Scottish Water has announced the successful completion of 'very challenging' sewer repair works in the centre of Glasgow.
High Street in the city centre had been closed between its junctions with Duke Street and Rottenrow since the beginning of January to enable essential repairs to the local waste water network to be carried out safely.
The duration of the road closure had to be extended in February, when the full scale and complexities of the work became clear.
Georgina Reid, Scottish Water's corporate affairs manager in the west, explained: "The extension of the road closure on High Street was unavoidable and the road was supposed to be closed until the end of June. We're really pleased that the road has reopened in time for a busy summer period, including the Cycling World Championships. There's absolutely no doubt the local community and road users will be too. Everyone has been very patient and understanding, for which we are very thankful.
"We would also like to thank our delivery partner George Leslie who have shown great resilience throughout, working tirelessly to get the job done for the good of our customers. They really have done a fantastic job in difficult circumstances."
Uncharted services, a 24-inch water main and tricky ground conditions all added to the complexities of the repair to the 200 year-old sewer.
In addition to the 20 metres of sewer pipe which was upgraded, three manholes were constructed and 22 metres of water main removed and replaced.
Blair Dixon was the senior project manager for Scottish Water working on this essential project. He said: "Given that the project was being delivered in one of the oldest street's in Glasgow, we fully expected there to be some issues for the team to overcome. The scale of the works kept growing and our delivery partner faced several challenges as the works unfolded. The team's resourcefulness and hard work has paid off and it's great that the project is now complete."
He added: "There were also some really interesting discoveries on this project; we uncovered some tram lines, we found an old hydraulic line which we believe could have helped operate the lifts in flats, and we uncovered lots of cobbles. The cobbles have been re-purposed and incorporated into Greyfriars Garden, a newly opened local community garden just near to where our works took place. It's nice to know that as well as a more resilient waste and water network, we've contributed towards a lasting legacy in High Street for people to enjoy."
Construction News
26/05/2023
'Very Challenge' Glasgow Sewer Works Complete


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont