Construction News
06/02/2023
Leith Walk Tram Line Electrification Set To Begin
The City of Edinburgh Council has announced the return of two-way traffic to Leith Walk, as preparations for tram testing begins.
North- and southbound traffic along the length of Leith Walk will be reintroduced during the week commencing 13 February, followed by the electrification of the full line.
Energisation of the line will allow for testing and commissioning to begin, with the first test trams expected on the route at the beginning of March. Final track preparations will also take place in the lead up to the first test tram running.
All tram track, overhead line poles and communications and power ducting has been installed, 93% of the overhead lines are in place and the final section at Picardy Place is being installed over the next two weeks.
Councillor Scott Arthur, Transport and Environment Convener, said: "In just a matter of weeks we'll see test trams running the length of the Trams to Newhaven route, which is really exciting. Energising the overhead lines and buffering of the tram tracks are the final steps before this happens.
"Reopening Leith Walk to two-way traffic is a key moment for the project too and, I'm sure, for all those who live and work in the area. I'd like to thank residents and businesses for their patience and support while we've carried out these works.
"Once fully complete, this project will be transformative for Leith Walk and the rest of the route, while benefitting the wider city economy and helping to cut congestion. Not only will it provide reliable, high-capacity connections to the north of the city but has significantly improved and enhanced public spaces and active travel links along the line."
The Trams to Newhaven project remains on schedule for completion by spring 2023 and within the £207.3m budget, with all major construction now complete ahead of the testing and commissioning period.
However, due to industry wide challenges with the availability of materials and skilled labour, impacted by Brexit and the war in Ukraine along with significant demand for labour in the UK and overseas, there are small pockets of public realm works that will now be completed over the coming months. Full details of the updated programme are available on the Trams to Newhaven website.
A communications campaign has been carried out to remind residents, businesses and stakeholders about the electrification of overhead lines, including safety requirements and permits needed to carry out any work. This work was originally scheduled to take place in October but was re-programmed to allow key infrastructure works to be completed.
To allow for work to connect the lines to take place, Edinburgh Trams services from the airport will terminate at the West End between 13 and 19 February.
North- and southbound traffic along the length of Leith Walk will be reintroduced during the week commencing 13 February, followed by the electrification of the full line.
Energisation of the line will allow for testing and commissioning to begin, with the first test trams expected on the route at the beginning of March. Final track preparations will also take place in the lead up to the first test tram running.
All tram track, overhead line poles and communications and power ducting has been installed, 93% of the overhead lines are in place and the final section at Picardy Place is being installed over the next two weeks.
Councillor Scott Arthur, Transport and Environment Convener, said: "In just a matter of weeks we'll see test trams running the length of the Trams to Newhaven route, which is really exciting. Energising the overhead lines and buffering of the tram tracks are the final steps before this happens.
"Reopening Leith Walk to two-way traffic is a key moment for the project too and, I'm sure, for all those who live and work in the area. I'd like to thank residents and businesses for their patience and support while we've carried out these works.
"Once fully complete, this project will be transformative for Leith Walk and the rest of the route, while benefitting the wider city economy and helping to cut congestion. Not only will it provide reliable, high-capacity connections to the north of the city but has significantly improved and enhanced public spaces and active travel links along the line."
The Trams to Newhaven project remains on schedule for completion by spring 2023 and within the £207.3m budget, with all major construction now complete ahead of the testing and commissioning period.
However, due to industry wide challenges with the availability of materials and skilled labour, impacted by Brexit and the war in Ukraine along with significant demand for labour in the UK and overseas, there are small pockets of public realm works that will now be completed over the coming months. Full details of the updated programme are available on the Trams to Newhaven website.
A communications campaign has been carried out to remind residents, businesses and stakeholders about the electrification of overhead lines, including safety requirements and permits needed to carry out any work. This work was originally scheduled to take place in October but was re-programmed to allow key infrastructure works to be completed.
To allow for work to connect the lines to take place, Edinburgh Trams services from the airport will terminate at the West End between 13 and 19 February.
30/01/2025
Scottish Water has officially launched its groundbreaking hydro scheme at Whiteadder Reservoir in East Lothian. The project, believed to be the first of its kind in Europe, will generate renewable energy to offset nearly a third of the power used by the Hungry Snout pumping station, which supplies d
30/01/2025
Built Environment–Smarter Transformation (BE-ST) in Glasgow has been awarded a €219,000 grant from Built by Nature to lead research into fire safety in mass timber buildings across the UK.
The grant responds directly to the UK Government's 2023 Timber in Construction Roadmap, which called for resea
30/01/2025
Construction is underway on the transformation of Dundee's Bell Street multi-storey car park into a £25.4 million green transport hub.
The project, funded by £14.4 million from the UK Government's Levelling Up Fund and an £11 million tender recently approved by the city council, follows £4.5 milli
30/01/2025
Forth Ports has submitted planning applications to The City of Edinburgh Council for the second phase of its Harbour 31 regeneration project in Leith. The applications seek Detailed Planning Consent and Listed Building Consent for "The Dry Dock at Harbour 31," a proposed creative and commercial hub
30/01/2025
Construction has officially commenced on The R&A's new Global Headquarters at St Andrews West. David Rickman MBE, former R&A executive, broke ground at a ceremony marking the start of the project.
The new headquarters, slated for completion in 2026, will consolidate St Andrews-based R&A staff into
30/01/2025
Clackmannanshire Council has approved a £14 million investment in its housing stock for the upcoming financial year. The decision was made at today's Council meeting, where councillors also agreed to a 10% increase in base rent and a new rental structure.
The new structure will result in 72% of ten
30/01/2025
St Andrews Timber & Building Supplies has announced the expansion of its Livingston branch with the addition of a new machine shop.
The 500m2 facility features a wall saw and a crosscut saw, with plans to introduce another four machines such as a pillar drill, planer and spindle moulder.
The servi
30/01/2025
A major refurbishment project is planned for the bridge carrying the B792 local road over the M8 motorway between Bathgate and Blackburn. Work is scheduled to begin in spring 2025 and is expected to last approximately four months.
The project will involve a range of repairs, including steelwork and
30/01/2025
Scotland's first floating solar power system, located at Forth Ports HQ in the Port of Leith, successfully weathered Storm Éowyn, described by the Met Office as "probably the strongest to hit the UK in the past 10 years".
Despite hurricane-strength winds and widespread disruption caused by the stor
30/01/2025
Paisley-based construction company, The JR Group, has committed to supporting social enterprises by signing the Social Enterprise Scotland Buy Social Pledge.
The initiative connects private businesses, SMEs, academic institutions, and public sector bodies with social enterprises, encouraging them t