Network Rail has announced that work has not begun on three railway bridges in Hairmyres as part of the East Kilbride enhancement project.
This activity marks the start of the wider engineering works on the £139.8m electrification project as part of a Scottish Government investment to decarbonise passenger services.
Two bridges must be raised and re-decked to create the room required to run overhead powerlines beneath the structures.
Engineers will replace a bridge at Thornton Road from 11 December until 9 April 2024, with the structure closing to traffic and a diversionary route in place during this time.
Work to a footbridge close to Hairmyres station and neighbouring Eaglesham Court takes place from 11 December, with a footpath diversion in place until 21 February.
A third bridge near Thornton Farm which has been out of use for a number of years will be demolished.
Key elements of the works will take place over the Christmas and New Year holiday period during 29-hour periods of continuous working:
• Removal and replacement of bridge at Thornton Road from 22:00hrs on 24 December until 07:00hrs on 26 December.
• Removal and replacement of footbridge at Eaglesham Court from 22:00hrs on 24 December until 07:00hrs on 26 December.
• Demolition of bridge near Thornton Farm from 22:00hrs on 31 December until 07:00hrs on 02 January.
*Works up to the morning of 26 December will completed ahead of Boxing Day train services. Please to check www.scotrail.co.uk for service information.
Gerry McQuade, Network Rail capital delivery director, said: "The bridge works are the starting point for our two-year programme to deliver the East Kilbride enhancement project.
"After several months of planning, along with our contractor Story, the team's excited to be on the ground as the bridge works get underway.
"The three bridges are the first of several structures we'll be replacing or modifying along the line of route. This will allow the installation of the new overhead equipment that will power a greener and more reliable railway for our passengers and lineside neighbours.
"Given the scale of the engineering being delivered over the Christmas and New Year period, and the road closure and footpath diversion in place, we fully appreciate the patience and support of the community during this time."
The East Kilbride enhancement project follows on from the recent electrification of the Glasgow - Barrhead line, with electric Class 380 trains being introduced on to this route from 11 December.
If you have any questions about the works, you can contact Network Rail's 24-hour national helpline on 03457 11 41 41.
Construction News
07/12/2023
Major Bridge Works Underway In Hairmyres


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont