30/04/2024

Work Progresses On £48m Millport Flood Protection Scheme

Construction News Image
North Ayrshire Council has announced the successful completion of the offshore works element of the ongoing £48 million Flood Protection Scheme on the Isle of Cumbrae.

As climate change is expected to increase the frequency and severity of flooding across Scotland, the Millport Flood Protection Scheme – which work started on last spring – will help improve the safety and security of the island's residents against increased coastal flooding threats.

The completed offshore works include:

• The installation of an offshore rock armour breakwater, which has created a calm area of water. This part of the works is essential to allow a proposed marina - which is an Ayrshire Growth Deal project - to be constructed in the future
-- Advertisement --
NorthernAsbestosServicesLtd



• Foreshore rockworks at Clyde Street and at Crichton Street/Clyde Street and

• The creation of concrete revetments - slopes that absorb wave energy to help reduce coastal erosion - at Kelburn Street, Millburn Street and Clyde Street on Cumbrae.

Thomas Reaney, North Ayrshire Council's Head of Service for Neighbourhood Services, said: "It is encouraging to see this project being delivered so effectively with our partners.

"Schemes like these reduce the chances of flooding and coastal erosion while protecting communities."

Onshore works around Glasgow Street are progressing well and include plans for: new benches being put in place; kerbing; surfacing works; jetty repairs – including the jetty near the famous Crocodile Rock; promenade wall repairs and repainting.

The main contractor for the flood protection work in Millport is Van Oord UK Ltd, with support from subsidiary Mackley Civil Engineering.

This project is being managed on behalf of the Council by global professional services business Turner & Townsend, with support from the Principal Designer Royal Haskoning DHV.

The offshore elements were completed in February, within the predicted planning scope, and mark a major milestone in enhancing the overall resilience of the island. Significant progress is also being made with the onshore works.

The Scottish Government is contributing 80 per cent towards the overall costs of the scheme, with the Council meeting the rest.

Latest Construction News

16/04/2025
Construction work on the £5 million repair and refurbishment project at the Loch Centre in Tranent is scheduled to commence in June 2026. East Lothian Council has announced the anticipated start date for the significant upgrade to the well-used community facility. Under the current timetable, the
16/04/2025
A £636,000 project to install solar panels at the Gorbals water pumping station in South Ayrshire has been successfully completed. The scheme aims to provide a renewable energy source for pumping water to thousands of customers in the region. The project involved the installation of 793 solar pan
16/04/2025
A planning application has been lodged with Glasgow City Council by The JR Group, acting on behalf of Wheatley Group, for the construction of 29 much-needed affordable homes in the Baillieston area of the city. The proposed development on Caledonia Road will offer a mix of one- and two-bedroom apa
16/04/2025
Residents in 20 blocks of flats across Coatbridge are already experiencing the positive impacts of a recently completed, ambitious energy efficiency refurbishment project. The extensive construction work has delivered significant improvements to the properties, including the installation of cavity
16/04/2025
Ground investigation works are commencing this month at the proposed site for Orkney Islands Council’s Scapa Deep Water Quay at Deepdale in Holm. These initial investigations will be followed by marine-based site investigation works scheduled to begin in June. These works form part of the Pre-Con
16/04/2025
Construction work has been finalised on a significant new housing development in Motherwell town centre, delivering 42 newly built, highly energy-efficient flats alongside the respectful conversion of the B-Listed YMCA building into a further six homes. The project, part of North Lanarkshire Council
16/04/2025
The Construction Industry Training Board (CITB) has today released its year-end performance data for its New Entrant Support Team (NEST), revealing a significant increase in apprenticeship starts. During the financial year 2024-25, NEST supported 4,128 individuals in commencing apprenticeships, a su
16/04/2025
A water-powered mill in Angus is set to grind grain once again after receiving a record-breaking donation to fund its restoration. The National Trust for Scotland has announced that a long-time member of the conservation charity has gifted an incredible £2.4 million, one of the largest single dona
15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground. Drone footage has captured the progress of the project, which is a partnership between developer Artisa
15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond. The new connections system, anticip
RBT Underfloor LimitedMorris & Spottiswood LtdACCON UK LtdWalshy JoinerySips Eco Panel Systems LtdDMC VisualsContainexHutton Stone Co LtdQuickFix Plumbing & HeatingScaffolding & Access Supplies Ltd