Trams To Newhaven Project Enters Final Testing Stage

Construction News Image
The first tram has run down Leith Walk in Edinburgh in over 65 years as official testing got underway in the final stages of the Trams to Newhaven project.

Ahead of the route opening for service in spring 2023, a period of testing and commissioning is required to ensure the newly constructed line, software and signals work effectively and safely.

On Monday (13 March), the first stage of testing began, which involves trams travelling at walking pace along small sections of the route, starting at Picardy Place. This will continue through the week, taking place during the night to minimise traffic disruption.

Once the first stage is completed, the frequency and speed of tram testing will increase, and trams will start running to a timetable. Drivers on the route have carried out significant training in the lead-up to testing, including on a state-of-the-art simulator. People are still being encouraged to take care and be aware of the presence of trams on the route for the first time over the coming weeks.

Councillor Scott Arthur, Transport and Environment Convener, said: "This is a huge milestone for Trams to Newhaven as we see the first trams on Leith Walk in my lifetime. We’re fast approaching the start of passenger services this spring, and that the project is set to be delivered on time and within budget, despite the challenges of recent years, is testament to the hard work of all those involved.
-- Advertisement --
NorthernAsbestosServicesLtd



"Bringing the tram to Newhaven will be transformative for the area, and the wider city. As well as boosting the economy and providing sustainable, high-capacity public transport to this densely populated part of Edinburgh, the project has significantly improved the entire route, with new cycle links, spaces to relax and spend time and newly planted trees and shrubs.

"As we enter the final phase of the project, testing and commissioning will make sure the line and infrastructure works safely and efficiently, while also confirming service capacity. Of course, this is the first time there will be trams on Leith Walk and in Leith in recent years so I would urge people to take extra care when in the area."

Lea Harrison, Managing Director of Edinburgh Trams, said: "To see one of our trams running along Leith Walk was a proud moment for us, and this latest milestone in the project will enable us to step up our own preparations for the launch of passenger services to Newhaven.

"This includes real-world driver training on the new section of line following an intense period of familiarisation involving our state-of-the-art tram simulator."

The Trams to Newhaven project remains on schedule for completion by spring 2023 and within the £207.3m budget, with all major construction now complete. A specific date for when the route will be open for passengers will be announced in due course.

As part of the commissioning process every aspect of the new infrastructure will be thoroughly tested to ensure it meets the required safety standards.

There will be some bus diversions around Leith Walk in place overnight during the week commencing 13 March to allow for the testing. The latest information on diversions is available on the Lothian Buses website.

Due to industry wide challenges with the availability of materials and skilled labour, impacted by Brexit and the war in Ukraine along with significant demand for labour in the UK and overseas, there are small pockets of public realm works that will now be completed over the coming months.

Latest Construction News

16/04/2025
Construction work on the £5 million repair and refurbishment project at the Loch Centre in Tranent is scheduled to commence in June 2026. East Lothian Council has announced the anticipated start date for the significant upgrade to the well-used community facility. Under the current timetable, the
16/04/2025
A £636,000 project to install solar panels at the Gorbals water pumping station in South Ayrshire has been successfully completed. The scheme aims to provide a renewable energy source for pumping water to thousands of customers in the region. The project involved the installation of 793 solar pan
16/04/2025
A planning application has been lodged with Glasgow City Council by The JR Group, acting on behalf of Wheatley Group, for the construction of 29 much-needed affordable homes in the Baillieston area of the city. The proposed development on Caledonia Road will offer a mix of one- and two-bedroom apa
16/04/2025
Residents in 20 blocks of flats across Coatbridge are already experiencing the positive impacts of a recently completed, ambitious energy efficiency refurbishment project. The extensive construction work has delivered significant improvements to the properties, including the installation of cavity
16/04/2025
Ground investigation works are commencing this month at the proposed site for Orkney Islands Council’s Scapa Deep Water Quay at Deepdale in Holm. These initial investigations will be followed by marine-based site investigation works scheduled to begin in June. These works form part of the Pre-Con
16/04/2025
Construction work has been finalised on a significant new housing development in Motherwell town centre, delivering 42 newly built, highly energy-efficient flats alongside the respectful conversion of the B-Listed YMCA building into a further six homes. The project, part of North Lanarkshire Council
16/04/2025
The Construction Industry Training Board (CITB) has today released its year-end performance data for its New Entrant Support Team (NEST), revealing a significant increase in apprenticeship starts. During the financial year 2024-25, NEST supported 4,128 individuals in commencing apprenticeships, a su
16/04/2025
A water-powered mill in Angus is set to grind grain once again after receiving a record-breaking donation to fund its restoration. The National Trust for Scotland has announced that a long-time member of the conservation charity has gifted an incredible £2.4 million, one of the largest single dona
15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground. Drone footage has captured the progress of the project, which is a partnership between developer Artisa
15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond. The new connections system, anticip
Morris & Spottiswood LtdRBT Underfloor LimitedQuickFix Plumbing & HeatingScaffolding & Access Supplies LtdM L Contracts Scotland (Stone) LtdJJK RoofingHBB GeoSales LtdBM DecoratingGarage Floors DirectA.G.S Steel Erectors Ltd