30/11/2023
BEAR Scotland Announces Final Phase Of A9 Active Travel Works
![Construction News Image](https://www.buildscotland.co.uk/newsimages/1_302937_BEAR.jpg)
BEAR Scotland has announced that the final phase of active travel and road safety improvements on the A9 between the Kessock Bridge and North Kessock Junction will get underway on Monday 4 December.
The project will see BEAR Scotland, Transport Scotland's operating company, complete surfacing and road markings to the improved, shared-use cycleway, which forms part of National Cycle Route 1. The works will make the cycleway safer and more accessible.
The works are scheduled to begin on Monday 4 December for one week. There will be northbound lane restrictions between 7am and 3:30pm each day. All works are scheduled to be complete by Friday 8 December, weather permitting.
To ensure the safety of roadworkers and road users, a single left lane closure will be in place on the A9 northbound carriageway each day (Monday – Friday). The existing National Cycle Route 1 path adjacent to the A9 northbound will be closed for the duration of the project whilst the surfacing works take place. Non-motorised users will be diverted to use the alternative National Cycle Route 1 path through North Kessock. The pedestrian and cycle crossing points will be open throughout the works.
Ian Stewart, BEAR Scotland's North West Representative said: "This project is part of an ongoing commitment to improve safety for all road users on the A9 and will see improvements to the existing links for pedestrians and cyclists in the area, helping to promote active travel. The project has taken longer than expected due to poor weather, however we aim to complete it before the worst of the winter weather. We thank drivers and the local community for their patience.
"The traffic management is essential to keep roadworkers and road users safe during this project as our teams will be working in the northbound verge, however we will do all we can to complete the remaining works as quickly and as safely as possible.
"We encourage road users to plan their journey in advance by checking the Traffic Scotland website for up to date traffic information and allow some extra time to reach their destination."
The project will see BEAR Scotland, Transport Scotland's operating company, complete surfacing and road markings to the improved, shared-use cycleway, which forms part of National Cycle Route 1. The works will make the cycleway safer and more accessible.
The works are scheduled to begin on Monday 4 December for one week. There will be northbound lane restrictions between 7am and 3:30pm each day. All works are scheduled to be complete by Friday 8 December, weather permitting.
To ensure the safety of roadworkers and road users, a single left lane closure will be in place on the A9 northbound carriageway each day (Monday – Friday). The existing National Cycle Route 1 path adjacent to the A9 northbound will be closed for the duration of the project whilst the surfacing works take place. Non-motorised users will be diverted to use the alternative National Cycle Route 1 path through North Kessock. The pedestrian and cycle crossing points will be open throughout the works.
Ian Stewart, BEAR Scotland's North West Representative said: "This project is part of an ongoing commitment to improve safety for all road users on the A9 and will see improvements to the existing links for pedestrians and cyclists in the area, helping to promote active travel. The project has taken longer than expected due to poor weather, however we aim to complete it before the worst of the winter weather. We thank drivers and the local community for their patience.
"The traffic management is essential to keep roadworkers and road users safe during this project as our teams will be working in the northbound verge, however we will do all we can to complete the remaining works as quickly and as safely as possible.
"We encourage road users to plan their journey in advance by checking the Traffic Scotland website for up to date traffic information and allow some extra time to reach their destination."
![](https://www.buildscotland.co.uk/newsimages/1_316150_marine-energy.jpg)
11/02/2025
A new report from the University of Edinburgh has revealed the significant economic potential of Scotland's marine energy sector, with the potential to contribute more than £8 billion to the Scottish economy by 2050 and support over 15,000 jobs.
"The energy contained in Scotland's seas is a vast an
![](https://www.buildscotland.co.uk/newsimages/1_316147_buchanan-street.jpg)
11/02/2025
Savills has brokered the sale of 98 Buchanan Street and 31 Royal Exchange Square, Glasgow, to Cervidae for £13.775 million.
The sale marks the conclusion of Old Park Lane Management's (OPLM) asset management plan in Scotland, as the company focuses on its core strategy of large-scale development in
![](https://www.buildscotland.co.uk/newsimages/1_316144_planning1.jpg)
11/02/2025
North Lanarkshire Council and NHS Lanarkshire have signed a Memorandum of Understanding (MoU) to collaborate on the delivery of two major infrastructure projects: the East Airdrie Link Road and the new University Hospital Monklands.
The MoU aims to ensure that the development of the East Airdrie Li
![](https://www.buildscotland.co.uk/newsimages/1_316136_hillington-west.jpg)
11/02/2025
Network Rail engineers are set to begin a £2.9 million project to renew both platforms at Hillington West station on the Glasgow – Paisley railway line.
Both platforms, which are 190 metres long, have reached the end of their service life and will be demolished and rebuilt with improved surfacing a
![](https://www.buildscotland.co.uk/newsimages/1_316143_home1.jpg)
11/02/2025
West Lothian Council has reported a significant reduction in the number of empty council properties, commonly known as "voids," in recent months.
Currently, around 1.7% of all council properties in West Lothian are vacant, a significant decrease from over 500 properties in November 2023.
"This is
![](https://www.buildscotland.co.uk/newsimages/1_316133_orkney.jpg)
11/02/2025
Plans for a new offshore wind hub in Orkney have been accelerated with the announcement of a £5 million grant from Highlands and Islands Enterprise (HIE).
The funding will support the development of a new deep-water quay at Scapa Flow, enabling the assembly of offshore wind turbines at the site.
"
![](https://www.buildscotland.co.uk/newsimages/1_316153_lingston.jpg)
11/02/2025
Work has commenced on a coastal protection scheme in Kingston, Moray, designed to mitigate the impacts of erosion in the area.
The project, funded by the Scottish Government, will involve the construction of a 50cm high shingle bank between Lein Car Park and the main shingle ridge at the lagoon.
"
![](https://www.buildscotland.co.uk/newsimages/1_316140_land2.jpg)
11/02/2025
The Scottish Land Commission has called for a stronger role for public land acquisition in addressing the rural housing crisis.
A new report published by the Commission highlights the need to utilise public land more effectively to ensure a steady supply of land for much-needed housing development
![](https://www.buildscotland.co.uk/newsimages/1_316138_linlithgow.jpg)
11/02/2025
Construction has commenced on a new mixed-use development in Linlithgow, comprising a 60-bed care home and 18 private apartments.
The 1.6-acre site, located near Linlithgow Train Station, will be developed by a joint venture between Morrison Community Care Group and CCG (Scotland).
"This new devel
![](https://www.buildscotland.co.uk/newsimages/1_316130_ssen-transmission.jpg)
11/02/2025
SSEN Transmission, the Perth-based electricity transmission company, has pledged its support to the Young Person's Guarantee, a Scottish Government initiative aimed at providing opportunities for all 16-24 year olds.
The company has reaffirmed its commitment to nurturing young talent in the Scottis