04/03/2024

Confirmation Of Grid Connection Location For Dogger Bank D

Construction News Image
SSE Renewables and Equinor have announcd the confirmation of a grid connection location from the Electricity System Operator (ESO) for a proposed fourth phase of the world's largest offshore wind farm.

Dogger Bank D will now connect into Birkhill Wood, a proposed new 400kV substation located in the East Riding of Yorkshire which will be built as part of National Grid's Great Grid Upgrade.

The announcement follows the publication of an impact assessment for the South Cluster by ESO, relating to energy projects which are due to be electrically connected off the east coast of England.

With the location of a grid connection confirmed, Dogger Bank D will now focus its full attention on connecting to the electrical transmission system.

The project is also exploring the future possibility of the development of Dogger Bank D to be coordinated with an Offshore Hybrid Asset between the UK and another European country's electricity market to form a multi-purpose interconnector. This option would increase energy security for the UK and reduce the need to curtail offshore wind output in times of oversupply on the GB network.
-- Advertisement --
NorthernAsbestosServicesLtd



The project team are undertaking a site selection process to identify potential cable corridors and where other onshore infrastructure associated with the grid connection at Birkhill Wood may be sited. Consultation will be held later this year to introduce the connection proposals to the local community.

Rob CussonsDogger Bank D Project Manager, said

"Dogger Bank D welcomes this confirmation which supports our ambition to develop this proposed offshore wind farm. Dogger Bank D promises to build on the legacy we're creating through the earlier phases of the Dogger Bank Wind Farm, during which we are working hard to deliver safe and respectful construction both offshore and onshore, as well as generating socio-economic value for current and future generations. We look forward to continuing these high standards for project development and working with our stakeholders to plan and deliver a sustainable and secure energy system."

With the confirmation of an onshore grid connection location in the East Riding of Yorkshire, the option to direct the wind energy produced by Dogger Bank D towards hydrogen production, as publicly consulted on in Autumn 2023, has been retired from the project. Plans to produce green hydrogen at a dedicated onshore facility had been explored in parallel with the electrical transmission opportunity by Dogger Bank D since the announcement of the project in February 2023. In response to the public consultation held last year, a feedback report for Dogger Bank D will be published later this month. This will contain a project update outlining the future direction for Dogger Bank D in addition to the findings from all feedback received. Representatives for the project have started early discussions with stakeholders about updated proposals for the project and are looking forward to actively engaging with communities on the progression of Dogger Bank D.

Latest Construction News

16/04/2025
Construction work on the £5 million repair and refurbishment project at the Loch Centre in Tranent is scheduled to commence in June 2026. East Lothian Council has announced the anticipated start date for the significant upgrade to the well-used community facility. Under the current timetable, the
16/04/2025
A £636,000 project to install solar panels at the Gorbals water pumping station in South Ayrshire has been successfully completed. The scheme aims to provide a renewable energy source for pumping water to thousands of customers in the region. The project involved the installation of 793 solar pan
16/04/2025
A planning application has been lodged with Glasgow City Council by The JR Group, acting on behalf of Wheatley Group, for the construction of 29 much-needed affordable homes in the Baillieston area of the city. The proposed development on Caledonia Road will offer a mix of one- and two-bedroom apa
16/04/2025
Residents in 20 blocks of flats across Coatbridge are already experiencing the positive impacts of a recently completed, ambitious energy efficiency refurbishment project. The extensive construction work has delivered significant improvements to the properties, including the installation of cavity
16/04/2025
Ground investigation works are commencing this month at the proposed site for Orkney Islands Council’s Scapa Deep Water Quay at Deepdale in Holm. These initial investigations will be followed by marine-based site investigation works scheduled to begin in June. These works form part of the Pre-Con
16/04/2025
Construction work has been finalised on a significant new housing development in Motherwell town centre, delivering 42 newly built, highly energy-efficient flats alongside the respectful conversion of the B-Listed YMCA building into a further six homes. The project, part of North Lanarkshire Council
16/04/2025
The Construction Industry Training Board (CITB) has today released its year-end performance data for its New Entrant Support Team (NEST), revealing a significant increase in apprenticeship starts. During the financial year 2024-25, NEST supported 4,128 individuals in commencing apprenticeships, a su
16/04/2025
A water-powered mill in Angus is set to grind grain once again after receiving a record-breaking donation to fund its restoration. The National Trust for Scotland has announced that a long-time member of the conservation charity has gifted an incredible £2.4 million, one of the largest single dona
15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground. Drone footage has captured the progress of the project, which is a partnership between developer Artisa
15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond. The new connections system, anticip
Morris & Spottiswood LtdRBT Underfloor LimitedThe Scottish Natural Insulation HubMaccaferri LtdPD ServicesMV CommercialSMS Alba Limited@rchitects Scotland LtdProlink Building Solutions LtdCross Blinds