A raft of new year promotions at both Director and Associate level have been made at DM Hall, one of Scotland's leading firms of Chartered Surveyors.
Seven professionals have been elevated to Director status in the firm. They are David Hyde and Wallace Kidd, both of whom work in the Glasgow Residential department; Martin Fleming and Kenny Geddes who are based in Hamilton; Hayley Anderson in the Aberdeen office’s North Commercial team; Adam Jennings in the West Commercial team based in Glasgow and Edinburgh-based Paul Carr from the East Commercial team.
Three individuals have also been promoted to Associate status: James Struthers in the Inverurie office, Graham Wilson in Galashiels, and Oliver Lawson who works in the East Commercial Team.
John McHugh, Managing Partner of DM Hall, said: "We congratulate all ten of our colleagues on their well-deserved promotions, either as Directors or Associates of DM Hall.
"Each has worked intensively over a period of time within the firm to establish their status and their expertise as exceptional surveying professionals. I speak on behalf of the entire DM Hall Partnership when I say we wish them every success in continuing to provide a first-class professional service to our clients while, at the same time, developing their own careers and helping building a strong and healthy future for the firm."
Construction News
02/02/2024
DM Hall Announces Promotions


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont