20/03/2023

'Significant Milestone' In Shetland Connectivity Project

Construction News Image
SSE has reached a significant milestone in connecting Shetland to the national electricity grid for the first time as the next section of subsea cable laying gets underway, helping secure the islands future security of supply of clean, low carbon power.

Waiting in waters off Weisdale Voe, specialist cable laying vessel the NKT Victoria and its expert team were readying themselves to start laying 60km of High Voltage Direct Current (HVDC) subsea cable system, bringing Shetland one step closer to being connected to the national grid for the first time. Once built, SSEN Transmission's Shetland HVDC link will help secure the islands future security of supply of clean, low carbon power; alongside enabling the connection of new renewable electricity generation.

The NKT Victoria lowered the end of the cable which was then successfully pulled onto shore via previously installed ducts by a winch located on the shoreline at Weisdale. Once secured in the transition joint bay, the offshore cable will be jointed to the previously installed HVDC land cable which will then connect to SSEN Transmission's Kergord HVDC converter station and AC substation.

The NKT Victoria will now make her way south out to sea along the designated cable route, slowly lowering around 60km of subsea HVDC cable system onto the seabed. Once the cable is in place on the seabed, it will be trenched into position using a multi-role construction support vessel with a specialist subsea jet trencher, which will ensure the cables are buried to the correct depth. Rock placement will also take place at some sections to ensure the cables are protected where trenching is not possible.

-- Advertisement --
NorthernAsbestosServicesLtd

SSEN Transmission's £660 million Shetland HVDC Link project involves installing a 260km subsea cable system between Noss Head in Caithness and Weisdale Voe in Shetland.

The project is split into three campaigns to allow for safe and accurate installation. The first 100km of cable was successfully installed in July last year, with NKT Victoria laying the cable from Noss Head in Caithness heading east and then northwards. The third and final campaign will take place later this year, which is 100km long and will complete the link between the first and second campaigns in the North Sea to join all three campaigns together and complete the full 260km subsea HVDC link.

SSEN Transmission's Shetland HVDC Link Project Director John Scott said: "The arrival of NKT Victoria in Shetland signals yet another major and hugely symbolic milestone in the Shetland HVDC Link project, and it's been great to see the cable make landfall in Shetland as the vessel begins her voyage into the North Sea and kick off the next cable campaign.

"The installation of the subsea cable system is complex and requires significant planning to reach this point, and working with subsea cable experts NKT has enabled this process to take place reliably, safely and to the highest standard.

"The second cable campaign marks an exciting step in the project for SSEN Transmission and our contractors, and we look forward to the completion of this phase of the subsea cable campaign over the coming weeks."

John Scott, HVDC Link Project Director, said: "The Shetland HVDC Link is crucial to transporting clean, renewable energy to where it is needed most, ultimately helping us achieve a network for net zero; alongside securing Shetland's future security of supply."

Claes Westerlind, Executive Vice President and Head of the NKT high-voltage factory in Karlskrona, Sweden, said: "I am very satisfied that we continue the good collaboration with SSEN Transmission by leveraging our extensive experience within HVDC-technology to enable low-carbon power supply to Shetland."

Shetland is currently an 'islanded' electricity network, with all electricity met from on-island sources, primarily the diesel powered Lerwick Power Station.

The link will enable 600MW of clean, renewable electricity generation to connect - including the 457MW Viking Energy Wind Farm, which upon completion is set to be the UK's most productive onshore wind farm - supporting UK and Scottish net zero and energy security targets.

The Shetland HVDC Link project is on track to be completed by Summer 2024.

Latest Construction News

03/01/2025

Insurepair, the Edinburgh-based all trades insurance reinstatement specialist, is to launch an ambitious business strategy. The firm will invest £100,000 in new technology over the next 12 months. Insurepair will adopt CoreLogic's Symbility® platform, an industry-leading property insurance claim ...
03/01/2025

Kier has completed construction of a new surgical centre at NHS Golden Jubilee in Clydebank. The centre will increase the hospital's patient capacity and enable the treatment of thousands of people waiting for vital care and procedures. Scottish First Minister, John Swinney, visited the project ...
03/01/2025

Clark Contracts recently hosted a behind-the-scenes look at the major redevelopment works at Bught Park in Inverness. The main contractor is refurbishing the B-listed grandstand and constructing a new pavilion and shinty museum. Work is now focused on completing the pavilion's interior fit-out. ...
03/01/2025

CCG Group has officially opened a new 25,000 sq ft window and door manufacturing facility in Cambuslang. The facility is part of a wider £6 million investment by CCG. It will fabricate a range of enhanced window and door sets and employ 60 skilled workers. CCG has been manufacturing window and ...
03/01/2025

Work on a £50 million redevelopment of Aberdeen beachfront is set to begin in earnest after the festive break. Construction teams will be on site immediately after Christmas to start work on the first main features of the project. Aberdeen City Council's Co-Leaders have welcomed the move. The ...
03/01/2025

The iconic gasholder in north Edinburgh, now named 'Gas Holder 1', is now permanently illuminated after dark. Refurbishment on the structure, funded by the UK Government, is complete. The frame is now lit brightly in the twilight hours and will remain lit in festive colours throughout ...
02/01/2025

SSE has made a final investment decision to proceed with the construction of its 208MW Strathy South onshore wind farm in the Scottish Highlands. Located in north-east Sutherland, the wind farm has been in development for over a decade. Once completed, it is expected to generate enough renewable ...
02/01/2025

A range of organisations supporting vulnerable communities across Scotland have received funding from SP Energy Networks' Net Zero Fund. The grants will enable these groups to implement projects that decarbonise their operations and accelerate their journey towards net zero emissions. Projects ...
02/01/2025

The first phase of a £10 million project to upgrade a strategic sewer main between Renfrew and Glasgow has been completed. Nearly a kilometre of pipe running beneath King's Inch Road has been relined, creating a new pipe within the existing one. Robert Archer, Scottish Water Alliance Manager, ...
02/01/2025

Two new transformers have arrived at the Errochty Grid Supply Point in Highland Perthshire. This marks a significant milestone in the project to upgrade the electricity network in the region. The 90MVA 132/33kV transformers were transported to the site following a carefully planned operation that ...
RBT Underfloor LimitedMorris & Spottiswood LtdToner Damp Proofing SuppliesNo HydroMaccaferri LtdBurnside Plant Hire LtdM K M Building Supplies LtdAlternative Tying Systems LtdContainexPerthshire Joinery Ltd
Terms and Conditions
2025/01/05 19:31:30