SSE Renewables has welcomed the latest milestone in the ongoing development of what will become the world's largest offshore wind farm, with the installation of the second unmanned High Voltage Direct Current (HVDC) platform at Dogger Bank.
Installed by Saipem, the substation is the second of three platforms, each supplied by Aibel, to be installed at Dogger Bank offshore wind farm, which is being constructed in three phases known as A, B, and C, each with a capacity of 1.2GW.
The platform was installed 130km from the UK coastline at Dogger Bank B by Saipem using the Saipem 7000 vessel and features a Hitachi Energy HVDC system developed to transmit power more efficiently than traditional AC systems. The platform will receive 1.2GW of AC power generated by the 95 offshore wind turbines of Dogger Bank B, before converting it to DC for transmission to an onshore converter station located near Beverley in East Riding of Yorkshire.
The first platform was installed at Dogger Bank A in April 2023, representing the first time this technology has been used in offshore wind in the UK. All three platforms will be controlled from shore and feature a lean design, resulting in a 70% weight reduction per MW compared to previous platform designs.
Mads Andersen, CEO and President of Aibel said: "At Aibel, we recognize that our success is not measured solely by the completion of projects but by the lasting impact we leave on the industry. With this major on-time delivery of Dogger Bank B, we mark another important milestone in Aibel's transition towards a greener industry. This achievement exemplifies the power of collaboration and reflects the enduring partnerships we have cultivated with industry leaders SSE Renewables, Equinor, Vårgrønn, and our esteemed partner, Hitachi Energy."
Andreas Berthou, Head of HVDC at Hitachi Energy's Grid Integration business, said: "The urgent energy transition requires strong collaboration, new business models, and global standards. We are proud to be the technology partner for the Dogger Bank Wind Farm project, with HVDC being the force multiplier for the clean energy transition, increasing access to an energy system that is more sustainable, flexible and secure. This is another significant milestone in securing the UK's future energy needs, made possible by foresighted partners such as SSE Renewables, Equinor and Vårgrønn that have made the UK a leader in the transition to clean power."
Measuring 75 meters long x 45 meters wide x 39 meters high, the platform utilises a four-legged steel jacket foundation structure designed and fabricated by Saipem in water depths of around 28 meters.
Gianalberto Secchi, COO of Saipem's Offshore Wind Business Line, commented: "We are proud to have contributed to the achievement of this important milestone for the groundbreaking Dogger Bank project, which reaffirms Saipem's leadership in the offshore industry and our expertise in supporting Clients in the development of offshore wind farms as a key resource for the energy transition worldwide."
Construction News
19/04/2024
Second HVDC Platform Installed At Dogger Bank Wind Farm


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont