Network Rail To Begin Ravenscraig Bridge Works
![Construction News Image](https://www.buildscotland.co.uk/newsimages/1_295240_Ravenscraig.jpg)
Scotland's Railway is preparing for an intense 10-day programme to install a 5000-tonne bridge on the West Coast Main Line (WCML) at Ravenscraig in North Lanarkshire.
The £16.9 million project is being delivered through an agreement between North Lanarkshire Council and Network Rail, to construct a new road under the railway line as part of the ongoing regeneration of the former steelworks site.
For the last 10 months, Network Rail and STORY Contracting engineers have been casting the bridge at Network Rail's compound next to the WCML and are now preparing to move it into position from April 1 to April 10.
Working around-the-clock, the team will begin this phase by excavating approximately 36,000 tonnes of material from the railway embankment and removing the track and overhead line equipment.
In a feat of innovation and engineering, the bridge and support structure, totalling around 6,000 tonnes, will then be driven into position using remote-controlled vehicles called self-propelled modular transporters (SPMTs) in what is believed to be the biggest move of its kind in Europe.
The track and the overhead line equipment will be reinstated before a series of signalling work takes place and the line is reopened.
Once the new bridge is in place, the council will progress with the construction of a new dual carriageway with pedestrian and cycle paths from Airbles Road/Windmillhill Street to Robberhall Road, as part of a wider investment to open the area for future development.
The work is being carried out at the same time as the £160m investment at Carstairs on the WCML to reduce disruption for customers. During this project, ScotRail services between Glasgow Central and Lanark will be affected, and passengers should check their journey in advance.
Councillor Paul Kelly, Depute Leader of North Lanarkshire Council, said: "Completion of the bridge is a vital step in constructing the new road and opening up Ravenscraig for investment and regeneration for many years to come,"
"With investment from Glasgow City Region City Deal and the council, the overall £127.2 million Ravenscraig Access Infrastructure project will improve local access to Ravenscraig for housing, leisure and business as well as creating improved connections north to the M8 and south through Motherwell and to the M74."
Jeremy Spence, Senior Programme Manager, Network Rail said: "This project represents more than £16 million worth of investment in the local area from North Lanarkshire Council and Glasgow City Region City Deal.
"Given the sheer size and scale of the bridge, it also represents a significant piece of engineering work, made possible by successes in innovation and collaboration with our major contracting partner, STORY.
"The upcoming intense period of activity marks a major milestone in this huge construction project, with Network Rail, Story and North Lanarkshire Council working closely over the last year to get it to this point
"Once our work is complete, it will allow the council to continue the regeneration of the area that will bring vacant and derelict land back into use while helping to create jobs and connecting people and businesses across the whole region.
"We would like to thank passengers and our lineside neighbours for their patience and understanding while we carry out this vital work."
John MacArthur, Managing Director, Story Contracting (Scotland), said: "As our teams gear up to safely deliver this major milestone of moving a 5,000-tonne structure during an intense 10-day blockade, it's great to reflect on all the hard work and commitment that has gone into the project so far.
"Working with our key supply chain partners, we've poured 2500m3 of concrete to form the structure, and put in 51,300 hours on site, whilst also being able to invest in the community by providing over 400 hours of work experience for local young people.
"We are therefore very proud to be supporting Network Rail and North Lanarkshire Council on this fundamental piece of civil engineering infrastructure."
The £16.9 million project is being delivered through an agreement between North Lanarkshire Council and Network Rail, to construct a new road under the railway line as part of the ongoing regeneration of the former steelworks site.
For the last 10 months, Network Rail and STORY Contracting engineers have been casting the bridge at Network Rail's compound next to the WCML and are now preparing to move it into position from April 1 to April 10.
Working around-the-clock, the team will begin this phase by excavating approximately 36,000 tonnes of material from the railway embankment and removing the track and overhead line equipment.
In a feat of innovation and engineering, the bridge and support structure, totalling around 6,000 tonnes, will then be driven into position using remote-controlled vehicles called self-propelled modular transporters (SPMTs) in what is believed to be the biggest move of its kind in Europe.
The track and the overhead line equipment will be reinstated before a series of signalling work takes place and the line is reopened.
Once the new bridge is in place, the council will progress with the construction of a new dual carriageway with pedestrian and cycle paths from Airbles Road/Windmillhill Street to Robberhall Road, as part of a wider investment to open the area for future development.
The work is being carried out at the same time as the £160m investment at Carstairs on the WCML to reduce disruption for customers. During this project, ScotRail services between Glasgow Central and Lanark will be affected, and passengers should check their journey in advance.
Councillor Paul Kelly, Depute Leader of North Lanarkshire Council, said: "Completion of the bridge is a vital step in constructing the new road and opening up Ravenscraig for investment and regeneration for many years to come,"
"With investment from Glasgow City Region City Deal and the council, the overall £127.2 million Ravenscraig Access Infrastructure project will improve local access to Ravenscraig for housing, leisure and business as well as creating improved connections north to the M8 and south through Motherwell and to the M74."
