West Coast Mainline Emergency Engineering Works Complete

Construction News Image
Network Rail has announced that emergency engineering works to fix flood-damage to the West Coast Mainline near Carstairs have now been completed.

Engineers have been working around-the-clock to repair and reopen the line since heavy rain on December 30 caused a landslip beneath the tracks – destabilising the foundations of the railway.

Over the last week, work has been undertaken to remove hundreds of tonnes of loose material from beneath the line, regrade the slopes and install over 300 tonnes of new stone to stabilise the embankment.

The track has also been relaid and signalling systems tested ahead of the line reopening on Friday.

Liam Sumpter, Network Rail Scotland route director, said: "Our engineers have worked as quickly as possible to complete these repairs and reopen the railway.

"This was a very challenging project, with hundreds of tonnes of material having to be removed and significant repairs made to over 40 metres of the railway.
-- Advertisement --
NorthernAsbestosServicesLtd



"We appreciate the inconvenience the closure of the line has caused and we thank everyone for their understanding during these recovery works."

Barry Milsom, executive director of operations and safety at Avanti West Coast, said: "We're pleased the West Coast Mainline has now reopened north of Carlisle following repairs to the tracks and would like to thank our customers for their patience and understanding while Network Rail carried out this urgent work.

"While our services to and from Glasgow can resume on Friday 6 January, a significantly reduced timetable will be in place on this day, as well as Saturday 7 January due to strike action. Therefore, we strongly encourage customers travelling to and from Scotland to make their journeys on Sunday 8, Monday 9 or Tuesday 10 January when we'll be operating our full timetable.

"If you're no longer able to travel, you can claim a full fee-free refund from where you bought your ticket. For the latest updates about your journey, please check www.avantiwestcoast.co.uk before travelling."

Passengers planning to travel south on strike dates should check their journey before travelling at www.nationalrail.co.uk/ or with their individual train operator.

The line has now reopened for passenger trains but customers are being urged only to travel if their journey is essential as services on the line will be severely limited by ongoing RMT strike action.

Latest Construction News

16/04/2025
Construction work on the £5 million repair and refurbishment project at the Loch Centre in Tranent is scheduled to commence in June 2026. East Lothian Council has announced the anticipated start date for the significant upgrade to the well-used community facility. Under the current timetable, the
16/04/2025
A £636,000 project to install solar panels at the Gorbals water pumping station in South Ayrshire has been successfully completed. The scheme aims to provide a renewable energy source for pumping water to thousands of customers in the region. The project involved the installation of 793 solar pan
16/04/2025
A planning application has been lodged with Glasgow City Council by The JR Group, acting on behalf of Wheatley Group, for the construction of 29 much-needed affordable homes in the Baillieston area of the city. The proposed development on Caledonia Road will offer a mix of one- and two-bedroom apa
16/04/2025
Residents in 20 blocks of flats across Coatbridge are already experiencing the positive impacts of a recently completed, ambitious energy efficiency refurbishment project. The extensive construction work has delivered significant improvements to the properties, including the installation of cavity
16/04/2025
Ground investigation works are commencing this month at the proposed site for Orkney Islands Council’s Scapa Deep Water Quay at Deepdale in Holm. These initial investigations will be followed by marine-based site investigation works scheduled to begin in June. These works form part of the Pre-Con
16/04/2025
Construction work has been finalised on a significant new housing development in Motherwell town centre, delivering 42 newly built, highly energy-efficient flats alongside the respectful conversion of the B-Listed YMCA building into a further six homes. The project, part of North Lanarkshire Council
16/04/2025
The Construction Industry Training Board (CITB) has today released its year-end performance data for its New Entrant Support Team (NEST), revealing a significant increase in apprenticeship starts. During the financial year 2024-25, NEST supported 4,128 individuals in commencing apprenticeships, a su
16/04/2025
A water-powered mill in Angus is set to grind grain once again after receiving a record-breaking donation to fund its restoration. The National Trust for Scotland has announced that a long-time member of the conservation charity has gifted an incredible £2.4 million, one of the largest single dona
15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground. Drone footage has captured the progress of the project, which is a partnership between developer Artisa
15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond. The new connections system, anticip
Morris & Spottiswood LtdRBT Underfloor LimitedGlasgow Architectural SalvageMatheson Damp Services LtdScotdeck LtdSELECTA GLASGOW LIMITEDCommercial Transmissions GroupWestermans International LtdHugh Simpson (Contractors) LtdTennants (Elgin) Ltd