Exploratory works at the site of what would be the UK's first large-scale pumped storage scheme to be developed in 30 years have commenced at Loch Lochy in the Great Glen in the Scottish Highlands.
SSE Renewables selected Strabag UK, a world leader in mining and tunnelling projects, to undertake the work earlier this year. The company which has extensive experience in complex infrastructure and ground engineering, was named the preferred tenderer to carry out the work after a rigorous selection process which concluded in April.
The work will see the creation of a tunnel approximately four metres wide and up to one kilometre long, which will cut into the hillside towards the proposed location of the underground powerhouse complex.
Samples of the materials within the hill will be analysed, and survey and assessment work will be carried out to give a detailed understanding of the geological conditions. The information will then be used in detailed design of underground structures.
The findings of the exploratory works will be used to inform the final design of the project and will be an important consideration in SSE Renewables' final decision on whether to proceed with the Coire Glas project.
Ian Innes, Project Director For Coire Glas, said: "Coire Glas is one of the most significant engineering projects to take place in the UK for decades. The commencement of these exploratory works is a great milestone for everyone on the Coire Glas Project Team and at SSE Renewables.
"With a reputation for innovation and delivering a wide variety of specialist skills and services on major construction projects, I am confident that Strabag UK's experience will prove an asset as we undertake this critical phase in the development of the Coire Glas project."
In November 2021, SSE Renewables' parent company, SSE PLC unveiled its Net Zero Acceleration Programme, or NZAP, which commits to investing around £7m a day on critical low-carbon infrastructure needed in net zero transition.
Major infrastructure projects including Coire Glas are at the heart of the NZAP with a target to double our installed capacity by 2026 and more than treble it by 2031, increasing output fivefold to over 50TWh annually. The fully funded NZAP will see 40% of the £12.5bn capex spent in SSE Renewables.
Time and date
CONSTRUCTION DIRECTORY
Construction News
14/12/2022
Loch Lochy Pumped Storage Scheme Exploratory Works Underway
Latest Construction News
22/11/2024
SP Energy Networks has announced a major investment in Britain's electricity grid, selecting 19 preferred partners to deliver a £5.4bn supply chain programme. This significant initiative aims to meet increasing energy demand and facilitate future growth. The selected companies, many of which are ...
22/11/2024
Edinburgh City Council has launched a 12-week public consultation on a new strategy to revitalise Princes Street and the wider Waverley Valley. The vision aims to create a more vibrant and welcoming city centre, attracting investment, supporting businesses, and enhancing the visitor ...
22/11/2024
Ener-G Services Limited, a leading UK electrical engineering company specialising in renewables, marine, and offshore sectors, has expanded its operations in Westhill, Aberdeenshire. The company has leased Unit 6E at Kingshill Commercial Park, a 2,500 sq ft space, on a 5-year lease. This new ...
22/11/2024
A consortium of leading scientists, industry experts, and academic institutions has joined forces to accelerate Scotland's offshore wind sector. The £2.5 million project, led by the University of Edinburgh in collaboration with the University of Dundee and the Forth and Tay Offshore cluster (FTO), ...
22/11/2024
The Port of Aberdeen and Turner & Townsend were highly commended in the 'Engineering, Construction & Infrastructure Project of the Year' category at the APM Project Management Awards 2024. The award recognises excellence in project management and the positive impact on end-users. The £420 million ...
22/11/2024
South Lanarkshire Council's £10 million fire safety improvement programme has reached a significant milestone, with CCG (Scotland) completing installations in over 1,700 high-rise residences across East Kilbride and Cambuslang. The Glasgow-based construction firm has been working closely with the ...
22/11/2024
SSEN Transmission, a key player in the UK's energy transition, is set to further expand its workforce and move into a new, sustainable office space in Glasgow. The company's commitment to net zero and the increasing demand for green energy workers has led to significant growth, with the number of ...
22/11/2024
Scottish Water is investing in the upgrade of its Loch Eck clean water plant in Dunoon. The project involves replacing outdated dry well pumps with new, more reliable pumps capable of operating in both wet and dry conditions. WGM Engineering, an RSK Group company, has been tasked with carrying out ...
22/11/2024
Scottish Land & Estates has expressed serious concerns over the Scottish Government's Land Reform Bill, particularly the provisions that would allow ministers to force landowners to sell large estates in lots. Sarah-Jane Laing, the organisation's chief executive, stated that while the land-based ...
22/11/2024
Clark Contracts employees have once again shown their commitment to community engagement by volunteering at Silverburn Park in Leven. On Thursday, 21st November, 16 members of the team spent their day planting over 400 trees and carrying out other landscaping tasks. This latest volunteering effort ...