SSEN Distribution has announced that construction is now underway at Gremista on infrastructure which will see Shetland's local electricity network connected to the main GB grid.
The Gremista site is a key part of SSEN Distribution's £99.8m overall investment in this historic project, and will see the distribution and transmission networks connected at a new substation – known as a Grid Supply Point (GSP).
SSEN Distribution has appointed island-based Tulloch Developments as its principal contractor for these works, with the overall project boosting the reliability of electricity supplies for homes and business on Shetland as well as supporting the country's drive to net zero, with a dramatic drop in carbon emissions as the community moves away from the current reliance on fossil-fuel generation.
Construction teams started on site earlier this week, and this part of the project is expected to run through to early summer 2023, after which the site will be handed over to SSEN Transmission to complete the civils and electrical works required to connect the GSP to the transmission and distribution networks.
Construction will be carried out in two phases, with Phase One details below:
Phase One: Civil earthworks and drainage
Working hours:
• Monday to Friday - 7am to 7pm
• Saturday - 9am to 6pm
• Sunday - 10am to 5pm
No rock-breaking or crushing will occur before 9.30am on Sundays.
• Blasting operations will be restricted to 8am to 6pm Monday to Friday, and Saturday 8am to 3pm
• No blasting on Sunday
• Haulage movements to and from Staneyhill Quarry down the A970 to Gremista GSP will be restricted at weekends to between 8am and 6pm Saturday, and 8am to 5pm Sunday
As Phase Two will begin shortly before the handover to SSEN Transmission, further details will be announced nearer the time.
Mark Kelly, who is SSEN Distribution's Project Director, said: "Commencing work on the Grid Supply Point is a major milestone - not just for ourselves on the project, but also for the wider Shetland community - as this site is a key part of the islands being connected to the mainland GB network.
"SSEN Distribution has a fantastic longstanding relationship with the Shetland communities. This project has seen years of planning and consultations with the wider public, local stakeholders and landowners, and I'd like to thank Shetland Islands Council and Lerwick Port Authority for their support in the lead up to construction starting earlier this week.
"And we're delighted to be working with Tulloch Developments on such a significant project. As a Shetland-based company, we believe their local knowledge, combined with over 40 years of experience, will help us to deliver the Grid Supply Point safely, on schedule and with the minimum impact on people's day-to-day lives."
Joe Smith, Director at Tulloch Developments, said: "Working with SSEN Distribution is great news for everyone here at Tulloch Developments. We're a local company with over 40 years of experience working across Shetland, and so we're proud to be part of this major project, which will lead to us all being connected to the mainland GB electricity network."
Construction News
02/12/2022
Shetland Grid Supply Point Infrastructure Works Underway


15/04/2025
Construction of a £70 million student accommodation development at 292-298 St Vincent Street in Glasgow has reached a significant milestone, with the building now visibly rising from the ground.
Drone footage has captured the progress of the project, which is a partnership between developer Artisa

15/04/2025
Energy regulator Ofgem is expected to confirm today (April 15) its finalised Connections Reform process, designed to expedite grid connections for renewable energy projects that are ready and crucial for achieving the UK's clean power targets for 2030 and beyond.
The new connections system, anticip

15/04/2025
The ambitious transformation of Glasgow’s landmark George Square has moved into a tangible phase with the commencement of the erection of hoardings around the perimeter of the civic space. Starting today, the hoardings will enclose the Square for the duration of its 18-month redevelopment.
The pane

15/04/2025
Members of the public are invited to attend a consultation feedback event to discuss the proposed infrastructure associated with a new underground electricity transmission cable between the Kinardochy and Errochty substations in Perthshire.
The event will take place on Monday, 28 April, from 4 pm t

15/04/2025
Turner & Townsend have been appointed as project managers to develop a business case for the potential extension of the Borders Railway beyond its current terminus at Tweedbank to Hawick and Carlisle.
This key appointment will enable crucial work to progress on the project, including feasibility s

15/04/2025
Arran Community Renewables, a Community Benefit Society based on the Isle of Arran, has secured planning consent for a 6 MW solar farm. The Glenkiln Solar Farm, located approximately 1km west of Lamlash, is projected to generate 5,600MWh of clean renewable energy annually from 2027.
The £5 million

15/04/2025
A new Route Map has been published by the Scottish Land Commission (SLC) to ensure communities across Scotland secure tangible and long-lasting benefits from nature restoration projects and investment in the country's natural environment.
The practical guide is designed for landowners, developers,

15/04/2025
Award-winning principal contractor Procast Group has further expanded its presence across Scotland with the opening of a new base in Dumfries. The Hamilton-based firm has invested £30,000 in a new warehouse and office facility in the Maxwelltown Industrial Estate in Dumfries and Galloway, marking it

14/04/2025
Glasgow City Council's Affordable Housing Supply Programme (AHSP) facilitated the completion of over 1,000 new affordable homes in the city during the past year, despite facing budgetary reductions at the start of the financial year.
The initial grant of £78.687 million from the Scottish Government

14/04/2025
A key phase of Scottish Water's £11.5 million project to upgrade a strategic rising sewer main connecting Renfrew and Glasgow is set to begin, resulting in a significant road closure.
From Monday, 28 April 2025, Ferry Road in Renfrew will be closed to all vehicular traffic for a period of four mont