Network Rail has announced the successful completion of a 13-month long project to strengthen the 160-year-old Camps viaduct.
Located in an ancient woodland, the 11-span viaduct serves as a crucial artery for passengers travelling between Glasgow and Motherwell by train.
Along with Story Contracting, Network Rail began work to extend the lifespan of the historic landmark, which towers 35m above the River Clyde, in spring 2023.
Engineers completed 1370 repairs, replaced more than over 10,000 rivets and added 65 tonnes of new steel during these extensive strengthening and refurbishment works.
Essential scour protection works were also carried out to both the east and west river banks and this included the installation of over 800 tonnes of rock armour.
Mark Wilson, senior programme manager, Network Rail, said: "It's great to see the work at Camps viaduct complete. The £6m project has helped strengthen the structure for years to come but it's so much more than that.
"There has been a lot of planning to make sure the project was carried out efficiently while causing as little disruption to the people who live nearby and minimising disturbance to the surrounding land, riverbed, and the wildlife that make the woodland their home.
"Work of this kind will not be needed for at least another 25 years. With a stronger bridge, we can help keep communities connected by continuing to run a safe and reliable railway."
Steven McVey, senior project manager, Story Contracting, said: "The Story project team at Camps Viaduct are proud to have delivered the refurbishment works to this important structure on behalf of Network Rail, alongside our key supply chain partners.
"This project not only demonstrates our commitment to enhancing Scotland's Railway infrastructure but also highlights our team's dedication to quality and safety in all aspects of engineering."
To protect the surrounding environment from dust or pollution, including the River Clyde which flows underneath, work on the structure was completed while the viaduct was encapsulated and sealed.
Pontoons were built in the river so that the scour and masonry repair work could be done most safely and to limit disruption during work on the riverbed and underwater.
Protecting the ancient woodland has involved the installation of Cellweb®TRP, which are mats laid on the ground at the start of the project to help protect the roots of the trees, the soil and other fauna.
The project team sought advice from experts including ecologists, park rangers and ornithologists, and, acting on best recommendations, installed netting on the structure to deter birds from nesting during the work.
For specific protected species in the area, an alternative nesting basket which was winched up to the tallest tree in the woodland was provided by tree climbing teams.
Construction News
22/05/2024
160-Year-Old Camps Viaduct Restoration Project Complete


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont