Network Rail has announced the launch of a major programme of repair works on the 123-year-old Glenfinnan viaduct is underway.
Working alongside principal contractor AmcoGiffen, Network Rail engineers have set up a compound at the foot of the landmark, which sits 100ft above the River Finnan on the West Highland Line, 17 miles from Fort William.
The £3.4 million works is part of Network Rail's ongoing maintenance programme and will help futureproof the viaduct.
The project is expected to take just under 12 months to complete and will see engineers assessing the condition and strength of the viaduct and making improvements beneath the track to keep the stone ballast in place.
Laura Craig, scheme project manager, Network Rail, said: "The main works to the viaduct will be concrete repairs. We'll also be doing some repairs to the pier that sits in the River Finnan.
"Years of planning have gone into this project. The work will not have a massive visual impact on the way the viaduct looks and that's very deliberate, with it being grade A listed.
"We won't be scaffolding the structure at all but in the coming weeks, you'll start to see the rope access technicians on the viaduct as they begin work."
There will be no disruption to rail services during the work on the structure.
Ahead of work commencing, a community drop-in event was held in Glenfinnan, allowing those who live near the viaduct the opportunity to ask questions directly to the project team.
Laura added: "We want to thank all who came to the drop-in event. It was great to catch up with locals to answer questions and chat about our plans.
"We know it's a much-loved viaduct and is, of course, the longest concrete viaduct in Scotland, spanning 1000ft.
"It's a bucket list job for our team to work on and we'll be sharing as much information and as many updates as we can throughout the project."
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
22/11/2024
SP Energy Networks has announced a major investment in Britain's electricity grid, selecting 19 preferred partners to deliver a £5.4bn supply chain programme. This significant initiative aims to meet increasing energy demand and facilitate future growth. The selected companies, many of which are ...
22/11/2024
Edinburgh City Council has launched a 12-week public consultation on a new strategy to revitalise Princes Street and the wider Waverley Valley. The vision aims to create a more vibrant and welcoming city centre, attracting investment, supporting businesses, and enhancing the visitor ...
22/11/2024
Ener-G Services Limited, a leading UK electrical engineering company specialising in renewables, marine, and offshore sectors, has expanded its operations in Westhill, Aberdeenshire. The company has leased Unit 6E at Kingshill Commercial Park, a 2,500 sq ft space, on a 5-year lease. This new ...
22/11/2024
A consortium of leading scientists, industry experts, and academic institutions has joined forces to accelerate Scotland's offshore wind sector. The £2.5 million project, led by the University of Edinburgh in collaboration with the University of Dundee and the Forth and Tay Offshore cluster (FTO), ...
22/11/2024
The Port of Aberdeen and Turner & Townsend were highly commended in the 'Engineering, Construction & Infrastructure Project of the Year' category at the APM Project Management Awards 2024. The award recognises excellence in project management and the positive impact on end-users. The £420 million ...
22/11/2024
South Lanarkshire Council's £10 million fire safety improvement programme has reached a significant milestone, with CCG (Scotland) completing installations in over 1,700 high-rise residences across East Kilbride and Cambuslang. The Glasgow-based construction firm has been working closely with the ...
22/11/2024
SSEN Transmission, a key player in the UK's energy transition, is set to further expand its workforce and move into a new, sustainable office space in Glasgow. The company's commitment to net zero and the increasing demand for green energy workers has led to significant growth, with the number of ...
22/11/2024
Scottish Water is investing in the upgrade of its Loch Eck clean water plant in Dunoon. The project involves replacing outdated dry well pumps with new, more reliable pumps capable of operating in both wet and dry conditions. WGM Engineering, an RSK Group company, has been tasked with carrying out ...
22/11/2024
Scottish Land & Estates has expressed serious concerns over the Scottish Government's Land Reform Bill, particularly the provisions that would allow ministers to force landowners to sell large estates in lots. Sarah-Jane Laing, the organisation's chief executive, stated that while the land-based ...
22/11/2024
Clark Contracts employees have once again shown their commitment to community engagement by volunteering at Silverburn Park in Leven. On Thursday, 21st November, 16 members of the team spent their day planting over 400 trees and carrying out other landscaping tasks. This latest volunteering effort ...