Trams To Newhaven Day Time Trials Begin

Construction News Image
Edinburgh Council has announced that the first day time trials of trams in the Trams to Newhaven project will begin today, Wednesday 19 April.

The milestone follows a month of successful overnight testing and commissioning, including initial walking speed trams, more recently reaching 20mph, and work to integrate signalling and interface with Edinburgh Trams' control centre.

From today, Edinburgh Trams will begin running trams from morning into the afternoon, which will allow the 40 newly-recruited drivers, along with experienced colleagues, to become familiarised with the route. Up until now, drivers have been training on a state-of-the-art simulator, featuring the existing line and a simulated version of the new track to the north of the city.

Testing to ensure the newly constructed line, software and signals work effectively and safely will also continue and over the coming weeks test tram frequency is expected to increase to a full timetable, as the launch of passenger services approaches.

-- Advertisement --
NorthernAsbestosServicesLtd

Councillor Scott Arthur, Transport and Environment Convener, said: "Seeing trams running the length of Leith Walk and beyond during the day will give a real taste of the future of the route – this is an exciting moment. Of course, this is the first time that the new trams will be on the line in the daytime, so I would encourage everyone to take extra care when in the area.

"We're on the cusp of passenger services beginning, with the project delivered on time and in budget, and this is the culmination of a great deal of hard work by all those involved, despite the challenges of the last few years.

"We can now look forward to a green, high-capacity transport link between the centre and north of the city, which will transform travel along the route, help boost the economy and open up development opportunities."

Edinburgh Trams' Managing Director Lea Harrison added: "Our innovative approach to driver training has delivered numerous benefits for our business but, ultimately, the focus has been on keeping everyone safe. This is why we put new recruits and existing tram drivers alike through rigorous training and ongoing professional development programmes to maintain the highest safety standards."

Edinburgh Trams' Assistant Marketing Manager and Driver Nicola Mearns said: "I am beyond delighted to be one of the first female members of the team to drive a tram to and from Newhaven throughout the day. After receiving thorough training on our in-house simulator, testing today has allowed my colleagues and I to put our knowledge into practice whilst familiarising ourselves with the new section of the line. This is definitely an exciting time for everyone involved at Edinburgh Trams."

The Trams to Newhaven project remains on schedule for completion by spring 2023 and within the £207.3m budget, with all major construction now complete. A specific date for when the route will be open for passengers will be announced in due course.

Latest Construction News

22/11/2024

SP Energy Networks has announced a major investment in Britain's electricity grid, selecting 19 preferred partners to deliver a £5.4bn supply chain programme. This significant initiative aims to meet increasing energy demand and facilitate future growth. The selected companies, many of which are ...
22/11/2024

Edinburgh City Council has launched a 12-week public consultation on a new strategy to revitalise Princes Street and the wider Waverley Valley. The vision aims to create a more vibrant and welcoming city centre, attracting investment, supporting businesses, and enhancing the visitor ...
22/11/2024

Ener-G Services Limited, a leading UK electrical engineering company specialising in renewables, marine, and offshore sectors, has expanded its operations in Westhill, Aberdeenshire. The company has leased Unit 6E at Kingshill Commercial Park, a 2,500 sq ft space, on a 5-year lease. This new ...
22/11/2024

A consortium of leading scientists, industry experts, and academic institutions has joined forces to accelerate Scotland's offshore wind sector. The £2.5 million project, led by the University of Edinburgh in collaboration with the University of Dundee and the Forth and Tay Offshore cluster (FTO), ...
22/11/2024

The Port of Aberdeen and Turner & Townsend were highly commended in the 'Engineering, Construction & Infrastructure Project of the Year' category at the APM Project Management Awards 2024. The award recognises excellence in project management and the positive impact on end-users. The £420 million ...
22/11/2024

South Lanarkshire Council's £10 million fire safety improvement programme has reached a significant milestone, with CCG (Scotland) completing installations in over 1,700 high-rise residences across East Kilbride and Cambuslang. The Glasgow-based construction firm has been working closely with the ...
22/11/2024

SSEN Transmission, a key player in the UK's energy transition, is set to further expand its workforce and move into a new, sustainable office space in Glasgow. The company's commitment to net zero and the increasing demand for green energy workers has led to significant growth, with the number of ...
22/11/2024

Scottish Water is investing in the upgrade of its Loch Eck clean water plant in Dunoon. The project involves replacing outdated dry well pumps with new, more reliable pumps capable of operating in both wet and dry conditions. WGM Engineering, an RSK Group company, has been tasked with carrying out ...
22/11/2024

Scottish Land & Estates has expressed serious concerns over the Scottish Government's Land Reform Bill, particularly the provisions that would allow ministers to force landowners to sell large estates in lots. Sarah-Jane Laing, the organisation's chief executive, stated that while the land-based ...
22/11/2024

Clark Contracts employees have once again shown their commitment to community engagement by volunteering at Silverburn Park in Leven. On Thursday, 21st November, 16 members of the team spent their day planting over 400 trees and carrying out other landscaping tasks. This latest volunteering effort ...
RBT Underfloor LimitedMorris & Spottiswood LtdEarth Tech LPS LTDSolway Ecology Consulting LtdPerfect View Aerial FilmingBurnside Plant Hire LtdSips Eco Panel Systems LtdM K M Building Supplies LtdAlternative Tying Systems LtdContainex
Terms and Conditions
2024/11/23 08:56:26