With the successful completion of works to install over 500km of conductor cable, 9,500 cubic metres of concrete, almost 3,000 tonnes of steel over the course of some 500,000 working hours, the new Port Ann to Crossaig overhead line project has been energised.
Stretching from Port Ann substation near Lochgilphead to the substation at Crossaig, the new overhead line developed by SSEN Transmission and their Principal Contractor Balfour Beatty is around 45km in length. Supported on 148 newly installed steel-lattice towers, the new line has been designed to be more resilient in extreme weather events, enhancing the security of supply for those living and working in the area.
This is the first major project to be energised under SSEN Transmission's RIIO T2 Framework, marking a major milestone in their wider strategy to deliver a network for net zero emissions across the north of Scotland.
The new line has been built to replace the existing 132kV line, originally built in the 1950s, which has reached the end of its operational life. SSEN Transmission has future proofed the new overhead line by building it to initially operate at 132kV with the capacity increase to 275kV, meaning it can accommodate future contracted electricity generation on to the grid.
Following on from energisation of the new overhead line, the existing 132kV line will be decommissioned and carefully removed from the landscape. This work is expected to be completed by the end of 2023.
During peak construction, around 150 people worked on the new overhead line between Port Ann to Crossaig, with over half-a-million working hours spent delivering the project across SSEN Transmission and its contractors.
The Port Ann to Crossaig project is the second phase in the wider Inveraray to Crossaig powerline upgrade, with the first phase – Inveraray to Port Ann – energised in July 2021. The replacement line, which stretches a total of 84km across both phases, serves as the main arterial route for electricity transmission in Argyll, keeping the lights on for homes and businesses throughout the Peninsula.
Building a project of this size has brought significant benefit to the local economy. Teams across both Phase 1 and 2 of the Inveraray to Crossaig project have contributed significantly to the £7 million spent by SSEN Transmission and their contractors on food and accommodation in the Argyll and Bute Council area since April 2020, including spending around 50,000 nights in local accommodation.
As a stakeholder-led business, the team has worked to keep the community informed throughout the project via monthly community liaison groups to keep stakeholders up to date on progress. The team also carried out various volunteering initiatives to give something back to the area, which included projects such installing a new sandpit for outdoor nursery MAKI Pups, run by Argyll and the Isles Coast and Countryside Trust; painting the interior living-space of Ardfenaig Residential Home in Ardrishaig; and donating high-vis clothing and torches to Tarbert High School to help keep pupils safe on their commute to school during the winter months.
SSEN Transmission has committed to replanting over 270 hectares of trees which were removed during construction, and, where possible, opting for native tree species. Last year, SSEN Transmission and leading community and conservation organisation Argyll and the Isles Coast and Countryside Trust (ACT), and Argyll and Bute Council joined forces to help deliver these tree planting commitments and in doing so, help support and enhance Scotland's rainforest in Argyll.
The ground-breaking partnership has already seen the initial phase of planting get underway on Argyll and Bute Council's sites near Lochgilphead, which once complete will see approximately 50,000 native trees planted. By planting native species, the planting will support local flora and fauna, creating natural habitats for native species to thrive, supporting SSEN Transmission's commitments to deliver biodiversity net gain and compensatory planting on all its major projects.
The planting will also create a natural asset for the local community to enjoy for generations to come, leaving a positive lasting legacy beyond SSEN Transmission's primary objective of delivering a network for net zero emissions across the north of Scotland.
SSEN Transmission Project Manager Peter Brum, said:
"Energising the line is a hugely significant milestone in the Port Ann to Crossaig project, and I'm delighted that after 24 months of hard work from across our teams and contractors Balfour Beatty and Scottish Woodlands, the new line is now live.
"The Port Ann to Crossaig replacement line joins to form the full Inveraray to Crossaig overhead line, which is providing a more secure, reliable and safe means of transporting energy to homes and businesses right across Argyll.
"Energising on schedule is a testament to everyone's hard work and dedication, in the often challenging working conditions brought by the Argyll weather and the remote locations of some parts of the line. The team came together to deliver this project safely, and while this project hasn't been without its challenges, it is testament to the team's experience, professionalism and dedication that when faced with problems we have worked together to reach solutions. As a project team we are proud of the role we are playing in delivering a network for net zero.
"We would like to thank the communities and land owners along the route for their support and continued patience throughout the build, without which the project and its role in reinforcing the transmission network in Argyll would not have been possible."
David Nevin, Balfour Beatty Senior Project Manager, said: "The successful energisation of the remaining circuits marks a momentous milestone for everyone involved from the Balfour Beatty and SSEN Transmission project teams. We are live and operational from Inveraray through to Crossaig. This upgrade secures the supply of energy to consumers in the Argyll & Bute Peninsula and supports the connection of increased renewable generation.
"We were exceptionally lucky to have had so many fantastic people support us in the delivery of the project. Everyone involved should be very proud of what we've achieved together in some of the most difficult and challenging terrain in the UK. This combined with a challenging programme all add to the sense of satisfaction upon successful energisation."
Teams are now turning to the remaining final phase of work, which involves taking down the previous overhead line and removing the old towers. This will be followed by reinstatement of construction areas and temporary access tracks, which will help restore areas temporarily used during the build.
Construction News
14/06/2023
New Port Ann To Crossaig Overhead Line Project Energised


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont