SSE has announced a major milestone in the ongoing development of Viking Wind Farm, with the successful installation of the project's 52nd Vestas V117 turbines.
Once complete and operation, Viking's 103 turbines will operate in the 4.3 MW power mode and generate up to 443MW of wind-powered electricity once fully operational, and will be the most productive onshore wind farm in the UK
Installation of turbine components got underway in February this year, with all the tower base sections (pre-installations) erected across site by mid-June. The completed tip height of each turbine is 155m.
Turbine components continue to be delivered from Lerwick Port under convoy operation and are expected to conclude later this month. All turbines are programmed for full erection in 2023, with Viking expected to be fully operational by the autumn of 2024.
Paul Nicolson, SSE Renewables' Head of Onshore Renewables Development and Construction for UK & Ireland/ Gerry Hamill, Project Manager for SSE Renewables said: "The installation of the 52nd turbine near Scar Quilse off the A970 is an exciting milestone for the project. The progress reflects our strategy to lead the transition to a net zero future through the world-class development, construction and operation of renewable power assets.
"Reaching this point in the project is testament to everyone involved in the installation process. By the end of this year, we expect all of Viking's turbines to be in place and once operational, in 2024, it will be capable of producing enough energy to power the equivalent of almost half a million homes including every home in Shetland, playing a crucial role in contributing towards the UK and Scotland's net zero targets."
Robert Yeates, Lead Project Manager with Vestas, said: "We are very pleased to have reached the halfway mark of the construction programme. This significant milestone has been achieved with the continued close collaboration with our partner SSE Renewables, RJM the principal contractor on the Viking Energy Wind Farm, and our subcontractors."
Construction News
06/07/2023
SSE Welcomes Latest Milestone In Viking Wind Farm Development


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont