Work Continues On £10m Islay Electricity Network Upgrade

Construction News Image
Some 292 new poles are to be installed across Islay to support almost 30km of new overhead line, as part of SSEN Distribution's £10m project to upgrade the electricity network.

Every pole has been given a number to indicate its position along the route, as well as being cut to a specific length to make sure the overall line has an aesthetic visual flow when viewed from afar.

And in addition to the new overhead infrastructure, Islay is also getting 12km of new underground High and Low Voltage cable, and a raft of new technology across the island's substations at Bowmore, Port Askaig, Port Ellen and Knocklearoch.

While the upgrade work will go a long way to reducing the potential for power cuts, there may still be occasions when a fault develops, or when storms may damage infrastructure, and with this in mind the work that SSEN is doing will enable engineers to restore supplies much more quickly, and minimise disruption for customers.

When the new overhead line is complete, the electricity network on Islay will be a complete loop for the first time - this will make a huge difference on the rare occasions there is a power cut, as it will allow SSEN's Control Centre engineers to temporarily re-route the affected supplies so that these customers are fed from a different part of the network, minimising the time they are off supply before the necessary repairs are carried out.
-- Advertisement --
NorthernAsbestosServicesLtd



SSEN Distribution and their principal contractor, Keltbray, set up a temporary project base at Ballygrant Quarry, where the poles were initially delivered and fitted with their cross arms (the metal bars which hold the lines) and signage.

Barry MacTaggart, SSEN's Project Manager, tells us more about the work that has been going on behind the scenes and the ways in which SSEN is minimising the environmental impact of building the new overhead line: "By using a helicopter to deliver these new poles along their 30km route, we're avoiding the need for lorries to cross the scenic, uninhabited, parts of Islay where there are no existing roads or tracks.

"As every pole was fitted with its cross arm and other livery before the helicopter picked it up and took its position on the route, this means that when colleagues go out to erect the poles, they only have to take the minimum amount of tools with them; they can also travel in smaller vehicles fitted with tracks rather than wheels – all of which minimises the environmental impact of our essential works."

SSEN's Head of Large Capital Delivery, Donald MacKinnon, explains more about the overall project and the benefits it will bring to homes and businesses on Islay: "We're committed to delivering a safe, secure and reliable supply of electricity to all our customers across Islay - this £10m investment covers a wide range of infrastructure upgrades and installations, all of which will bring a major boost the island's network.

"From the new overhead lines to the automated equipment we're installing in all four of Islay's primary substations, everything we're doing is designed to not only make the electricity infrastructure more robust and therefore less susceptible to power cuts, but also more flexible and adaptable, so we can restore supplies more quickly on the rare occasions the power is off.

"When it's completed in June 2024, all of this work will help upgrade the network for not just our existing customers, it will also ensure the reliability of power supplies across the island for many years to come."

Latest Construction News

16/04/2025
Construction work on the £5 million repair and refurbishment project at the Loch Centre in Tranent is scheduled to commence in June 2026. East Lothian Council has announced the anticipated start date for the significant upgrade to the well-used community facility. Under the current timetable, the
16/04/2025
A £636,000 project to install solar panels at the Gorbals water pumping station in South Ayrshire has been successfully completed. The scheme aims to provide a renewable energy source for pumping water to thousands of customers in the region. The project involved the installation of 793 solar pan
16/04/2025
A planning application has been lodged with Glasgow City Council by The JR Group, acting on behalf of Wheatley Group, for the construction of 29 much-needed affordable homes in the Baillieston area of the city. The proposed development on Caledonia Road will offer a mix of one- and two-bedroom apa
16/04/2025
Residents in 20 blocks of flats across Coatbridge are already experiencing the positive impacts of a recently completed, ambitious energy efficiency refurbishment project. The extensive construction work has delivered significant improvements to the properties, including the installation of cavity
16/04/2025
Ground investigation works are commencing this month at the proposed site for Orkney Islands Council’s Scapa Deep Water Quay at Deepdale in Holm. These initial investigations will be followed by marine-based site investigation works scheduled to begin in June. These works form part of the Pre-Con
16/04/2025
Construction work has been finalised on a significant new housing development in Motherwell town centre, delivering 42 newly built, highly energy-efficient flats alongside the respectful conversion of the B-Listed YMCA building into a further six homes. The project, part of North Lanarkshire Council
16/04/2025
The Construction Industry Training Board (CITB) has today released its year-end performance data for its New Entrant Support Team (NEST), revealing a significant increase in apprenticeship starts. During the financial year 2024-25, NEST supported 4,128 individuals in commencing apprenticeships, a su
16/04/2025
A water-powered mill in Angus is set to grind grain once again after receiving a record-breaking donation to fund its restoration. The National Trust for Scotland has announced that a long-time member of the conservation charity has gifted an incredible £2.4 million, one of the largest single dona
15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground. Drone footage has captured the progress of the project, which is a partnership between developer Artisa
15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond. The new connections system, anticip
RBT Underfloor LimitedMorris & Spottiswood LtdHBB GeoSales LtdBM DecoratingGarage Floors DirectA.G.S Steel Erectors LtdRobinsons GroupCrown Street Lighting LtdArdent Consulting EngineersPlanning Handbook