Ofgem Gives The Go-Ahead For New Transmission Link In Orkney

Construction News Image
Energy regulator Ofgem has given the go-ahead for a new transmission link in Orkney.

The approval follows Ofgem's public consultation on the proposals for Orkney's Community Wind Farm Project and the need for an electricity link from Orkney to the Scottish mainland.

To approve the 'Needs Case' for the cable, the regulator required a total of 135MW of renewable generation to justify a 220MW cable installation.

Orkney Islands Council will contribute nearly 90MW through Orkney's Community Wind Farm Project.

The Council's wind farm project consists of three six-turbine wind farms, each with planning approval, located at Quanterness in St Ola, Wee Fea in Hoy and on the island of Faray.

Since identifying the need for the project back in 2016, a total of £2.5 million has been spent by Orkney Islands Council on developing the project to date.

During the initial site identification and feasibility studies, £575,000 was spent performing and Orkney wide site investigation and evaluation of potential sites. Following this assessment, the Council was able to identify three sites that met the requirements for developing a wind farm project that provided the best chance of securing planning permission.

Following site identification, approximately £1.3 million was spent on progressing the projects through the Environmental Impact Assessment (EIA) and planning consent processes. This included site surveys, preparing EIA documents for the planning applications, and receiving technical advice.
-- Advertisement --
NorthernAsbestosServicesLtd



All three sites receiving planning permission from the Scottish Government.

In addition, £60,000 has been spent on additional requirements for progressing the wind farms and meeting Ofgem’s Needs Case including updating the project’s business case, securing grid applications, and applying for a Contracts for Difference.

£540,000 has been spent on staff costs with three local jobs currently in place.

The projected costs for the procurement of turbines and construction for all three sites will be in the region £110 million.

The current financial assessment indicates the project would generate an average real profit of £5.5 million per annum for the Council, which over the 25-year lifespan of the project, would equate to a profit of nearly £138 million.

From an economic report that was recently published, a new electricity transmission link between Orkney and the Scottish mainland could be worth at least £371 million to the Orkney economy, rising to £807 million if the wave and tidal energy industry makes use of the cable too.

As well as generating significant income for the county, the projects will also provide an estimated annual payment of £432,000 into a 'location-specific community benefit fund', for local communities to drive transformational projects of their own.

Orkney Islands Council Leader, James Stockan, said: "We are absolutely delighted with today’s announcement from Ofgem, this is a giant leap towards Orkney achieving our energy aspirations. Once operational, it also opens up opportunities for a number of businesses to expand, increasing employment and boosting our local economy.

"Our projects team has worked diligently to ensure that the wind farm project would meet Ofgem’s conditions. Although a final decision has not been made by the Council as to whether or not Orkney’s Community Wind Farm Project will go ahead, the potential socio-economic benefits are enormous, and given the Council’s financial challenges alongside the cost-of-living crisis we are all facing, it is essential that we find new ways of generating income.

"The three wind farms will also help us meet not only our own carbon reduction aspirations but contribute to Scottish and UK Government targets too."

Latest Construction News

15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground. Drone footage has captured the progress of the project, which is a partnership between developer Artisa
15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond. The new connections system, anticip
15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment. The pane
15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire. The event will take place on Monday, 28 April, from 4 pm t
15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle. This key appointment will enable crucial work to progress on the project, including feasibility s
15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027. The £5 million
15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment. The practical guide is designed for landowners, developers,
15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it
14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year. The initial grant of £78.687 million from the Scottish Government
14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure. From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont
RBT Underfloor LimitedMorris & Spottiswood LtdSips Eco Panel Systems LtdDMC VisualsContainexHutton Stone Co LtdQuickFix Plumbing & HeatingScaffolding & Access Supplies LtdM L Contracts Scotland (Stone) LtdJJK Roofing