Glasgow Central's Platform 1 Renewal Works 'Progressing Well'
![Construction News Image](https://www.buildscotland.co.uk/newsimages/1_296469_Network-rail.jpg)
Network Rail has welcomed the progress being made in the delivery of a 10-week programme to renew track at Glasgow Central's platform 1.
Passengers travelling through Scotland's busiest station will soon benefit from this £1.2m project to improve the track at platform 1 as part of efforts to enhance the safety and reliability of the railway for years to come.
Engineers have been on site since early March, removing rail along the length of the platform and breaking out sections of the concrete slab beneath.
More than 100 timber sleepers have been replaced with focus now turning to hanging and installing all 723 baseplates which sit under the rail and help keep it stable. While there, Network Rail teams also plan to renew signalling cables, clean the buffers and upgrade the tactile paving along the platform.
Platform 1 has been closed during the works, which began on 4 March 2023, with the project running alongside the existing closure of the West Coast Main Line (WCML) at Carstairs Junction to minimise the impact on passengers and is expected to open on time on 12 May.
And during the week, Liam Sumpter, Scotland's Railway Route Director visited the team delivering this crucial work.
Liam Sumpter said: "These essential works at Glasgow Central station will ensure we continue to run a safe and reliable railway.
"Had we used normal access arrangements this work would be spread over a period of approximately four years' worth of Saturday nights and would be considerably more costly. Instead, we've planned this 10-week programme to run at the same time as the closure of Carstairs Junction so that disruption to passengers is kept to a minimum.
"We have made some efficiencies in costs and timescales and have used this to allow for a deep clean of Platform 1 and removal of overgrown vegetation which is difficult to access during normal circumstances.
"We continue to thank passengers for their patience and understanding while we undertake these essential works."
Passengers travelling through Scotland's busiest station will soon benefit from this £1.2m project to improve the track at platform 1 as part of efforts to enhance the safety and reliability of the railway for years to come.
Engineers have been on site since early March, removing rail along the length of the platform and breaking out sections of the concrete slab beneath.
More than 100 timber sleepers have been replaced with focus now turning to hanging and installing all 723 baseplates which sit under the rail and help keep it stable. While there, Network Rail teams also plan to renew signalling cables, clean the buffers and upgrade the tactile paving along the platform.
Platform 1 has been closed during the works, which began on 4 March 2023, with the project running alongside the existing closure of the West Coast Main Line (WCML) at Carstairs Junction to minimise the impact on passengers and is expected to open on time on 12 May.
And during the week, Liam Sumpter, Scotland's Railway Route Director visited the team delivering this crucial work.
Liam Sumpter said: "These essential works at Glasgow Central station will ensure we continue to run a safe and reliable railway.
"Had we used normal access arrangements this work would be spread over a period of approximately four years' worth of Saturday nights and would be considerably more costly. Instead, we've planned this 10-week programme to run at the same time as the closure of Carstairs Junction so that disruption to passengers is kept to a minimum.
"We have made some efficiencies in costs and timescales and have used this to allow for a deep clean of Platform 1 and removal of overgrown vegetation which is difficult to access during normal circumstances.
"We continue to thank passengers for their patience and understanding while we undertake these essential works."
![](https://www.buildscotland.co.uk/newsimages/1_316097_land-reform.jpg)
10/02/2025
Scottish Land & Estates has warned that calls for more radical changes to the Land Reform (Scotland) Bill could have a devastating impact on rural businesses and communities.
The organisation, which represents landowners and rural businesses across Scotland, expressed concern over calls from campai
![](https://www.buildscotland.co.uk/newsimages/1_316096_scottish-hydropower.jpg)
10/02/2025
A new report has highlighted the increasing challenges facing Scotland's hydropower sector due to climate change, particularly the impact of increased sediment buildup.
Commissioned by Scotland's Centre of Expertise for Waters (CREW), the report, published today, warns that climate change is expect
![](https://www.buildscotland.co.uk/newsimages/1_316095_watertap.jpg)
10/02/2025
Scottish Water has launched a seven-week public consultation on its draft Long-Term Strategy, inviting stakeholders, customers, and communities to provide feedback on its plans for the next 25 years.
The strategy outlines the challenges facing water and waste water services in Scotland, including t
![](https://www.buildscotland.co.uk/newsimages/1_316094_scottish-power.jpg)
10/02/2025
ScottishPower has announced a significant increase in starting salaries for its apprentices, with the company now offering a minimum of £24,310 per year for first-year craft apprentices.
This move by SP Energy Networks, ScottishPower's electricity grid business, makes it the first electricity grid
![](https://www.buildscotland.co.uk/newsimages/1_316087_cairngorm-funicular.jpg)
10/02/2025
Maintenance work has commenced on the Cairngorm Funicular Railway, with staff carrying out essential checks on the electrical, mechanical, and hydraulic systems that govern the movement of the carriages.
An engineer from Swiss funicular specialist Garaventa will join the team this week to conduct s
![](https://www.buildscotland.co.uk/newsimages/1_316089_nhbc.jpg)
10/02/2025
NHBC CEO Steve Wood has announced his intention to step down from the role later this year, bringing to an end eight years of leadership at the organisation.
Under Wood's guidance, NHBC has undergone a period of significant transformation, strengthening its position within the housing sector.
"It
![](https://www.buildscotland.co.uk/newsimages/1_316064_kier.jpg)
07/02/2025
Kier Construction has been awarded a £683.8m contract by the Scottish Government to deliver a new, state-of-the-art prison in Glasgow.
The new prison, HMP Glasgow, will replace the existing HMP Barlinnie, which was built in 1880 and has been deemed unfit for purpose.
"It's an honour to be awarded
![](https://www.buildscotland.co.uk/newsimages/1_316063_stirling.jpg)
07/02/2025
Stirling Council has approved a 7.2% rent increase for council tenants for the 2025/26 financial year. The increase will generate approximately £18.5 million, which will be reinvested in the council's housing stock.
The decision follows a consultation with tenants, with 61% of respondents supportin
![](https://www.buildscotland.co.uk/newsimages/1_316062_shetland-islands.jpg)
07/02/2025
Shetland Islands Council is once again seeking the input of local residents on a range of community issues as part of the 'Our Place – Your Say' project.
The project, which was last conducted in 2016, aims to gather public opinion on 15 key themes, including transport, housing, community safety, an
![](https://www.buildscotland.co.uk/newsimages/1_316058_m90-halbeath.jpg)
07/02/2025
Essential maintenance works have been announced for the Halbeath Road in Dunfermline, with the aim of improving the road surface and traffic flow.
The project, which is scheduled to begin on 24 February and last until March 14, 2025, will involve resurfacing the road from Garvock Bank Railway Bridg