Jeremy Spence, Senior Programme Manager, Network Rail said: "This project represents more than £16 million worth of investment in the local area from North Lanarkshire Council and Glasgow City Region City Deal.
"Given the sheer size and scale of the bridge, it also represents a significant piece of engineering work, made possible by successes in innovation and collaboration with our major contracting partner, STORY.
"The upcoming intense period of activity marks a major milestone in this huge construction project, with Network Rail, Story and North Lanarkshire Council working closely over the last year to get it to this point
"Once our work is complete, it will allow the council to continue the regeneration of the area that will bring vacant and derelict land back into use while helping to create jobs and connecting people and businesses across the whole region.
"We would like to thank passengers and our lineside neighbours for their patience and understanding while we carry out this vital work."
John MacArthur, Managing Director, Story Contracting (Scotland), said: "As our teams gear up to safely deliver this major milestone of moving a 5,000-tonne structure during an intense 10-day blockade, it's great to reflect on all the hard work and commitment that has gone into the project so far.
"Working with our key supply chain partners, we've poured 2500m3 of concrete to form the structure, and put in 51,300 hours on site, whilst also being able to invest in the community by providing over 400 hours of work experience for local young people.
"We are therefore very proud to be supporting Network Rail and North Lanarkshire Council on this fundamental piece of civil engineering infrastructure."
![](https://www.buildscotland.co.uk/newsimages/1_316150_marine-energy.jpg)
11/02/2025
A new report from the University of Edinburgh has revealed the significant economic potential of Scotland's marine energy sector, with the potential to contribute more than £8 billion to the Scottish economy by 2050 and support over 15,000 jobs.
"The energy contained in Scotland's seas is a vast an
![](https://www.buildscotland.co.uk/newsimages/1_316147_buchanan-street.jpg)
11/02/2025
Savills has brokered the sale of 98 Buchanan Street and 31 Royal Exchange Square, Glasgow, to Cervidae for £13.775 million.
The sale marks the conclusion of Old Park Lane Management's (OPLM) asset management plan in Scotland, as the company focuses on its core strategy of large-scale development in
![](https://www.buildscotland.co.uk/newsimages/1_316144_planning1.jpg)
11/02/2025
North Lanarkshire Council and NHS Lanarkshire have signed a Memorandum of Understanding (MoU) to collaborate on the delivery of two major infrastructure projects: the East Airdrie Link Road and the new University Hospital Monklands.
The MoU aims to ensure that the development of the East Airdrie Li
![](https://www.buildscotland.co.uk/newsimages/1_316136_hillington-west.jpg)
11/02/2025
Network Rail engineers are set to begin a £2.9 million project to renew both platforms at Hillington West station on the Glasgow – Paisley railway line.
Both platforms, which are 190 metres long, have reached the end of their service life and will be demolished and rebuilt with improved surfacing a
![](https://www.buildscotland.co.uk/newsimages/1_316143_home1.jpg)
11/02/2025
West Lothian Council has reported a significant reduction in the number of empty council properties, commonly known as "voids," in recent months.
Currently, around 1.7% of all council properties in West Lothian are vacant, a significant decrease from over 500 properties in November 2023.
"This is
![](https://www.buildscotland.co.uk/newsimages/1_316133_orkney.jpg)
11/02/2025
Plans for a new offshore wind hub in Orkney have been accelerated with the announcement of a £5 million grant from Highlands and Islands Enterprise (HIE).
The funding will support the development of a new deep-water quay at Scapa Flow, enabling the assembly of offshore wind turbines at the site.
"
![](https://www.buildscotland.co.uk/newsimages/1_316153_lingston.jpg)
11/02/2025
Work has commenced on a coastal protection scheme in Kingston, Moray, designed to mitigate the impacts of erosion in the area.
The project, funded by the Scottish Government, will involve the construction of a 50cm high shingle bank between Lein Car Park and the main shingle ridge at the lagoon.
"
![](https://www.buildscotland.co.uk/newsimages/1_316140_land2.jpg)
11/02/2025
The Scottish Land Commission has called for a stronger role for public land acquisition in addressing the rural housing crisis.
A new report published by the Commission highlights the need to utilise public land more effectively to ensure a steady supply of land for much-needed housing development
![](https://www.buildscotland.co.uk/newsimages/1_316138_linlithgow.jpg)
11/02/2025
Construction has commenced on a new mixed-use development in Linlithgow, comprising a 60-bed care home and 18 private apartments.
The 1.6-acre site, located near Linlithgow Train Station, will be developed by a joint venture between Morrison Community Care Group and CCG (Scotland).
"This new devel
![](https://www.buildscotland.co.uk/newsimages/1_316130_ssen-transmission.jpg)
11/02/2025
SSEN Transmission, the Perth-based electricity transmission company, has pledged its support to the Young Person's Guarantee, a Scottish Government initiative aimed at providing opportunities for all 16-24 year olds.
The company has reaffirmed its commitment to nurturing young talent in the Scottis