Network Rail has announced the completion of a milestone in a £6.8 million programme of enhancement works near Perth station.
The project is part of ongoing investment by the Scottish Government in Scotland's Railway that will help reduce rail journey times between the Central Belt and the North East, improve connectivity and enhance capacity for both passenger and freight trains.
Starting in March 2022, this initial phase involved track work east of Perth station at Barnhill, historically a constrained section of the route next to the River Tay.
Working with contractor the Rail Systems Alliance, Network Rail undertook a nine-month programme of alignment work to replace a curved section of track by installing a new single line and also remodelling the junction by replacing switches and crossings. This allows an increase in line speed for trains from 20mph to 50mph on this part of the route
Speeding up journey times also improves capacity for more freight services to be introduced to the network.
Chris Sharkey, Network Rail programme manager, said: "Completion of work at Barnhill represents a significant part of enhancement work that provides tangible benefits for our passengers and freight customers.
"Ultimately, the work enables smoother, faster journey times and more resilience on the network, particularly during times of disruption.
"This was a challenging location to work in, given it is constricted by the existing railway infrastructure and I'm delighted the team achieved this key milestone on time.
"I would like to thank our lineside neighbours at Barnhill for their patience during the delivery of this vital improvement work to Scotland's Railway."
Damian Briody, Transport Scotland's head of rail projects and technical services, said: "This latest Scottish Government investment in Scotland's Railway is another example of our efforts to reduce journey times on this important route between the north east and the Central Belt.
"These enhancements will improve connectivity for both passenger and freight services which, in turn, will help encourage more people out of their cars and more companies to opt for rail freight over road transportation."
With work at Barnhill complete, the team is focused on the next phase of activity - installing a new cross over south of Dunblane station to further improve operational resilience.
The existing turnback facilities for trains at Dunblane constrain the timetable and network resilience in this location. By installing the new cross over, this will help eliminate these issues by reducing the time is takes for a train to move up the line and significantly improve the diversionary capability when work is completed in advance of the May 2024 timetable.
Construction News
27/01/2023
Major Milestone In £6.8m Perth Station Enhancement Works


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont