SSEN Transmission has reached a major milestone in the ongoing development of their multi-million-pound powerline construction between Port Ann and Crossaig, with over half of the 148 towers now in place.
The 148 steel lattice towers are part of the new electrical transmission overhead line which will replace the existing infrastructure in the area, which was originally built in the 1950s and is now reaching the end of its operating life. The new replacement powerline is one of the most significant electricity network investments in the region in decades and will provide a new robust and reliable transmission network in the area.
The process of installing the towers involves creating a robust foundation at each tower location, which is followed by erecting the steel lattice frames of the tower in sections using a large crane. The crane manoeuvres each section into position, and a team of engineers, harnessed to the towers, fix and anchor each piece into position. So far 75 of the 148 towers are fully erected, with the remaining 73 expected to be completed by spring next year.
Once the towers are installed, a total of 270km of overhead line wires will be pulled into position on the towers between Lochgilphead and Crossaig. Since September, over 70km of wires have already been installed, by teams using a combination of helicopters and large conductor pulling machinery.
The project is the second phase in the wider Inveraray to Crossaig powerline upgrade, with the first phase – Inveraray to Port Ann – energised in July 2021. Since then, teams have been working to reinstate the land and some of the access areas used in construction for the first phase.
The Inveraray to Crossaig overhead line will operate at 132kV, with the capacity to be upgraded to 275kV in the future, forming a key part of SSEN Transmission's Argyll 275kV strategy to create a safe and reliable network in the region.
Peter Brum, SSEN Transmission Project Manager said: "We're really pleased to reach this major milestone in the ongoing construction of the replacement line between Port Ann and Crossaig, with over half of the new reinforced steel towers now in position and ready for wiring.
"We have highly skilled teams involved in this project, and together they are making great progress in the overall delivery of this scheme even though they have faced some challenging autumnal conditions in the past few months. Despite these conditions, they have completed three quarters of the total tower foundation installations, along with the first 70km of wiring completed, and we're on track to see the new line energised in summer next year.
"As a responsible developer it is really important to us that we continue to work with the community and keep them updated on this important project as we progress. We thank them for their continued patience and understanding as we deliver this critical national infrastructure project which will serve the region for many decades to come."
The Inveraray to Crossaig overhead line reinforcement project is split into two phases. Phase one, Inveraray to Port Ann, was energised in July 2021, with Phase Two, Port Ann to Crossaig, expected to be energised in 2023 with works fully completed in early 2024.
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
03/01/2025
Insurepair, the Edinburgh-based all trades insurance reinstatement specialist, is to launch an ambitious business strategy. The firm will invest £100,000 in new technology over the next 12 months. Insurepair will adopt CoreLogic's Symbility® platform, an industry-leading property insurance claim ...
03/01/2025
Kier has completed construction of a new surgical centre at NHS Golden Jubilee in Clydebank. The centre will increase the hospital's patient capacity and enable the treatment of thousands of people waiting for vital care and procedures. Scottish First Minister, John Swinney, visited the project ...
03/01/2025
Clark Contracts recently hosted a behind-the-scenes look at the major redevelopment works at Bught Park in Inverness. The main contractor is refurbishing the B-listed grandstand and constructing a new pavilion and shinty museum. Work is now focused on completing the pavilion's interior fit-out. ...
03/01/2025
CCG Group has officially opened a new 25,000 sq ft window and door manufacturing facility in Cambuslang. The facility is part of a wider £6 million investment by CCG. It will fabricate a range of enhanced window and door sets and employ 60 skilled workers. CCG has been manufacturing window and ...
03/01/2025
Work on a £50 million redevelopment of Aberdeen beachfront is set to begin in earnest after the festive break. Construction teams will be on site immediately after Christmas to start work on the first main features of the project. Aberdeen City Council's Co-Leaders have welcomed the move. The ...
03/01/2025
The iconic gasholder in north Edinburgh, now named 'Gas Holder 1', is now permanently illuminated after dark. Refurbishment on the structure, funded by the UK Government, is complete. The frame is now lit brightly in the twilight hours and will remain lit in festive colours throughout ...
02/01/2025
SSE has made a final investment decision to proceed with the construction of its 208MW Strathy South onshore wind farm in the Scottish Highlands. Located in north-east Sutherland, the wind farm has been in development for over a decade. Once completed, it is expected to generate enough renewable ...
02/01/2025
A range of organisations supporting vulnerable communities across Scotland have received funding from SP Energy Networks' Net Zero Fund. The grants will enable these groups to implement projects that decarbonise their operations and accelerate their journey towards net zero emissions. Projects ...
02/01/2025
The first phase of a £10 million project to upgrade a strategic sewer main between Renfrew and Glasgow has been completed. Nearly a kilometre of pipe running beneath King's Inch Road has been relined, creating a new pipe within the existing one. Robert Archer, Scottish Water Alliance Manager, ...
02/01/2025
Two new transformers have arrived at the Errochty Grid Supply Point in Highland Perthshire. This marks a significant milestone in the project to upgrade the electricity network in the region. The 90MVA 132/33kV transformers were transported to the site following a carefully planned operation that ...