Network Rail has reached a crucial phase in its programme of accessibility works at Anniesland Station in Glasgow,
Ahead of the installation of two new lifts, engineers have been making space and strengthening the foundations for the lift shafts by sheet piling – driving huge sheets of steel into the ground.
The next step will see the lift towers installed at street level on Great Western Road over two weekends in June.
To enable the safe installation of the lift towers, Great Western Road at Anniesland Cross will be reduced to one westbound lane.
Liam Sumpter, Managing Director for Scotland's Railway, said: "We're moving towards a crucial time in the Anniesland Access for All project, which will bring easy, step-free access closer to reality for passengers.
"With the preparatory work almost complete, ready for the installation of the lift towers, I'd like to thank passengers, residents and those travelling through Anniesland Cross for their understanding, patience, and acceptance during the disruption they have faced and of the need to work so close to their homes.
"I look forward to seeing the completion of this work, which will provide a fully accessible station at Anniesland and more comfortable journeys for all – including those with limited mobility, those carrying heavy luggage or those with pushchairs."
The improvements are part of the Access for All (AfA) programme and are designed to help create a brighter and more accessible entrance to the station.
Network Rail has worked with Glasgow City Council throughout the project and to ensure the traffic and pedestrian management system is as safe as possible.
Councillor Angus Millar, City Convener for Transport, Glasgow City Council, said: "It's great to see work going ahead to improve accessibility at Anniesland Station and I am very pleased council staff have been giving practical support to this project.
"Encouraging more sustainable travel choices is right at the heart of our plans for transport in Glasgow.
"The new lifts will make it much easier to reach the station and will help more people in the Anniesland area to connect with Glasgow's rail network by walking, wheeling and cycling."
Fabricated at M&S Engineering in Dumfries and Galloway, the lift towers will stand 9 metres tall and will be lifted in using a 230-tonne crane.
Steel walkways will connect the towers to the existing station platforms to make it easier to use the station for those with mobility difficulties, people travelling with bicycles, pushchairs or heavy luggage.
Construction News
17/05/2024
'Crucial Phase' Of Anniesland Station Accessibility Works


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont