09/01/2024

Levenmouth Rail Link Signalling System Commissioned

Construction News Image
The signalling system for the new £116 million Levenmouth Rail Link has been commissioned by Network Rail – marking a milestone that will see trains able to use the new line.

The signalling was successfully tested and brought into use over the weekend (January 6/7) and ScotRail will now be able to begin training drivers on the new route.

This will see a significant number of trains on the track in coming weeks as drivers develop their knowledge of the new section of railway between Thornton Junction and Leven Station.

Completion of the signalling and the start of driver training is a major step on the way to reconnecting Leven to the mainline railway with passenger services set to begin this summer.

A Scottish Government funded investment, the Levenmouth Rail Link will deliver six miles of new railway and two new stations – at Leven and Cameron Bridge – to open up new social and economic opportunities for the local community.

Fiona Hyslop, Minister for Transport said: "This is a key milestone in reconnecting Levenmouth with the rail network, delivering benefits and opportunities to the people of Leven and Fife. It is also clear evidence of our commitment to investing in Scotland's Railway as we seek to attract more people onto public transport.
-- Advertisement --
NorthernAsbestosServicesLtd



"I'd like to thank everyone involved in the project thus far and look forward to seeing the completion of the stations and active travel links. The imminent start of driver training is another major step towards the railway opening and I aim to visit in the coming weeks to see this progress."

Gerry McQuade, capital delivery director for Scotland's Railway, said: "The commissioning of the signalling system is the last piece of the jigsaw which delivers a fully operational railway ready for driver training.

"The project team will now focus on completing both of the new stations on the line and enhancing the active travel links – walking and cycling routes - that will connect the communities to the new railway."

David Lister, ScotRail Safety, Engineering & Sustainability Director, said: "With the new signalling system now commissioned, ScotRail will begin a programme of driver training enabling our trains to run safely onto the wider network.

"This investment marks one of the final steps towards opening the Levenmouth line, which will deliver new and improved services for our customers across Fife and East Scotland."

Signalling systems allow trains to move around the network, tracking them as they progress along the railway and stopping them safely at stations and junctions.

Specialist engineers have worked for months to design and install the different elements of the new system along the route.

The system on the Levenmouth branch, which is controlled from Network Rail's Edinburgh signalling centre, includes:

• 15 Signals (lineside lights to advise drivers when they can move safely)

• 22 Axle counters (which identify the location of trains on the network)

• 3 sets of points (movable rails that direct trains at junctions)

• 21 Location cabinets (that manage power and communications between different signalling elements)



Latest Construction News

15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground. Drone footage has captured the progress of the project, which is a partnership between developer Artisa
15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond. The new connections system, anticip
15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment. The pane
15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire. The event will take place on Monday, 28 April, from 4 pm t
15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle. This key appointment will enable crucial work to progress on the project, including feasibility s
15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027. The £5 million
15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment. The practical guide is designed for landowners, developers,
15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it
14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year. The initial grant of £78.687 million from the Scottish Government
14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure. From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont
Morris & Spottiswood LtdRBT Underfloor LimitedPD ServicesMV CommercialSMS Alba Limited@rchitects Scotland LtdProlink Building Solutions LtdCross BlindsDiscount Kitchens and Bathrooms LtdHutton Stone Co Ltd