Balfour Beatty Launches Nine New Electricity Transmission Projects

Construction News Image
Balfour Beatty and SSEN Transmission has launched work on the development of nine Electricity Transmission projects across the north of Scotland.

The work forms part of SSEN Transmission's 'Pathway to 2030' network redevelopment programme, to which Balfour Beatty was appointed in August 2023. This first phase of works will see Balfour Beatty provide technical solutions for:

• The new 400kV Beauly to Blackhillock overhead line

• The new 400kV Blackhillock to Peterhead overhead line

• The new 400kV Fetteresso to Tealing overhead line

• The upgrade of the Tealing to Alyth overhead line to 400kV operation

• he upgrade of the Tealing to Westfield overhead line to 400kV operation

• The construction of a new 400kV substation near Peterhead

• The construction of a new 132kV substation near Peterhead

• The construction of a new 400kV substation near Braco

• The extension of the New Deer substation and 400kV cable connections to the New Deer 2 substation

During this initial phase of works, Balfour Beatty will provide its expertise to support SSEN Transmission to identify and resolve any potential construction challenges, streamline the planning process, advise on the best use of materials, plan the phasing of work to ensure optimal productivity and scope out the use of modern methods of construction.
-- Advertisement --
NorthernAsbestosServicesLtd



In addition, and as a result of this level of early contractor involvement and the long-term nature of SSEN Transmission's Pathway to 2030' network redevelopment programme , Balfour Beatty will strategically map the talent required to deliver the nine projects, enabling the company to invest in capability and expertise, and provide long-term career opportunities to people in the surrounding area, including Apprenticeship and Graduate roles as part of the company's commitment to The 5% Club.

This award marks the first step in the delivery of the onshore transmission infrastructure required for SSEN Transmission's 'Pathway to 2030' programme, which will contribute to securing future energy independence by enabling the connection and transportation of affordable, homegrown, low carbon power.

Steve Tarr, Balfour Beatty's Chief Executive Officer of Transport, Energy and Power Major Projects said: "As the largest power transmission contractor in the UK, we have a key role to play in realising the UK and Scottish Government's ambitious renewable energy targets.

"This early-stage collaboration is incredibly exciting for all of us at Balfour Beatty, as it will allow us to bring our knowledge, built and fostered over 100 years, to the fore of these ambitious schemes to drive efficiencies and speed up the construction programme."

Tony Scott, Director of Capital Development and Delivery said:"We're delighted to have Balfour Beatty working with us to help deliver our 'Pathway to 2030' investment programme.

"At SSEN Transmission we have a longstanding relationship with Balfour Beatty and the knowledge and experience that they will bring will prove invaluable in helping to deliver the critical national infrastructure that is needed to make net zero a reality."

As part of the Early Contractor Involvement phase, which is currently underway with over 100 people from across Balfour Beatty involved, work will start in Spring of this year. Main construction is expected to commence in 2026, with energisation of all nine projects expected by 2030.

Construction contracts for these nine projects are expected to be awarded from the end of 2025 into 2026.

Latest Construction News

15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground. Drone footage has captured the progress of the project, which is a partnership between developer Artisa
15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond. The new connections system, anticip
15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment. The pane
15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire. The event will take place on Monday, 28 April, from 4 pm t
15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle. This key appointment will enable crucial work to progress on the project, including feasibility s
15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027. The £5 million
15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment. The practical guide is designed for landowners, developers,
15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it
14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year. The initial grant of £78.687 million from the Scottish Government
14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure. From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont
RBT Underfloor LimitedMorris & Spottiswood LtdThe Water PointCRGP LimitedM&C McLean LtdStoneCleanScotland.co.ukDunedin Stone LtdSEEIT3DLogical Insulation Solutions LimitedDenfind Stone Limited