Comprising some 2,885 tonnes of steel, and 9,500 cubic metres of concrete, SSEN Transmission and their delivery partner, Balfour Beatty, have erected the last of the 148 steel transmission towers on the Port Ann to Crossaig overhead line project.
The transmission towers will initially operate at 132kV with the capacity to increase to 275kV to accommodate future connection of offshore and onshore generation. This marks a significant milestone for the project team who have overcome many challenges to deliver this nationally significant project.
Work on the project began in May 2021, with teams working to fell the new corridor for the overhead line and installing over 100km of temporary and permanent access tracks. Construction of the towers began in October 2021, beginning first with the tower foundations. The towers were assembled in sections at ground level and lifted into place using a mobile crane to fix them into position.
SSEN Transmission Project Manager, Peter Brum, said: "On a project of this scale you are always working towards the next major milestones, but for me seeing the final tower top being lifted into place, that's one of the most significant.
"This project traverses some of Scotland's most rugged landscape, so reaching this milestone has been no mean feat and worth taking a moment to celebrate.
"We would like to thank the communities along the route for their continued patience and understanding as we work as safely and efficiently as possible to deliver this critical piece of national infrastructure which, once complete, will be powering homes and businesses in the region for many decades to come."
The new Port Ann to Crossaig overhead line is part of SSEN Transmission's multi-million pound programme of investments in the region, upgrading and replacing the network, much of which was built in the 1950's, strengthening the power supply for those living and working in the area and helping to reduce the impact of the severe weather events. Once complete the project will help to strengthen one of the transmission network's main arteries in the west of Scotland, making it one of the most significant electricity network investments in the region in decades.
The project team will now focus on completing the installation of the remaining overhead wiring. Using a combination of helicopters and large conductor pulling machinery, over 75% of the overhead line wires have already been installed, and the remaining wiring will be completed by early summer.
The project is the second phase in the wider Inveraray to Crossaig powerline upgrade, with the first phase – Inveraray to Port Ann – energised in July 2021.
Construction News
21/04/2023
Final Port Ann To Crossaig Steel Transmission Tower Installed


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont