06/02/2023

Major Milestone In Alyth Substation Development

Construction News Image
SSEN Transmission has welcomed a major milestone in the ongoing construction of their new Alyth Substation, with the delivery of a new transformer unit.

The new Static Compensating Transformer (SCT) unit, weighing around 120 tonnes, is a key component in the ongoing development of the substation, which will play a major role in helping to support the connection of new renewable generation in the north of Scotland to the grid and enabling clean energy to be taken from where it is generated to where it is needed.

Teams from SSEN Transmission and principal contractor Siemens BAM have been working since construction began in April 2021 to coordinate a safe delivery and arrival of the key component to the substation, which once installed will help manage the flow of energy across the network.

The specialist transformer unit is being shipped to Dundee quay before being transported to its final location at the new Alyth substation overnight on Saturday 11 February.

To help minimise disruption to local residents, businesses and road users and ensure the transformer unit arrives safely, specialist haulier Allelys has been appointed to transport the unit via convoy using a large 12-axle specialist vehicle under the guidance and supervision of Police Scotland. The transformer convoy will depart from Dundee quay at 7pm on Saturday 11 February under Police Scotland escort and make its way to Alyth substation via the A90 Kingsway East, A94 and B954.
-- Advertisement --
NorthernAsbestosServicesLtd



Once arrived at the B954 junction with Balendoch Road, the transformer will be transferred from the 24-axle trailer to a 12-axle trailer and sit overnight. For safety, the junction with Balendoch Road on the B954 will remain closed. At 9am on Sunday 12 February it will then be transported along the U100 to the substation site, allowing the B954 to reopen as before.

Due the transformer's size, the delivery vehicles will be travelling at a reduced speed for safety, and the journey from Dundee to the overnight stop at the B954 is expected to take up to six hours. Vehicles should be able to pass the convoy at regular opportunities on the road network under guidance from Police Scotland, when safe to do so.

SSEN Transmission Lead Project Manager Archie Munro said: "We're gearing up for the arrival of our 120-tonne SCT transformer – one of the largest components in the Alyth substation project – which marks a major milestone in the construction of this key project on SSEN Transmission's east coast network.

"The transformer will ultimately enable and manage the flow of energy through the substation and overall network, and it will help accommodate increased renewable generation from across the north of Scotland.

"We've taken steps to limit any disruption as much as possible by scheduling the delivery to take place overnight and have been regularly engaging with the local community and stakeholders to advise them of our plans in advance.

"The complex delivery has been carefully coordinated by our project teams, working with the specialist haulier, Allelys, as well as Dundee Council and Police Scotland, to ensure disruption can be kept to a minimum for the local community and road users in the area.

"We would like to take this opportunity to thank the local community in advance for their patience and understanding while we transport the transformer to its final location in Alyth."

The construction of the Alyth substation is part of a wider scheme to upgrade the East Coast transmission network. Once complete it will enable the connection of new renewable generation to the grid, helping to facilitate the transmission to net zero emissions. The project at Alyth is on course to be completed later this year.

Latest Construction News

16/04/2025
Construction work on the £5 million repair and refurbishment project at the Loch Centre in Tranent is scheduled to commence in June 2026. East Lothian Council has announced the anticipated start date for the significant upgrade to the well-used community facility. Under the current timetable, the
16/04/2025
A £636,000 project to install solar panels at the Gorbals water pumping station in South Ayrshire has been successfully completed. The scheme aims to provide a renewable energy source for pumping water to thousands of customers in the region. The project involved the installation of 793 solar pan
16/04/2025
A planning application has been lodged with Glasgow City Council by The JR Group, acting on behalf of Wheatley Group, for the construction of 29 much-needed affordable homes in the Baillieston area of the city. The proposed development on Caledonia Road will offer a mix of one- and two-bedroom apa
16/04/2025
Residents in 20 blocks of flats across Coatbridge are already experiencing the positive impacts of a recently completed, ambitious energy efficiency refurbishment project. The extensive construction work has delivered significant improvements to the properties, including the installation of cavity
16/04/2025
Ground investigation works are commencing this month at the proposed site for Orkney Islands Council’s Scapa Deep Water Quay at Deepdale in Holm. These initial investigations will be followed by marine-based site investigation works scheduled to begin in June. These works form part of the Pre-Con
16/04/2025
Construction work has been finalised on a significant new housing development in Motherwell town centre, delivering 42 newly built, highly energy-efficient flats alongside the respectful conversion of the B-Listed YMCA building into a further six homes. The project, part of North Lanarkshire Council
16/04/2025
The Construction Industry Training Board (CITB) has today released its year-end performance data for its New Entrant Support Team (NEST), revealing a significant increase in apprenticeship starts. During the financial year 2024-25, NEST supported 4,128 individuals in commencing apprenticeships, a su
16/04/2025
A water-powered mill in Angus is set to grind grain once again after receiving a record-breaking donation to fund its restoration. The National Trust for Scotland has announced that a long-time member of the conservation charity has gifted an incredible £2.4 million, one of the largest single dona
15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground. Drone footage has captured the progress of the project, which is a partnership between developer Artisa
15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond. The new connections system, anticip
Morris & Spottiswood LtdRBT Underfloor LimitedWalshy JoinerySips Eco Panel Systems LtdDMC VisualsContainexHutton Stone Co LtdQuickFix Plumbing & HeatingScaffolding & Access Supplies LtdM L Contracts Scotland (Stone) Ltd