Build Scotland Construction Directory
Time and date
CONSTRUCTION DIRECTORY
Share this page
Construction News
04/08/2023

Final Convoy Viking Wind Turbine Components Delivered

Construction News Image
The final convoy of wind turbine components have been delivered to the site of the Viking Wind Farm in Shetland, marking a major milestone for the SSE Renewables project.

Over 280 convoys were successfully completed since getting underway in February, which has seen over one thousand turbine components safely transported from Lerwick Port to Viking Wind Farm site.

A specialist team from Police Scotland co-ordinated the convoys, with the turbine manufacturer Vestas being responsible for safely managing the process of getting the components from their factories to Lerwick and then taking their final journey to the Viking site.

The installation of 103 Vestas V117 turbines which will operate in the 4.3 MW power mode continues to make good progress with 83 turbines now fully erected. The project team have worked at pace in some very challenging conditions, with all the components on site, all turbines are expected be installed by autumn 2023.

-- Advertisement --
NorthernAsbestosServicesLtd

Heather Donald, SSE Renewables' Onshore Renewables Development and Construction Director, said: "It's great that we've reached this milestone in the project with convoys completing. It takes a lot of planning and organisation to get to this point. It's been a huge team effort from Police Scotland, Vestas and McFadyen's Transport Ltd, a specialist haulage company based in Scotland, to complete this phase of the project with minimal impact on motorists.

"We would like to thank the local community for their patience and support over the past few months whilst we transported turbine components from Lerwick Port to mainland Shetland."

Robert Yeates, Lead Project Manager with Vestas said: "To see the conclusion of convoys is a proud moment for everyone that has been involved in the programme over the last six months. A lot of planning was involved prior to the convoys commencing to ensure we did everything possible to transport these huge and heavy components to site safely.

"We're grateful to the local community for their patience during this delivery programme. We can now look forward to completing the installation of the turbine components that have been delivered to site."

Once complete in 2024, the 443MW Viking Wind Farm will be capable of producing enough energy to power the equivalent of almost half a million homes, including every home in Shetland – playing a crucial role towards achieving Scotland's net zero targets.

Latest Construction News

26/11/2024

Scottish Water has unveiled its largest-ever procurement initiative, aiming to modernise the nation's water and wastewater infrastructure while safeguarding the environment. The program, named Delivery Vehicle 4, is valued between £5 billion and £9 billion and is set to run from 2027 to 2033, with ...
26/11/2024

The City of Edinburgh Council has granted planning permission, subject to conditions, for the refurbishment of Calton Square, an office building currently occupied by Baillie Gifford until the end of December 2025. Promoted by Ardstone Capital on behalf of Manova Partners, the project aims to ...
26/11/2024

First Minister John Swinney, MSP for Perthshire North, praised the progress being made on the construction of the new Perth High School during a visit on Friday, 22 November. He was joined by Jim Fairlie, MSP for Perthshire South and Kinross-shire, alongside senior Perth and Kinross Councillors, ...
26/11/2024

A state-of-the-art playpark has officially opened at King George V Park in Bearsden, following the completion of a £100,000 refurbishment. Funded by a combination of East Dunbartonshire Council (EDC) Capital Funding and the Scottish Government’s Renewing Scotland’s Play Parks initiative, the ...
26/11/2024

Fife Council has launched a public consultation, inviting residents, businesses, and organizations to contribute ideas and propose sites for inclusion in the next Local Development Plan, known as Fife's Place Plan. The council is calling on community councils, landowners, and developers to share ...
26/11/2024

The Chief Executive of East Lothian Council has announced she is to retire in February 2025. Monica Patterson who has been Chief Executive for almost five years, has spent most of her professional career working in local government. Prior to joining East Lothian Council in 2010, she was Head of ...
25/11/2024

West of Scotland Housing Association (WSHA) and Connect Modular have jointly submitted a planning application to Glasgow City Council for the development of 33 affordable homes in Cowlairs. This project aligns with the wider Cowlairs Park regeneration scheme and the city's ambitious housing ...
25/11/2024

Arc-Tech (Scotland) has successfully completed a £6m Mechanical and Electrical (M&E) services package for the Lost Shore Surf Resort in Edinburgh. The state-of-the-art resort, which opened its doors earlier this month, features a range of amenities, including a wave pool, luxury lodges, and ...
25/11/2024

Scottish Water has successfully completed the construction of a groundbreaking hydro energy generation scheme at Whiteadder Reservoir in East Lothian. This innovative project, believed to be the first of its kind in Europe, will harness the power of water to offset a significant portion of the ...
25/11/2024

Work is set to commence on a £6.5 million project to upgrade the Double Dykes Gypsy/Traveller site near Perth. The initiative aims to replace outdated chalets with modern, energy-efficient accommodation and implement significant site improvements. Perth & Kinross Council secured £3.9 million from ...
Morris & Spottiswood LtdRBT Underfloor LimitedToner Damp Proofing SuppliesNo HydroSEEIT3DCF Concrete PumpingMaccaferri LtdDiscount Kitchens and Bathrooms LtdShopfronts ScotlandJSJ Foam Insulation Ltd
Terms and Conditions
2024/11/27 01:11:35