Network Rail has announced that work to electrify the rail line between Glasgow and Barrhead will get underway on Saturday, 24 June.
Engineers will be working around-the-clock for approximately six weeks – until 03 August – to prepare the line to Barrhead for electrification, as part of a £63m upgrade.
During this critical phase of the Scottish Government-funded project, engineers will install overhead power lines and carry out platform works at Kennishead, Priesthill & Darnley, Nitshill and Barrhead stations.
At Nitshill, the existing station footbridge is also being removed and replaced with a new ramp to Platform 2 to provide step-free access.
Beyond Barrhead, track, signalling and embankment upgrades will also be delivered near Lugton, in East Ayrshire, while the line is closed.
Paul Reilly, Network Rail senior programme manager, said: "This major investment in Scotland's Railway will play a vital part in creating a more sustainable, greener railway for customers.
"Closing the railway for an extended period is never an easy decision to take, however, it does mean we can get this complex work done more quickly and with less long-term disruption for passengers.
"We appreciate the inconvenience this work will cause customers and those living closest to the railway. I want to thank people for their continued patience as we complete a project that will transform the railway environment and the passenger experience."
To help minimise disruption for passengers, ScotRail will have replacement buses in operation between Kilmarnock and Glasgow until normal train services resume on Friday, August 4.
In addition to a replacement bus service, there will also be reduced services to/from Glasgow to Crossmyloof and Pollokshaws West stations. Trains between Carlisle, Dumfries and Glasgow will terminate at Kilmarnock for a connecting replacement bus service.
David Simpson, ScotRail service delivery director, said: "We know that the works will be an inconvenience to customers but we are doing everything we can to keep people moving.
"People should plan ahead, taking alternative routes to and from Glasgow, or using our replacement bus services. And please check our social media channels, website, and app for up-to-date information on how to complete your journey.
"This an exciting project for Scotland's Railway, and we are delighted to see more of the network being electrified as we continue our journey to net zero."
Once the Barrhead-Glasgow electrification project completes later this year, it will enable electric services to operate on the route and further encourage more passengers on to the railway.
Time and date
CONSTRUCTION DIRECTORY
Construction News
19/06/2023
Network Rail Set To Begin Latest Line Electrification Works
Latest Construction News
20/12/2024
City of Edinburgh Council has granted planning permission for a major development on the site of Edinburgh Airport's disused runway. The 'Elements Edinburgh' project, led by Crosswind Developments, will deliver 3,000 new homes, 500,000 square feet of commercial space, hotels, and extensive open ...
20/12/2024
Scotland's First Minister, John Swinney, and UK Minister of State for Science, Research and Innovation, Lord Vallance, have marked the start of construction on a new £20 million Oligonucleotide Manufacturing Innovation Centre in Glasgow. This state-of-the-art facility, due to open in 2025, will be ...
20/12/2024
SSEN Distribution has outlined a strategic plan to deliver a more efficient and sustainable electricity network, aligning with the UK's ambitious net zero goals. The company's Strategic Development Plans (SDPs) aim to address the challenges and uncertainties of the energy transition, including the ...
20/12/2024
North Lanarkshire Council is leading the way in reducing the carbon footprint of road infrastructure, partnering with Transport for West Midlands, Amey, and Colas on a groundbreaking initiative. As part of the ADEPT Live Labs 2 programme, the Centre of Excellence for Decarbonising Roads (CEDR) is ...
20/12/2024
Over 300 primary school pupils across Scotland have had a taste of the construction industry thanks to a festive competition hosted by Barratt Homes and David Wilson Homes. Pupils from P2 to P4 classes in Inverness, Aberdeen, Perth, St Andrews, East Lothian, and Glasgow were challenged to design a ...
20/12/2024
The Construction Industry Training Board (CITB) has announced a delay to its Consensus process, which will now begin on 17 March 2025. The delay is to allow for the publication of the ITB review, expected in early 2025. CITB aims to align its 2025-29 Strategic Plan with the review's ...
19/12/2024
Work is set to begin on a major regeneration project in Elgin's South Street in early 2025. The first phase of the £18 million Levelling Up Fund project will see the demolition of several properties, including former shops and derelict sites. The development will include: • 38 new affordable ...
19/12/2024
Ambitious plans to revitalise Dumbarton's Artizan Centre have moved a step closer with the granting of planning permission for the next phase of the project. West Dunbartonshire Council's planning committee approved the application to improve shopfronts, landscaping, and infrastructure at the town ...
19/12/2024
CALA Homes (East) has been selected by West Lothian Council to build 15 new affordable homes in Linlithgow. The development, located at Preston Glade, will include a mix of house types, including two-bedroom bungalows, three-bedroom semi-detached houses, and one-bedroom cottage flats. All homes ...
19/12/2024
Taylor Roofs, a leading Scottish roofing company, has expanded into a new headquarters in Livingston. The family-run business, which serves customers across central Scotland, including Edinburgh, Glasgow, and the Lothians, has outgrown its previous base in Bathgate. The new, larger premises will ...