informed by significant public engagement and stakeholder consultation in 2022 and 2023. The next phase of activity in the George square project will be the preparation of tender documents for the various contracts required to deliver the works.

The George Square works are being delivered alongside those for the surrounding Avenues over two phases. The first phase will see works in George Square, John Street, North Hanover Street, George Street (between Nelson Mandela Place and Montrose Street) Cochrane Street, St Vincent Place and Hanover Street, and Miller Street commencing construction in 2025 with completion due in 2027. The second phase of construction - at St Vincent Street (from Buchanan Street to Newton Street) and George Street (from Montrose Street to High Street) will follow.

The scheme is part of the wider £115million Avenues project - a network of new, attractive, accessible, safe, sustainable and easily-maintained routes throughout the city centre that are people-focused, encourage active travel and are more attractive to residents, workers, visitors and investors. The Avenues project is funded through the Glasgow City Region City Deal, with the funding provided by the Scottish and UK Governments.

The final cost for the project will be determined through the procurement process.George Gillespie, Executive Director of Neighbourhoods, Regeneration and Sustainability at Glasgow City Council, said: "The confirmation of the timetable of works for the George Square project is clearly a significant stage in what will be a transformational scheme for Glasgow's foremost civic space. A great deal of consultation led to the final design for the Square and reflects the ambition to build a space that respects the place the Square holds in our history and meets the future needs of the city and its visitors."

The Glasgow City Region City Deal will see both governments provide £500million of funding for infrastructure projects.

Latest Construction News

03/12/2024

ScottishPower has offered a lifeline to workers facing potential redundancy at Ineos's Grangemouth refinery and construction firm ISG. The energy company is preparing to recruit 1,000 people next year and is actively seeking skilled workers from these industries. Recognising the skillset overlap ...
03/12/2024

Temporis Capital, Clarke Energy, and Trina Storage have announced the start of construction on a 50MW/100MWh Battery Energy Storage System (BESS) in Boat of Garten, Scottish Highlands. Clarke Energy will act as the EPC contractor, while Trina Storage will supply the BESS system, including its ...
03/12/2024

Scottish and Southern Electricity Networks (SSEN) has launched a new initiative, 'Demand Diversification', to explore innovative ways of managing peak electricity demand in the north of Scotland. The project involves real-world trials and simulations to assess the potential of demand-side response ...
03/12/2024

Procast Group, a leading principal contractor, has acquired Glasgow-based building surveying and cost consultancy firm JC+P Property and Construction Consultants in a six-figure deal. The acquisition aims to strengthen both businesses and facilitate future growth. JC+P's six-strong team will ...
03/12/2024

The Chartered Institute of Building (CIOB) is set to launch its third global survey to investigate the mental health challenges faced by construction workers. The previous study, published in 2020, revealed alarming statistics, including: • 97% of construction workers experiencing high levels of ...
03/12/2024

A public consultation is underway for the development of a new secondary school in Hazlehead. The consultation will provide an opportunity for the community to view proposed designs for the new Hazlehead Academy Campus and offer feedback. Aberdeen City Councillor Martin Greig, convener of the ...
02/12/2024

East Ayrshire Council has announced a £166 million investment plan to deliver hundreds of new and affordable homes across the region. The strategic plan, approved by local councillors, aims to address housing needs and improve the lives of residents. The council has already made significant ...
02/12/2024

Cala Homes (East) has secured a £4.8 million contract to build 21 new social rent homes on behalf of Fife Council. The new homes, a mix of two-bedroom cottage flats and terraced houses, will be built at the Inchcolm Green development in Aberdour. Construction is set to begin in January 2025 and is ...
02/12/2024

Thomas Johnstone Ltd, a renowned fit-out contractor, has been selected to undertake a multi-million-pound refurbishment project at Crieff Hydro Hotel. The project will involve creating a new day-to-night bar, upgrading dining areas, and introducing a stylish speakeasy bar. Despite the extensive ...
02/12/2024

A new extension to Sciennes Primary School in Edinburgh has been officially certified as a Passivhaus building, setting a new standard for energy-efficient school design in the city. The project has also been recognised with three prestigious industry awards. The £3.2 million extension, designed ...
RBT Underfloor LimitedMorris & Spottiswood LtdA.G.S Steel Erectors LtdRBT Underfloor LimitedJGasJohnston Oils LimitedThe Big Block Co LtdFour Seasons Scotland Design & Build LtdEuro-Fab (Scotland)Gas Call Services Ltd
Terms and Conditions
2024/12/03 17:54:38