10-Week Programme Of Bridge Repair Works In West Lothian

Construction News Image
West Lothian Council has announced a 10-week programme of vital maintenance works for six bridges in Livingston.

The bridges involved are located at:

• A71 Bankton Road at Crofthead Interchange;

• Almondvale Road between Almondvale Road Roundabout and Retail Park Roundabout (near ALDI store);

• A899 Livingston Road (dual carriageway) at Centre Interchange;

• A899 Livingston Road at Centre Interchange.

The work will include replacing defective bridge joints, deck repairs and carriageway resurfacing works to ensure the bridges remain safe for the future.

A rolling programme will take place between Monday 31 July and Friday 6 October, with work being completed on one bridge before moving onto the next to minimise disruption. The work is being carried out by Chemcem (Scotland) Ltd on behalf of the council.

A West Lothian Council spokesperson said: "We would like to make sure that Livingston residents and those who travel over these bridges are aware of these works in advance.

"The scale of these works means that some diversions and temporary traffic lights will be put in place to allow the essential repairs to be carried out safely.

"Those affected are advised to plan their journeys accordingly and allow extra time for travel."

Detail of works:

A71 Bankton Road at Crofthead Interchange
-- Advertisement --
NorthernAsbestosServicesLtd



The work at the A71 Bankton Road at Crofthead Interchange will start from 31 July for an estimated two weeks and is planned in two phases:

From Monday 31 July for approximately one week, a short section of the A71 Bankton Road will be closed at Crofthead Interchange to allow for the replacement of bridge joints. Traffic will be diverted via the Crofthead Interchange slip-roads. 

From Monday 7 August for approximately one week, a short section of the A71 Bankton Road will be closed at Crofthead Interchange to allow for the replacement of bridge joints and carriageway resurfacing at the nearby Crofthead Interchange Underpass. Westbound traffic will be diverted via the Crofthead Interchange slip-roads. For eastbound traffic, the A71 Bankton Road will be closed at Newpark Roundabout (at Alderstone Road) and traffic will be diverted via Alderstone Road, Almondvale Road and the A899 Livingston Road towards Lizzie Brice's Roundabout to rejoin the A71.

Almondvale Road between Almondvale Road Roundabout and Retail Park Roundabout

The work on the Almondvale Road between Almondvale Road Roundabout and Retail Park Roundabout near ALDI store will start on Monday 14 August for an estimated two weeks.

Lane closures with temporary traffic lights will be used to manage traffic while a defective bridge joint is replaced at Dedridge North Bridge.

A899 Livingston Road at Centre Interchange

Work on the A899 Livingston Road at Centre Interchange is expected to start on Monday 28 August for an estimated two weeks. 

A short section of the A899 Livingston Road at Centre Interchange will be closed in the northbound lanes to allow for the replacement of bridge joints and carriageway resurfacing.

Northbound traffic on the A899 will be put into a contraflow system for a short distance using the central reserve cross-over points and the southbound carriageway. It is intended that all interchange slip roads will remain open during these works.

A899 Livingston Road near Livingston East Roundabout at Deer Park

Work on the A899 Livingston Road near Livingston East Roundabout at Deer Park is expected to begin on Monday 11 September for an estimated four weeks.

This will allow work to safely take place on the replacement of bridge joints, carriageway resurfacing and the renewal of the anti-skid surface treatment at Nettlehill Railway Bridge, which is located just south of Livingston East Roundabout.

It will be necessary to reduce the carriageway approaching the roundabout from three traffic lanes down to one traffic lane, which will likely lead to traffic queuing and delays.

Latest Construction News

15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground. Drone footage has captured the progress of the project, which is a partnership between developer Artisa
15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond. The new connections system, anticip
15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment. The pane
15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire. The event will take place on Monday, 28 April, from 4 pm t
15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle. This key appointment will enable crucial work to progress on the project, including feasibility s
15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027. The £5 million
15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment. The practical guide is designed for landowners, developers,
15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it
14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year. The initial grant of £78.687 million from the Scottish Government
14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure. From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont
RBT Underfloor LimitedMorris & Spottiswood LtdScaffolding & Access Supplies LtdM L Contracts Scotland (Stone) LtdJJK RoofingHBB GeoSales LtdBM DecoratingGarage Floors DirectA.G.S Steel Erectors LtdRobinsons Group