Scottish Water has announced the successful completion of a major technological transformation of Glasgow's Victorian era Partick Pumping Station.
Built some 120 years ago, the pumping station remains a key part of the city's waste water infrastructure and still serves 170,000 people. It is one of more than 30 pumping stations Scottish Water is upgrading by connecting to a cloud-based digital app that provides alerts and data-driven insights.
The investment at Partick is enabling the publicly owned utility to improve the operability, efficiency and reliability of the pumping station, reduce energy consumption and help the company reach its Net Zero targets while continuing to protect the local environment, including the rivers Kelvin and Clyde.
The pumping station is a key part of the waste water infrastructure in Greater Glasgow because two major sewers come into it and it lifts flows from those sewers to a gravity sewer which takes waste water to Dalmuir Waste Water Treatment Works (WWTW) in Clydebank for treatment.
The installation of the state-of-the-art 'smart hardware' at Partick, which will help view and manage pumping performance better, is in sharp contrast to how the pumping station was operated when it opened in 1904 with the use of old steam-driven pumps.
When opened by the Glasgow Corporation, the ornate B listed Renaissance red sandstone building in Dumbarton Road used three powerful steam-driven pumps.
These lifted sewage from the lower levels and propelled it through the city's sewer system. Boilers generated the steam needed to power the pumps and, in addition to all the machinery that was required, the station housed a set of stables for horses, which were used to help with moving coal to heat water and create the steam for the pumps.
As technology advanced, the steam pumps were replaced in the 1960s by electric pumps and, in 2012, Scottish Water completed a major £2.3m upgrade of the pumping station to help protect the local environment and improve its efficiency.
Now Scottish Water has ambitions to improve its asset management strategy, reduce its energy consumption and reach its Net Zero targets by 2040 and, following the success of similar work at WWTWs, they are applying a similar solution to sewage pumping stations to help deliver these improvements.
A new year-long £2m initiative covering the 32 largest waste water pumping stations is progressing to connect the facilities, and their asset and equipment data, to the Xylem Avensor cloud portal. The new technology aims to improve instant, live streaming visibility of what's happening on-site 24/7.
It will enable:
• Improving service as operators have much better visibility of how the station is performing.
• Quicker response for teams when situations do arise.
• Proactive responses, helping to reduce the risk of pumps breakdown and Environmental Pollution Incidents, making energy savings and reducing on our carbon footprint and net zero emissions.
• Monitoring of energy consumption helping Operations to keep their pumps running efficiently.
Nathan Wield, Scottish Water's wastewater operations manager, said: "We have installed this smart hardware at Partick Pumping Station to be able to view and manage pumping performance better, which is a long way from the old steam driven pumps that were originally installed in the station at the start of the 20th century.
"It's 120 years old this year and this latest investment will be hugely important because it'll enable us to monitor and better understand how one of our largest, critical assets is performing. Being able to see pump performance, energy usage, weather information and well levels, gives us confidence in managing our assets, and means we're able to respond to emerging risks more quickly.
"Being able to do this 24-7 and remotely, by connecting this data to the cloud, means we have full visibility of the pumps performance data, which enables us to make better investment decisions and spend customers' money more cost-effectively so we really do win on all fronts.
"Using this new technology at Partick means we are able to react to alerts on pump performance proactively, mitigating the risk of failures and, in turn, reducing the risk of a pollution spill, so the investment there is very significant."
Scottish Water is committed to transforming the way it operates and invests and its Routemap to Net Zero sets out a journey to net zero emissions by 2040. The company's aim is to reduce the amount of energy it consumes to deliver its vital water and wastewater services.
Construction News
02/05/2024
Major Technological Upgrade Complete At Partick Pumping Station


16/04/2025
Construction work on the £5 million repair and refurbishment project at the Loch Centre in Tranent is scheduled to commence in June 2026.
East Lothian Council has announced the anticipated start date for the significant upgrade to the well-used community facility.
Under the current timetable, the

16/04/2025
A £636,000 project to install solar panels at the Gorbals water pumping station in South Ayrshire has been successfully completed.
The scheme aims to provide a renewable energy source for pumping water to thousands of customers in the region.
The project involved the installation of 793 solar pan

16/04/2025
A planning application has been lodged with Glasgow City Council by The JR Group, acting on behalf of Wheatley Group, for the construction of 29 much-needed affordable homes in the Baillieston area of the city.
The proposed development on Caledonia Road will offer a mix of one- and two-bedroom apa

16/04/2025
Residents in 20 blocks of flats across Coatbridge are already experiencing the positive impacts of a recently completed, ambitious energy efficiency refurbishment project.
The extensive construction work has delivered significant improvements to the properties, including the installation of cavity

16/04/2025
Ground investigation works are commencing this month at the proposed site for Orkney Islands Council’s Scapa Deep Water Quay at Deepdale in Holm.
These initial investigations will be followed by marine-based site investigation works scheduled to begin in June.
These works form part of the Pre-Con

16/04/2025
Construction work has been finalised on a significant new housing development in Motherwell town centre, delivering 42 newly built, highly energy-efficient flats alongside the respectful conversion of the B-Listed YMCA building into a further six homes. The project, part of North Lanarkshire Council

16/04/2025
The Construction Industry Training Board (CITB) has today released its year-end performance data for its New Entrant Support Team (NEST), revealing a significant increase in apprenticeship starts. During the financial year 2024-25, NEST supported 4,128 individuals in commencing apprenticeships, a su

16/04/2025
A water-powered mill in Angus is set to grind grain once again after receiving a record-breaking donation to fund its restoration.
The National Trust for Scotland has announced that a long-time member of the conservation charity has gifted an incredible £2.4 million, one of the largest single dona

15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip